EORs: Let’s Call The Whole Thing Off

I stress this is a personal view. Others may differ.

As Ella Fitzgerald said in that song:

“For you like this and the other

While I go for this and that

Goodness knows what the end will be

…

Let’s call the whole thing off””

And more recently Ashe:

“This isn’t cold feet, these aren’t fireworks

The sky is menacing and that’s an iceberg

…

Stop the wedding!”

My personal view:

It’s never too late to abandon the longstanding, not yet delivered, still vague, still without proof of concept, idea of replacing environmental impact assessment and strategic environmental assessment with “environmental outcomes reports”.

One of the benefits arising from that 2016 Brexit vote – more innocent times perhaps – was said to be that departure would allow us to construct a more proportionate, effective and efficient version of environmental assessment.

Ten years on, can we perhaps be honest with ourselves? It’s not going to happen, folks! Has there been any evidence over the last ten years of this country replacing any process with one that is simpler and more effective? We’re at least as good at inventing unnecessary complexity as any EU bureaucrat or judge. And wouldn’t it be ironic if we finally chose to depart from that EU assessment structure just at the time that the government is contemplating greater regulatory alignment with the EU in certain areas? Whilst much depends on the form that any “realignment” (what a nothing word) takes, the government should surely not at this point be introducing new divergences without good reason. And I see no clamour at all for EORs.

The legislative framework for environmental outcomes reports was first introduced in May 2022 by way of Part 6 of the Levelling-up and Regeneration Bill, with no detail at that stage as to the form that EORs would actually take. It seemed to me to be an expression or desire, in search of a methodology. The previous government consulted on the possible principles in March 2023 – see my 25 March 2023 blog post Join The Club/Environmental Outcomes Reports for my commentary at the time.

The Bill then became an Act in October 2023, with regulation-making powers for Part 6 in force from December 2023.

Then nothing until the July 2024 general election and in December 2024 Matthew Pennycook’s Commons statement Development and the Environment which confirmed that the government’s new approach in relation to these matters “ would be supported by the new framework of Environmental Outcomes Reports (EORs) that will replace the current systems of environmental assessment with a more effective and outcome-focused tool for managing the effects of development on the natural environment.”

Roll forward to 13 March 2026 and the Government finally publishes its response to the previous government’s March 2023 consultation process, together with Environmental Outcomes Reports: Roadmap to reform (no not that reform). The roadmap sets out the phases of work now to be carried out and you will see that there is much to be done. The document promises:

“We will bring forward Environmental Outcomes Reports by the end of 2027 to replace Environmental Impact Assessment regulations under the Town and Country Planning Act 1990 and the Planning Act 2008 (for Nationally Significant Infrastructure Projects). Alongside this, we will introduce Environmental Outcomes Reports to replace the current system of Strategic Environmental Assessment. We will consider the most effective, and least disruptive, approach to transitioning from Environmental Impact Assessment and Strategic Environmental Assessment to Environmental Outcomes Reports, which may include parallel running of systems for a time limited period.”

Do any of us (1) believe this timetable or (2) believe that it will result in an improved system? I know what is most likely! EIA and SEA will continue unamended, with all of the current failings of those processes, with the additional requirement for EORs sitting over them… For the foreseeable future all those emerging new style local plans will have to grapple with old style SEA as well as whatever further requirements EORs might bring. That wasn’t meant to happen.

I don’t think there is an international example out there of what the government is seeking to achieve. The logical approach to environmental assessment is surely the well-trodden EIA/SEA methodology. To throw out the whole methodology because there are currently problematic aspects of how it is being carried out is to throw out the baby with the bathwater.

Might I suggest that now might be the time for ministers to channel their inner Ella/Ashe and ask themselves: why not call the whole thing off, stop work on EORs and instead focus on real, achievable, improvements to EIA and SEA processes?

After all, don’t we know the main issues?

Here’s two for a start.

First, there is insufficient discipline imposed, via government guidance, to standardise and streamline their structure or constrain their scale (e.g. indicative word limits, advice against replicating other assessment processes, discouraging lengthy quotations from national local policy documents and so on).

Secondly, the scale of the documentation is often blamed on the need to cover off the risk of legal challenge. Yes, more can be done to restrict further the bringing of opportunist legal challenges on the basis of asserted flaws in assessment work (e.g. by imposing procedural deadlines on the ability to JR the outcome of screening or scoping opinions or directions), but, even in advance of that, more can be done to bring across to potential claimants that most of these challenges fail in any event! I looked back at what I said in my 27 January 2024 blog post EIA Should Not Be A (Duller) Version Of Gladiators:

“It needs to be borne in mind that the EIA process is intended to be an aid to efficient and inclusive decision making in special cases, not an obstacle-race” (Carnwath LJ as he then was, in R (Jones) v Mansfield District Council (Court of Appeal, 16 October 2003).

The courts continually tell us this, despite so many professionals, politicians and objectors still treating the process of environmental impact assessment as some duller version of Gladiators.

Perhaps if we heeded this message the Government wouldn’t need to tie itself up in knots trying to replace environmental impact assessment and strategic environmental assessment with this still vague idea of environmental outcomes reports (reported by Planning Resource this week as now not likely to progress until 2025!).”

The naivety of my words in brackets there…

NB To end more positively: full credit to the Planning Inspectorate for the sensible changes made on 12 November 2026 to its Planning appeals: procedural guide – for appeals relating to applications dated on or after 1 April 2026 following last week’s blog post.

Simon Ricketts, 15 November 2026

Personal views, et cetera

EIA Should Not Be A (Duller) Version Of Gladiators

 “It needs to be borne in mind that the EIA process is intended to be an aid to efficient and inclusive decision making in special cases, not an obstacle-race” (Carnwath LJ as he then was, in R (Jones) v Mansfield District Council (Court of Appeal, 16 October 2003).

The courts continually tell us this, despite so many professionals, politicians and objectors still treating the process of environmental impact assessment as some duller version of Gladiators.

Perhaps if we heeded this message the Government wouldn’t need to tie itself up in knots trying to replace environmental impact assessment and strategic environmental assessment with this still vague idea of environmental outcomes reports (reported by Planning Resource this week as now not likely to progress until 2025!).

I thought about this when looking at this week’s (free subscription) Town Library weekly judgments update  – it contains amongst other things two Court of Appeal judgments dealing with particular assessment issues that regularly arise – as to cumulative effects and as to defining the “project“.

First we have R (Substation Action Save East Suffolk v Secretary of State (Court of Appeal, 17 January 2024) which concerned a challenge to development consent orders for the construction of the East Anglia One North and East Anglia Two offshore wind farms with associated onshore and offshore development.

The case has attracted some interest in relation to the court’s determination that the sequential test in relation to flood risk does not apply to the risk of flooding from surface water:

“The relevant provisions of EN-1, the Framework and the PPG do not require an applicant for development consent to demonstrate that whenever there is a risk of flooding from surface water there are no other sites reasonably available where the proposed development could be located in an area of lower surface water flood risk. The risks of flooding from surface water are to be taken into account when deciding whether to grant development consent under section 104 of the 2008 Act. The way in which account is to be taken of that risk raises issues of planning judgment in the application of the relevant provisions of the policies. The judge was correct in her interpretation of the policy and in finding that there was no irrationality or other public law error in the way in which the first respondent dealt with this issue when granting development consent.”

However, it was also interesting to read the the court’s consideration of the extent to which the potential effects on the environment arising from other projects need to be taken into account as cumulative effects. The appellant contended that “certain projects (known as the “Nautilus” and “Eurolink” schemes) have been identified as projects which could connect with the new National Grid substation. An assessment of the effect of those two projects was included in an Extension Appraisal document supplied by the second and third respondents. The appellant contends that the first respondent should have taken that information into account when deciding whether to make the development consent orders but he did not do so.” The reference in Schedule 4 of the EIA Regulations that the environmental statement must describe the likely significant effects of the development, including “the cumulation of effects with other existing and/or approved projects” is regarded as somewhat of a minefield.

The court ducked whether these potential future projects were to be regarded as “existing or approved” because the decision maker lawfully deferred consideration of the cumulative effects on the basis that there was not yet any adequate information on which a cumulative assessment could be based. “Such information as was available on the likely effects of other potential projects was not relevant to the assessment of the significant effects of the projects forming part of the applications for development consent in the present case.”

EIA pragmatism exhibit #1.

Secondly we have R (Together Against Sizewell C) v Secretary of State (Court of Appeal, 20 December 2023) which concerned a challenge to a development consent order for the proposed Sizewell C nuclear power station. The challenge related to Habitats Regulations Assessment rather than environmental impact assessment but the principles read across. It was argued that the Secretary of State  was wrong in law to treat the permanent supply of water to Sizewell C as not being part of the same project as Sizewell C for the purposes of carrying out an “appropriate assessment” under the Habitat Regulations (“Ground 1”) and that even if the Secretary of State was right to regard the permanent water supply as a separate project, he erred in failing to carry out a cumulative assessment of its effects together with those of Sizewell C itself, as per the Habitats Regulations (“Ground 2”).

Lazily I’m now just going to quote from our Town Library case summary:

“Ground 1

The Court dismissed Ground 1. The Court accepted, firstly, that there was no material difference between the meaning of a “project” under the Habitat Regulations and environmental impact assessment regulations and, secondly, that the principle adopted in previous cases that determining the nature and scope of a project, including whether two or more developments are to be regarded as one project, is a matter for the decision-maker to determine, which can only be subject to judicial review by the court on the grounds of irrationality or other unlawfulness. The Court, although seeking not to be prescriptive, endorsed the factors identified in the Wingfield case as capable of influencing this exercise of judgment.

The Court found no irrationality or any other unlawfulness in the Respondent’s decision, noting not only that he was entitled to reach this decision, but the Court would have reached the same conclusion.

It should also be noted that the Court rejected an argument that the Respondent unlawfully avoided appropriate assessment under the Habitats Regulations and saw the approach taken as a realistic and legitimate use of the “staged approach” previously approved in case law.

Ground 2

Ground 2 was dismissed by the Court for a number of reasons. These reasons included that it is well established that the consideration of cumulative impacts arising from a subsequent development that is still inchoate may be deferred to a later consent stage. Given that insufficient information was available as to the water supply, the decision to defer assessment by the Respondent was rational and lawful.

The Court rejected the argument that no proper assessment of the impacts would be carried out at the later stage because the construction of Sizewell C would result in the inevitable approval of the water supply proposal. There was no evidential basis for assuming that regulators would fail to carry out their statutory duties to assess the adverse effects of the water supply. The Court also rejected the argument that deferral was irrational because of a risk of Sizewell C not being operational in the absence of a water supply, as there was a reasonable level of certainty a permanent water supply would be provided and further the alternatives would still be subject to appropriate assessment.

Accordingly, the appeal was dismissed.”

EIA (HRA) pragmatism exhibit #2.

Simon Ricketts, 27 January 2024

Personal views, et cetera

Photograph courtesy BBC

Back To Reality

You may be returning from that escapist world that is MIPIM and grimacing at the prospect of a week’s worth of emails, or you may be finishing a week of grimacing at all the LinkedIn pics of your colleagues in Ray-Bans. In any event, we now have three developments in relation to the Levelling-up and Regeneration Bill, currently at Committee stage in the House of Lords, sent to test the old saying that a change is a good as a rest…

I’m very grateful for three of my partners, not part of the MIPIM contingent, who have particularly had their eyes on the following:

Government amendment relating to removal of “hope” value in relation to particular categories of CPO

The Government tabled amendments on 13 March 2023 to the Levelling-up and Regeneration Bill that would have significant impacts on landowners. Raj Gupta has written a Compulsory Reading blog post LURB in the Lords – no hope (16 March 2023) on the potentially far-reaching implications. We have arranged a Clubhouse Planning Law Unplanned session at 5 pm on Thursday 23 March to discuss the proposal, led by Raj, Jon Stott, Greg Dickson and other leading specialists. Please RSVP here if you would like to tune in and/or take part in the discussion.

Government consultation on environmental outcomes reports – a new approach to environmental assessment

The Government published its consultation today, 17 March 2023, on the design on its proposed new system of environmental assessment. See the press statement, and consultation document. Duncan Field has set out some initial comments in a LinkedIn post. Again, we are going to arrange a Clubhouse Planning Law Unplanned event, probably for Thursday 30 March but further details will appear shortly.

Government consultation on the proposed infrastructure levy

The Government published its consultation today, 17 March 2023, on the design of the proposed infrastructure levy. See the press statement, technical consultation and a February 2023 research paper published alongside it. Clare Fielding will shortly be publishing a Levy-Headed blog post as to the likely implications.

Now to unpack. And let my picture be a warning for you to keep your parents away from the Be Real app.

Simon Ricketts, 17 March 2023

Personal views, et cetera