Stephenicity

There will be no blog post this weekend, in memory of Stephen Ashworth.

I commend his Dentons partner Roy Pinnock’s LinkedIn post and the many wonderful comments it elicited.

Stephen – if only we could all cut through the nonsense like you could. You were the one I looked up to, always did.

My condolences to Stephen’s family and to his colleagues.

Simon

30 April 2021

M’lud On The Tracks: HS2

Great Bob Dylan album, almost.

This post collects together in one place some of the recent planning, environmental and compulsory purchase litigation in relation to the High Speed Two rail project.

R (Keir) v Natural England (16 April 2021, Lang J; further hearing before Holgate J, 23 April 2021, judgment reserved)

This is the interim injunction granted by Lang J preventing HS2 and its contractors from varying out works at Jones’ Hill Wood, Buckinghamshire, until either the disposal of the claim or a further order.

The claim itself has Natural England as the defendant and seeks to challenge its grant of a licence under the Conservation of Habitats Regulations 2017 in relation to works that may disturb a protected species of bat.

The question as to whether the injunction should be maintained came back to court yesterday, 23 April, before Holgate J, as well as whether permission should be granted in the claim itself, and he has reserved judgment until 2pm on 26 April.

Secretary of State for Transport v Curzon Park Limited (Court of Appeal hearing, 21 and 22 April 2021, judgment reserved)

This was an appeal by the Secretary of State for Transport against a ruling by the Upper Tribunal on 23 January 2020. My Town Legal colleagues Raj Gupta and Paul Arnett have been acting for the first respondent, landowner Curzon Park Limited, instructing James Pereira QC and Caroline Daly. Thank you Paul for this summary:

The case concerns certificates of appropriate alternative development (‘CAADs’) under the Land Compensation Act 1961. A CAAD is a means of applying to the local planning authority to seek a determination as to what the land could have been used for if the CPO scheme did not exist. Its purpose it to identify every description of development for which planning permission could reasonably have been expected to be granted on the valuation date if the land had not been compulsorily purchased. Importantly, subject to a right of appeal, the grant of a CAAD conclusively establishes that the development is what is known as ‘appropriate alternative development’. This is significant as:

• When compensation is assessed it must be assumed that planning permission for that development(s) in the CAAD either was in force at the valuation date or would with certainty be in force at some future date and

• Following reforms in the Localism Act 2001, where there is, at the valuation date, a reasonable expectation of a particular planning permission being granted (disregarding the CPO scheme and CPO) contained in a CAAD it is assumed that the planning permission is in force which converts the reasonable expectation into a certainty.

There are four adjoining sites, each compulsorily acquired by HS2 for the purposes of constructing the Curzon Street HS2 station terminus at Cuzon Street Birmingham – four different landowners and four different valuation dates (i.e. vesting dates under the GVD process). Each landowner applied for a CAAD for mixed use development including purpose-build student accommodation (PBSA). In the real world, the cumulative effects of the proposed adjoining developments (e.g. including but not limited to the proposed quantum and need for PBSA in light of a PBSA need in the local plan) would have been a material planning consideration. However, Birmingham City Council considered each CAAD application in isolation. The Secretary of State argued that they should have considered the other CAAD applications as notional planning applications and, therefore, as material considerations which would have been very likely to result in CAADs issued for smaller scale mixed-used development being issued leading to a lower total compensation award and bill for HS2. The preliminary legal issue to be determined by the Upper Tribunal and now the Court of Appeal is:

Whether, and if so how, in determining an application for a certificate of appropriate alternative development under section 17 LCA 1961 (CAAD) the decision-maker in determining the development for which planning permission could reasonably have been expected to be granted for the purposes of section 14 LCA 1961 may take into account the development of other land where such development is proposed as appropriate alternative development in other CAAD applications made or determined arising from the compulsory acquisition of land for the same underlying scheme’.

The Upper Tribunal had rejected the landowners’ argument that the scheme cancellation assumption (i.e. disregarding the CPO scheme) under the Land Compensation Act 1961 required CAAD applications on other sites to be disregarded. However, critically, the Tribunal agreed with the landowners’ that CAAD applications were not a material planning consideration and that there was no statutory basis for treating them as notional planning applications as the Secretary of State has argued. The Tribunal also disagreed with the Secretary of State that the landowners’ interpretation of the statutory scheme would lead to excessive compensation pointing out that the landowners’ ability to develop their own land in their own interests was taken away when their land was safeguarded for HS2 and from November 2013 when the HS2 scheme was launched until 2018 when the land interests were finally acquired by HS2 any planning permissions for these sites would have been determined in the shadow of the HS2 scheme and safeguarding of the land. The Secretary of State appealed the Upper Tribunal decision and the Court of Appeal granted permission to appeal in July 2020 noting that the appeal raises an important point on the principle of equivalence (i.e. the principle underpinning the CPO Compensation Code) that a landowner should be no worse off but no better off in financial terms after the acquisition than they were before) which may have widespread consequences for the cost of major infrastructure projects.

A judgment from the Court of Appeal (Lewison LJ, Lindblom LJ and Moylan LJ) is expected in the next month or so.

Sarah Green v Information Officer & High Speed Two Limited (First Tier Tribunal, 19 April 2021)

This was an appeal against the refusal by HS2 Limited to disclose, pursuant to the Environmental Information Regulations 2004, information as to the potential effect of its works on chalk aquifers in the Colne Valley. The information requested was as follows:

What risk assessments have taken place, of the potential increased risk to controlled waters as a result of imminent works by HS2 contractors along the Newyears Green bourne and surrounding wetland?

Are any of the risk assessments independent from the developers (HS2) and where are the risk assessment (sic) accessible to the public?

By the time of the hearing before the First Tier Tribunal, three reports had been disclosed, redacted. The Tribunal summarised the issues before it as follows:

“(1) whether HS2 correctly identified the three reports as being the environmental information which Ms Green requested and whether there was further material held which came within the request;

(2) whether at the time of Ms Green’s request the three reports were “still in the course of completion” or comprised “unfinished documents” and, if so, whether the public interest in maintaining the regulation 12(4)(d) exception outweighed that in disclosure;

(3) whether disclosure of those parts of the three reports which have been redacted in reliance on regulation 12(5)(a) would have adversely affected “public safety” and, if so, whether the public interest in maintaining the regulation 12(5)(a) exception outweighed the public interest in their disclosure.”

The Tribunal found, expressing its reasoning in strong terms, that the public interest in disclosure outweighed the public interest in maintaining any exemption.

“The reports in question in this case concern a major infrastructure project which gives rise to substantial and legitimate environmental concerns. They specifically relate to the risks of contamination to the drinking water supplied to up to 3.2 million people resulting from the construction of the HS2 line. This is clearly environmental information of a fundamental nature of great public interest.”

HS2 appeared to be concerned that “if the versions of the reports current in January 2019 were made public they “… could have been used to try and impact work undertaken in finalising the information”.

“It seems to us that such an approach almost entirely negates the possibility of the public having any input on the decision-making process in this kind of case, which goes against a large part of the reason for allowing public access to environmental information.

The suggestion that public officials concerned in making enquiries and freely discussing options to mitigate environmental problems might be discouraged or undermined by early disclosure of their work seems to us rather fanciful and was not supported by any kind of evidence; the case is not comparable in our view to that of senior officials indulging in “blue sky” thinking about policy options. We accept that the material is “highly technical” but we cannot see why a lack of understanding on the part of the public would have any negative impact on HS2’s work; if a member of the public or a pressure group wanted to contribute to the debate in a way that was likely to have any effect on the decision-making process they would no doubt have to engage the services of someone like Dr Talbot, who would be able to enter the debate in a well- informed and helpful way.”

“HS2’s second main point, that the Environment Agency will be approving and supervising everything, does not seem to us of great weight. Of course the Environment Agency is there to act in the public interest in relation to the environment but its involvement cannot be any kind of answer to the need for public knowledge of and involvement in environmental decisions. The EA is itself fallible and should be open to scrutiny. If the public could simply entrust everything to it there would be no need for the EIR.

HS2’s third main point is that if inchoate information is released it could be misleading and they would incur unnecessary expense correcting false impressions. We were not presented with any specific evidence or examples to illustrate how this problem might have been encountered in practice. It does not seem to us a very compelling point.”

R (Maxey) v High Speed 2 Limited (Steyn J, 10 February 2021)

This was an interim ruling in an application for judicial review, made only nine days previously, of the decision by HS2 Limited to extract the protesters that were occupying the tunnel under Euston Square Gardens and alleging a failure to safely manage Euston Square Gardens in a manner compatible with HS2 Limited’s obligations under the European Convention of Human Rights. It followed a rejection of an application by Mr Maxey for an interim injunction and followed an order made requiring him to cease any further tunnelling activity, to provide certain categories of information to HS2 Limited or others and to leave the tunnel safely, with which he had not complied.

At the hearing, Mr Maxey was renewing his “application for orders requiring (a) the cessation of operations to extract the protesters from the tunnel and (b) to implement an exclusion zone. In addition, the Claimant has expanded the interest relief he seeks to include provision forthwith by the Defendant of (a) oxygen monitoring equipment; (b) a hard-wired communication method; (c) food and drinking water for the Claimant and the protesters; and (d) to make arrangements for the removal of human waste from the tunnel.” He was also seeking to overturn the orders against him.

The judge rejected Mr Maxey’s arguments:

While I accept that the Defendant is (or at the very least there is a good argument that the Defendant is) currently under a duty to take all reasonable steps to protect those in the tunnel under the site (including the Claimant) from death or serious injury, on the evidence before me there is no realistic prospect of the Court finding that the Defendant is breaching its duty. In my judgment, the claim for interim relief does not meet the first test.

That suffices to dispose of the interim relief application. But if it were necessary to consider the balance of convenience, I would have to bear in mind the strong public interest in permitting a public authority’s decision (here a decision to proceed with the operation and a decision as to the necessary safeguards) to remain in force pending a final hearing of the application for judicial review, so the party applying for interim relief must make out a strong case for the grant of interim relief. The Claimant has not come close to establishing a strong enough case to justify the Court stopping the operations to remove those who are in the tunnel, given the compelling evidence as to how dangerous it is for them to remain there.”

R (Packham) v Secretary of State for Transport (Court of Appeal, 31 July 2020)

I summarised this case in my 9 January 2021 blog post Judges & Climate Change. It was Chris Packham’s failed challenge to the Government’s decision to continue with the HS2 project following the review carried out by Douglas Oakervee, the grounds considered by the Court of Appeal being “whether the Government erred in law by misunderstanding or ignoring local environmental concerns and failing to examine the environmental effects of HS2 as it ought to have done” and “whether the Government erred in law by failing to take account of the effect of the project on greenhouse gas emissions between now and 2050, in the light of the Government’s obligations under the Paris Agreement and the Climate Change Act 2008”.

R (London Borough of Hillingdon) v Secretary of State for Transport (Court of Appeal, 31 July 2020)

This case was heard consecutively with the Packham appeal. It related to Hillingdon’s challenge to the Secretary of State’s decision to allow (against his inspector’s recommendations) an appeal against Hillingdon’s refusal to grant HS2 Limited’s application for approval, under the Act authorising the relevant stage of the HS2 project, of plans and specifications for proposed works associated with the creation of the Colne Valley Viaduct South Embankment wetland habitat ecological mitigation. HS2 Limited had refused to provide Hillingdon with information so that an assessment could be made as to the effect of the proposed works on archaeological remains, HS2 Limited’s position being that it was “under no obligation to furnish such information and evidence. It says that this is because it will, in due course, conduct relevant investigations itself into the potential impact of the development upon any archaeological remains and take all necessary mitigation and modification steps. HS2 Ltd says that it will do this under a guidance document which forms part of its contract with the Secretary of State for Transport which sets out its obligations as the nominated undertaker for the HS2 Project.”

Lang J had upheld the Secretary of State’s decision but this was overturned by the Court of Appeal:

“The key to this case lies in a careful reading of Schedule 17 and the powers and obligations it imposes upon local authorities and upon HS2 Ltd. In our judgment, the duty to perform an assessment of impact, and possible mitigation and modification measures under Schedule 17, has been imposed by Parliament squarely and exclusively upon the local authority. It cannot be circumvented by the contractor taking it upon itself to conduct some non-statutory investigation into impact. We also conclude that the authority is under no duty to process a request for approval from HS2 Ltd unless it is accompanied by evidence and information adequate and sufficient to enable the authority to perform its statutory duty.”

[Subsequent note: Please also see London Borough of Hillingdon v Secretary of State for Transport (Ouseley J, 13 April 2021), “Hillingdon 2” where on the facts Ouseley J reached a different conclusion, holding that an inspector had not acted unlawfully in determining an appeal without information sought by the council from HS2 Limited as to the lorry routes to be used by construction lorries to and from the HS2 construction sites within its area].

R (Granger-Taylor) v High Speed Two Limited (Jay J, 5 June 2020)

This was a judicial review claim brought by the owner of a listed Georgian building near Regents Park. The property was separated by a large retaining wall, built in 1901, from the perimeter of the existing railway. “It rests approximately 17 metres from the front of the property and the drop from the level of the road to the railway below is approximately 10 metres. Unsurprisingly, given that the substrate is London clay, the wall has suffered periodic movement and shows signs of cracking. The Claimant’s expert says that it is “metastable”.”

The claimant was concerned as to the engineering solution arrived at for that section of the route, which was known as the Three Tunnels design. “This judicial review challenge is directed to the safety of the Three Tunnels design in the specific context of the outbound tunnel travelling so close to the base of the retaining wall. It is contended on the back of expert engineering evidence that this aspect of the design has engendered an engineering challenge which is insurmountable: in the result, the design is inherently dangerous. The risk is of catastrophic collapse of the retaining wall, either during the tunnelling works or subsequently, which would if it arose cause at the very least serious damage to the Claimant’s property. Consequently, the Claimant asserts a breach of section 6 of the Human Rights Act 1998 because her rights under Article 8 and A1P1 of the Convention have been violated.”

The judge boiled the questions down to the following:

has the Claimant demonstrated that she is directly and seriously affected by the implementation of the Three Tunnels design, given the risk of catastrophic collapse identified by Mr Elliff? In my view, that question sub-divides into the following:

(1) should I conclude on all the evidence that the Three Tunnels design is so inherently flawed in the vicinity of the retaining wall that no engineering solution could be found to construct it safely? and

(2) have the Defendants already committed themselves to implement the Three Tunnels design regardless of any further work to be undertaken under Stage 2?

After detailed consideration of expert engineering expert on both sides, the judge rejected the claim.

Anixter Limited v Secretary of State for Transport (Court of Appeal, 30 January 2020)

This was a compulsory purchase case, about whether an owner of four units on the Saltley Business Park in Birmingham, faced with compulsory purchase of one of them, had served counter-notices in time such as to trigger its potential ability to require acquisition of its interests in all four buildings. The court ruled that it had not.

It certainly seems an age since R (HS2 Action Alliance) v Secretary of State for Transport (Supreme Court, 22 January 2014) where in a previous law firm life I acted for the claimant, instructing David Elvin QC and Charlie Banner (now QC). The case concerned whether the publication by the Government of its command paper, “High Speed Rail: Investing in Britain’s Future – Decisions and Next Steps” engaged strategic environmental assessment requirements and whether the hybrid bill procedure would comply with the requirements of the Environmental Impact Assessment Directive (for more on the HS2 hybrid bill procedure, see my 30 July 2016 blog post HS2: The Very Select Committeehttps://simonicity.com/2016/07/30/hs2-the-very-select-committee/). The loss still grates. And in consequence of that ruling…

There’s a slow, slow train comin’.

Simon Ricketts, 24 April 2021

Personal views, et cetera

Thank you to my Town Legal colleague Lida Nguyen for collating a number of these cases.

Our clubhouse Planning Law, Unplanned session at 6pm on 27 April will follow a similar theme, so if you are interested in issues relating to HS2 or in wider questions as to judicial review, interim injunctions, access to information or compulsory purchase compensation, do join us, whether to contribute to the discussion or just listen in. As always, contact me if you would like an invitation to the clubhouse app (which is still iphone only I’m afraid).

Detail from Bob Dylan’s painting Train Tracks

Trent Won, Cil Nil

The community infrastructure levy system, in its application to lay individuals in particular, is monstrous, absurdly over-engineered, often badly administered and unfairly opaque.

Could anyone disagree after reading Lang J’s judgment handed down yesterday in R (Trent) v Hertsmere Borough Council (16 April 2021)? (Or for another example see my 19 January 2019 blog post CIL The Merciless).

Solicitor Alison Trent brought proceedings for judicial review, as a litigant in person, in order to quash a totally unjustified demand notice for £16,389.75 that she received on 21 April 2020 in relation to the construction of a dwelling in Radlett.

Her success represents a loud wake-up call for CIL collecting authorities.

Planning permission was issued on 10 February 2017 for demolition of a house and the construction of a replacement three bedroom dwelling.

Even with a project as simple as this, there is a complicated sequence of notices:

⁃ Under regulation 65(1) of the CIL Regulations 2010 “the collecting authority must issue a liability notice as soon as practicable after the day on which a planning permission first permits development”.

⁃ The person assuming liability for CIL then has to serve an assumption of liability notice and, if appropriate as here, a self build exemption claim form.

⁃ A commencement notice must then be served on the authority before development commences.

When something goes wrong in that sequence, matters invariably get messy.

Here:

⁃ There was no evidence that the necessary liability notice had been sent out in 2017 although a draft was on the council’s computer system.

⁃ Ms Trent had unwittingly jumped the gun by purporting to submit a self build exemption form ahead of planning permission being issued and had failed to submit an assumption of liability notice, both mistakes apparently at least partly due to misleading advice she had received from the authority.

⁃ The development took place and, when the authority realised, it issued a liability notice, demand notice and imposed surcharges for failing to submit an assumption of liability notice (surcharge of £50) and failure to submit a commencement notice to the Council (surcharge of £2,500).

Ms Trent had successfully appealed to the Planning Inspectorate against the imposition of the surcharges. The inspector found that (1) the council had failed to issue a liability notice and therefore she had never been in a position to serve an assumption of liability notice – the 2017 notice had never been served and the 2019 notice was not served “as soon as practicable” after planning permission had been issued – and that (2) the deemed commencement date on the demand notice was incorrect. She had also argued that the notices did not meet procedural formalities but the inspector did not need to consider that issue.

Unbelievably, the authority then issued a replacement demand notice, on 21 April 2020, relying on the 2019 liability notice which the inspector had considered not to be valid!

Ms Trent challenged the issue of that demand notice by way of judicial review, arguing as follows:

“In the light of the Inspector’s findings, and the Council’s material misunderstandings or errors of fact and/or errors of law and/or procedure, the Council’s decision to issue the 2020 demand notice, on the basis that the 2019 liability notice was valid, was manifestly improper and/or irrational and/or unfair and unreasonable.

…the Council’s decision to issue the 2020 demand notice, and to maintain its registration on the Land Charges Register for the Property in respect of the alleged CIL liability, was a breach of the Council’s duty under section 6 of the Human Rights Act 1998 in that it acted in a manner which was incompatible with her Convention rights under Article 1 of Protocol 1 to the European Convention on Human Rights (“ECHR”).”

The judge found as follows (extracts from judgment):

“In my judgment, the Defendant was required to issue and serve statutory notices which complied with the requirements in the CIL Regulations, and to do so in the prescribed sequence. In consequence, the Claimant was not under an obligation to pay the CIL, as required by the 2020 demand notice, unless and until the Defendant had issued and served a valid liability notice, in accordance with regulation 65 of the CIL Regulations.”

“Planning permission was granted on 10 February 2017. So the 2019 liability notice was issued 2 years and 6 months (less 5 days) after the grant of planning permission. I agree with the Inspector that such a long period of time cannot reasonably be described as “as soon as practicable” and this amounted to a breach of the requirement in regulation 65(1). The breach was not waived by the Claimant.

Regulation 65(1) imposes a mandatory requirement without any provision for extensions of time. Time starts to run from the date on which a planning permission first permits development. The phrase “as soon as practicable” gives an authority some flexibility, for example, if the recipients are not readily identifiable or their address known, or if there is an administrative backlog. But in the light of the statutory scheme and its purpose, the expectation must be that any delay would be measured in weeks or months, not years. I consider that the absence of any provision for extensions of time was deliberate, to ensure that authorities comply with the duty in a timely way.”

“In my judgment, it is of fundamental importance to the operation of the statutory scheme that the liability notice is issued and served soon after the grant of planning permission because of the key information it contains about the recipient’s liability to CIL, and the next steps which follow under the scheme. It is not the practice of this Council to provide this information in any other form or at any other time, and I assume that the same applies in other authorities.

I consider that the failure to issue and serve a valid liability notice on the Claimant within the prescribed time period was prejudicial. If the Claimant had received a timely liability notice, in February 2017, it would have alerted her to” the need to apply for exemptions.

In my judgment, as the liability notice is a formal legal document, which imposes a tax liability on the recipient, and places a land charge on the owner’s property, it is of fundamental importance that the recipient is correctly identified by their name. In this case, the liability notice should have been addressed and issued to “Alison Trent”. She should have been identified as the owner of the relevant land. Instead, the Defendant addressed and issued the liability notice to “C/O Alison Trent & Co”. “Alison Trent & Co.” is the Claimant’s business. It has no legal or beneficial interest in No. 40 and does not fall within any of the categories of recipients. I consider that the only plausible explanation for this error was incompetence on the part of the Defendant. As the liability notice was not addressed and issued to the correct person, it is invalid.

The regulations do not contain any provisions to save a non-compliant notice. The Claimant pointed out that this is in contrast to other regulatory schemes such as enfranchisement notices under section 13 of the Leasehold Reform, Housing and Urban Development Act 1993 which may be saved by paragraph 15(1) of Schedule 3.

As a general rule, failure to effect valid service of a liability notice would invalidate a notice. However, in this case, the notice was successfully served on the Claimant, care of the London business address, which was the second of the two addressees she provided on the Land Register. Therefore, despite the failure to serve the Claimant at No. 38 or No. 40, which was in breach of the requirements of the CIL Regulations, I do not consider the failure is of sufficient significance to invalidate the notice.”

Whilst the inspector could not formally quash the 2019 liability notice, “I would expect a responsible authority to have regard to the Inspector’s findings when deciding upon its next steps.”

The Claimant’s ground of challenge under Article 1 of Protocol 1 to the ECHR turned on the lawfulness of the 2019 liability notice, and the consequent 2020 demand notice, requiring her to pay the CIL as assessed. As I have found that the notices were not valid, it follows that there would be a breach of A1P1 if the Claimant was required to pay the CIL.”

“In conclusion, the Claimant’s claim for judicial review is allowed. The liability notice issued by the Council on 5 August 2019, and the demand notice issued by the Council on 21 April 2020, are invalid for the reasons set out in this judgment, and are to be quashed.”

So there we have it.

Woe betide any collecting authority that delays unreasonably in serving a liability notice (common in my experience) or addresses it incorrectly. The judgment would imply that the authority may lose the right to serve a liability notice at all (and thereby not be entitled to levy any CIL in relation to the development) if it delays unreasonably in serving a liability notice (in this case there was a delay of two and a half years, but in circumstances where the authority’s records had probably, although wrongly, shown that one had already been served). That had not previously been my understanding and it would be extremely risky for a developer to embark on construction in reliance on that approach, rather than (as is often currently the case) chasing down the late notice so that it can go on the merry-go-round of assumption of liability, securing exemptions and serving the commencement notice. But I can foresee arguments being raised in some situations.

And woe betide this Government if its proposed Infrastructure Levy is as unnecessarily complicated as CIL. First, why do we have a self build exemption in the first place? Secondly, given that we do, it should be obvious from the planning application that the development proposed is likely to qualify. Why the need for any forms at all? Under a properly constructed system, there would be no need for these reeling spools of, of, yes, of red tape – there I’ve said it.

Simon Ricketts, 17 April 2021

Personal views, et cetera

PS This week’s clubhouse Planning Law Unplanned session will be a careers special. 6pm, 20 April. As always, message me for more information.

How To Stay Out Of Trouble In The Planning Court

When cat herders describe their job to a friend, they probably say “It’s like editing a legal textbook written by 20 barristers from the same set of chambers, to an over-arching style guide, and a deadline”.

As editor of the new second edition of “Cornerstone on the Planning Court” (Bloomsbury Professional), Michael Bedford QC would make an excellent herder of cats. Or maybe Cornerstone Barristers are just a collaborative bunch. After all, “Cornerstone on the Planning Court” is part of a series that includes Cornerstone on “Anti-Social Behaviour”, on “Information Law” and on “Social Housing Fraud”.

The first edition of Cornerstone on the Planning Court (which shall I call COTPC1) was published in September 2015, just under 18 months after the Planning Court was created. Our office copy is well-thumbed, corner-folded and spine-broken. Beyond the Civil Procedure Rules and practice directions (which, folks, don’t tell you half of what you need to know!), it has provided the main source of rigorous but practical guidance as to the operation of this new forum, now the sharp end for most litigation of relevance to planners and planning lawyers but which structurally occupies an uncertain space as a specialist list within the Queen’s Bench Division of the High Court (see also my 8 July 2018 blog post, The Planning Court).

The Planning Court has proved remarkably popular. By traditional litigation standards, the permission stage is rapid, followed by a final hearing for those cases which have not been sieved out through that process. Cases earmarked as “significant” are allocated to judges who are particularly experienced in planning law matters. There has also been an enormous throughput.

With Landmark Chambers, we carried out some analysis last year of the cases which have come before the court, which I summarised in my 15 August 2020 blog post, Introducing The Planning Court Explorer. We also held a recorded webinar where Duncan Field and I were joined by John Litton QC, Jenny Wigley QC and Tim Buley QC – PC in 2020: Has the Planning Court proved a success?

The nature of the court, separate but not separate from the wider judicial review functions of the Administrative Court, serves to obscure even basic statistics as to its overall caseload. So I was really taken by a video post last week from Mark Howells at Kings Chambers, Data and statistics of planning judicial reviews (6 April 2021) a deep dive into zipped files and data entries for information which surely should be made more easily available.

With so much new case law, together with changes to costs protection procedures, COTPC2 is a welcome update.

The second half of the book, pages 245 to 451, comprises the relevant Civil Procedure Rules themselves and related practice directions, protocols and forms. The first half of the book combines insightful summaries of the historical development of planning law and its current components, together with judicial review and statutory challenges (at a level which would be a good read even for those new to the subject) and of the many key legal principles arising in Planning Court claims, with detailed from-soup-to-nuts practical guidance for practitioners as to every aspect of the litigation process.

The foreword to COTPC2 is by Holgate J, who takes care to distinguish between decision-making procedures within the planning system which “determine the merits of the competing arguments in each case. The Court exists to deal solely with any public law issues that arise from those decisions and to do so as efficiently as possible, avoiding unnecessary delay”. He refers to “two of the fundamental foundations of our constitution: the rule of law and the separation of power between the courts, the legislature and the executive. These govern the Planning Court just as much as any other part of our legal system”. He quotes Lord Carnwath in the Suffolk Coastal case, one of the most influential cases since COTPC1:

“…the judges are entitled to look to applicants, seeking to rely on matters of planning policy in applications to quash planning decisions (at local or appellate level), to distinguish clearly between issues of interpretation of policy, appropriate for judicial analysis, and issues of judgment in the application of that policy; and not to elide the two”.

We have been warned.

The constitutional role of administrative law is of course a topical issue. My 12 September 2020 blog post, Faulks Review Of Administrative Law: Call For Evidence reported on the review instituted last year by the Government. Many of us were somewhat fearful as to what might emerge but the March 2021 report is to my mind an impressive, considered, piece of work.

My only disappointment is that the “no nonsense” approach of the Planning Court in many respects, particularly in relation to timescales, might have been endorsed as appropriate for wider adoption but instead we seem simply to have been acknowledged as operating in our own little world…

Particular congratulations should go to Celina Colquhoun (39 Essex chambers), as the only planning barrister on the review panel.

The Government has published a consultation document setting out proposed reforms to administrative law in response to the recommendations in the review, with a deadline of 29 April 2021. I noticed this week that ironically the Ministry of Justice has already received a threat of judicial review, from a solicitors’ firm, on the basis that the deadline is considered to be too short.

But I’ll pause there because this post was intended as a review of a book about Planning Court judicial review rather than a review of a proposed judicial review of a proposed review of judicial review.

There is one overwhelming selling point of COTPC2 for me: in the nicest possible way, it will help me sleep.

After all, who of us does not stay awake worrying about phantom missed deadlines, overlong bundles, unnecessary witness statements, late settlement notifications and everything else that can possibly go wrong?

We all want to stay out of trouble in the Planning Court, so thank you Michael and colleagues.

Simon Ricketts, 10 April 2021

Personal views, et cetera

PS This week’s Planning Law, Unplanned clubhouse session (6pm on 13 April) will have as its theme your most bizarre planning inquiry/court hearing/site visit/planning committee stories. We want to hear them on the night, with a prize to the best.

Forthcoming Commercial To Resi Rules Tightened After Consultation

I have taken care over the heading of this piece about the Town and Country Planning (General Permitted Development etc.) (England) (Amendment) Order 2021, laid before Parliament on 31 March 2021, which introduces a new class MA into the GPDO, granting deemed planning permission for change of use from commercial and business use (class E) to residential (class C3) from 1 August 2021.

I have taken care because so much of the noise this week was about how the Government hasn’t listened to the responses it received to its 3 December 2020 consultation paper, whereas for me the news is that it has listened to much of the criticism it received. The final form of the regime is significantly constrained compared to the consultation version. Give credit where credit’s due!

I summarised the initial proposal in my 4 December 2020 blog post, E = C3, expressing a number of concerns. Responses to the consultation from all quarters expressed equivalent concerns – some of course going further, in questioning more fundamentally the role of the permitted development rights process.

Aside from the Order itself which saw the light of day later on that day, we have the 31 March 2021 press statement (at the now traditional one minute past midnight) and the Government’s response to the consultation process.

The RTPI and others were tweeting their reactions before the Order had even been published on line (although to be fair the headlines were in the press statement). A joint letter was sent yesterday, 1 April 2021, to the prime minister by the RTPI, RIBA, RICS and CIOB. I acknowledge that many have “in principle” concerns about the availability of fast-track permitted development rights procedures but isn’t the letter somewhat of an over-reaction? What do members of those organisations think? Call me a defeatist pragmatist, but the proposals could have been so much worse!

These were the Government’s objectives, as they were stated in the December consultation document:

“In his ‘Build, Build, Build’ statement of 30 June 2020 the Prime Minister said that we would provide for a wider range of commercial buildings to be allowed to change to residential use without the need for a planning application. To meet this aim, support housing delivery and bring more residential use into our high streets and town centres, boosting footfall and creating additional demand, we propose to introduce a new national permitted development right for the change of use from the new Commercial, Business and Service use class to residential use. The new right would help support economic recovery, housing delivery and the regeneration of our high streets and town centres.”

The proposals were always intended to be introduced much more quickly than the proposals in last year’s planning white paper – after all existing permitted development rights expire on 31 July 2021 in relation to changes of use from the classes that went to form the new class E:

“While Planning for the future sets out our longer-term ambitions, we want at the same time to continue to explore more immediate changes to the planning system to provide greater planning certainty and flexibility to ensure that it can effectively contribute to some of the immediate challenges facing the country.”

It is also worth remembering that the rights which expire on 31 July already include rights to convert offices (no floorspace limit), light industrial (500 sq m floorspace limit) and retail (150 sq m floorspace limit). The rules to be introduced from 1 August allow greater flexibility in a number of respects but are also significantly tighter than the existing rights in various ways.

My colleague Tom Brooks has prepared a detailed client summary in relation to all of the PD changes within the Order (this blog post is only dealing with class MA rather than the other excitements within). If you message or email me I will send it to you next week, but for the purposes of this blog post I set out below the Government’s summary of the proposed changes:

“We will introduce a new national permitted development right to create new homes through the change of use from Commercial Business and Service uses. The right will:

• have effect from 1 August 2021

• be subject to a size limit of 1,500 sq m of floorspace changing use

• apply to buildings that have been in Commercial, Business and Service uses for two years, including time in former uses now within that class

• apply to buildings that have been vacant for at least three continuous months

• apply in conservation areas, but not in other article 2 (3) land such as National Parks and Areas of Outstanding Natural Beauty

• be subject to prior approval by the local planning authority on specific planning matters

• attract a fee of £100 per dwellinghouse.”

The consultation proposals had:

• no size limit (and this size limit cuts back on what can already be achieved via the existing office to resi PD right)

• no requirement that the relevant building should have been in commercial , business and service uses (i.e. any of the uses that now make up class E) for the two years leading up to the date of the application for prior approval (for offices to residential, the cut off point in the existing rules is 29 May 2013).

• no requirement that the building must have been vacant for the three months leading up to the date of the application for prior approval (a requirement which has not existed in relation to existing PD rights).

There is also now an express carry-forward to 1 August 2022 of existing article 4 directions that restrict office to residential permitted development rights – addressing what would have been a significant loophole (see e.g. my 7 February 2021 blog post Art 4 Life).

Prior approval requirements will still include transport, contamination, flooding, noise, and adequate natural light. As trailed in the consultation proposals, prior approval will be required, where relevant, as to the impact on the character or sustainability of a conservation area caused by the change of ground floor use of a building within a conservation area. Where relevant, prior approval will also be required as to the impact on the intended residential occupiers if the area is considered important for “general or heavy industry, waste management, storage and distribution, or a mix of such uses” and as to the impact on local provision if there is a loss of services provided by a registered nursery or health centre.

Prior approval applications will need to include a floor plan indicating “the total floor space in square metres of each dwellinghouse” (and remember that the Government’s nationally described minimum space standard applies to any schemes which are the subject of a prior approval application from 6 April 2021 in any event).

For the first time, notices will need to be served on on any adjoining owner or occupier and, where the proposed development relates to part of a building, on any owner or occupier of the other part or parts of the building.

Remember that there is no exemption from CIL for permitted development, the usual rules apply – although most commonly the in-use buildings exemption will apply if at least part of the building has occupied for a use which is lawful for at least six months continuously in the last three years.

Mitigation cannot be secured as to matters that are not the subject of the prior approval process, so PD residential development is still free from affordable housing and other social infrastructure commitments (e.g. contributions to the cost of education facilities), but remember that the scale of development now permitted, with the 1,500 square metres cap, is far lower than the scale of conversions of office buildings that we have previously seen. The horse has bolted on that one.

The new rights do not limit in any way the need for planning permission for external works to the building that materially affect its external appearance, so finger-pointing as against the Government’s “beauty” aspirations is misdirected in my view.

What concerns are we left with? Yes, the new rules will allow residential development in potentially unsustainable locations. Yes, the new rules will allow commercial frontages in high streets to be converted to residential use in a way which may harm the traditional function of town centres (although subject to the need for a separate planning permission for the external treatment of the building). Yes, the new rules do limit in practice the role of the local planning authority in determining what are appropriate uses for a particular area. Yes, there will still be room for uncertainty and “gaming” of the system, particularly around the vacancy requirement. Set against these concerns, are the Government’s objectives in terms of enabling more homes to be delivered quickly and in finding new uses for redundant commercial floorspace and is the need for us all to acknowledge the various protections that are now (at last) in place, seeking to ensure that accommodation is to be delivered to at least a minimum standard (e.g. size of homes, light) and seeking to reduce the potential for the new rights to lead to unintended outcomes (e.g the floorspace cap, vacancy requirement).

Where does the balance lie? Are there now sufficient checks and balances? Are we going to see a final rush to make prior approval applications under the existing rules? Join a number of us on Clubhouse for a discussion on this very subject – from 6pm on Tuesday 6 April.

Simon Ricketts, 2 April 2021

Personal views, et cetera