Moving Into First Homes: 3 Key Deadlines

The Government’s First Homes announcements this week mean that we all need to understand the practicalities as to how this new form of discounted market sale housing will work and to plan around three key implementation dates.

On 24 May 2021 we had the formal ministerial statement together with the publication of MHCLG guidance providing “further detail on First Homes and their implementation”. For prospective purchasers there is also the Government’s Own Your Own Home website.

The three key dates are as follows:

28 June 2021

From the guidance: “ Local plans and neighbourhood plans submitted for examination before 28 June 2021, or that have reached publication stage by 28 June 2021 and subsequently submitted for examination by 28 December 2021, will not be required to reflect the First Homes policy requirement

(However: “Planning Inspectors should consider through the examination whether a requirement for an early update of the local plan might be appropriate.”)

28 December 2021

From the guidance: “The new First Homes policy requirement does not apply for the following:

sites with full or outline planning permissions already in place or determined (or where a right to appeal against non-determination has arisen) before 28 December 2021

28 March 2022

It also does not apply to “applications for full or outline planning permission where there has been significant pre-application engagement which are determined before 28 March 2022”.

So if you wish to avoid the new requirement and you are not in an area where a plan has been adopted under the transitional arrangements, you need to have submitted your application so that it will be determined (or so that that the statutory right to appeal on the basis of non-determination has arisen) by 28 December 2021 and if there is any doubt as to whether you will meet that deadline it would be prudent to have engaged in “significant pre-application engagement” such that the deadline for achieving permission is 28 March 2022.

“If an applicant wishes to amend a planning application to include First Homes which is already submitted and likely to be granted before these dates, the local planning authority should be flexible in accepting First Homes as an alternative type of tenure.

Local authorities should have flexibility to accept alternative tenure mixes for planning applications that are determined within the timescales identified above, although they should consider whether First Homes could be easily substituted for another tenure, either at 25% or a lower proportion.”

From the guidance:

What is a First Home?

First Homes are a specific kind of discounted market sale housing and should be considered to meet the definition of ‘affordable housing’ for planning purposes. Specifically, First Homes are discounted market sale units which:

a) must be discounted by a minimum of 30% against the market value;

b) are sold to a person or persons meeting the First Homes eligibility criteria […];

c) on their first sale, will have a restriction registered on the title at HM Land Registry to ensure this discount (as a percentage of current market value) and certain other restrictions are passed on at each subsequent title transfer; and,

d) after the discount has been applied, the first sale must be at a price no higher than £250,000 (or £420,000 in Greater London).

First Homes are the government’s preferred discounted market tenure and should account for at least 25% of all affordable housing units delivered by developers through planning obligations.”

….

“Who is eligible to purchase a First Home?

A purchaser (or, if a joint purchase, all the purchasers) of a First Home should be a first-time buyer as defined in paragraph 6 of schedule 6ZA of the Finance Act 2003 for the purposes of Stamp Duty Relief for first-time buyers.

Purchasers of First Homes, whether individuals, couples or group purchasers, should have a combined annual household income not exceeding £80,000 (or £90,000 in Greater London) in the tax year immediately preceding the year of purchase.

A purchaser of a First Home should have a mortgage or home purchase plan (if required to comply with Islamic law) to fund a minimum of 50% of the discounted purchase price.

These national standard criteria should also apply at all future sales of a First Home.”

…..

How should the remaining 75% of affordable housing be secured through developer contributions?

Once a minimum of 25% of First Homes has been accounted for, social rent should be delivered in the same percentage as set out in the local plan. The remainder of the affordable housing tenures should be delivered in line with the proportions set out in the local plan policy.

For example, if a local plan policy requires an affordable housing mix of 20% shared ownership units, 40% affordable rent units and 40% social rent units, a planning application compliant with national policy would deliver an affordable housing tenure mix of 25% First Homes and 40% social rent. The remainder (35%) would be split in line with the ratio set out in the local plan policy, which is 40% affordable rent to 20% shared ownership, or 2:1. 35% split in this way results in 12% shared ownership; and 23% affordable rent.

In another example, if a local plan policy requires 80% of units to be shared ownership and 20% to be social rent, a policy compliant application would deliver 25% First Homes units, 20% social rent and 55% shared ownership.

If a local authority has an up-to-date policy on cash contributions in lieu of onsite contributions, then a planning application compliant with national policy will align with this approach.”

The requirement will be secured by our trusty friend, the section 106 agreement (or unilateral undertaking). The guidance states: “The government will publish template planning obligations for this purpose, which the local planning authority can use as a basis for agreements prepared locally.” A workable template (stress the word “workable”) would be very useful indeed.

How will this policy mechanism work across very different housing market areas across the country and what might be the unintended consequences? I recommend an excellent Lichfields blog post, First Homes: dicing with the discount (Rachel Clements and Bethan Haynes, 27 May 2021).

They ask where can First Homes potentially have the biggest impact?

“First Homes have the potential to have the greatest impact in areas where first-time buyers are currently priced out of the open market (at the entry-level) but where First Homes would be within reach, when the minimum 30% discount is applied. We estimate this represents around one in five authorities in England – around 63 in total.”

Will it avoid the problems that caused the previous Starter Homes concept to fail (e.g see my 29 February 2020 blog post Starter Homes Were A Non Starter – What Future For First Homes?)? What do we make of this continuing political decision to intervene in the market in the interests of encouraging home ownership at the expense (where viability is impacted) of affordable housing for rent, for those on a lower rung of the housing ladder?

There is plenty more to say on the subject, for instance the new opportunity arising to bring forward First Homes exception sites on allocated land outside the green belt or designated rural areas. But for now, I suspect that developers and local planning authorities alike will be wanting to do some basic number-crunching and to bear those three deadlines in mind.

Simon Ricketts, 28 May 2021

Personal views, et cetera

This Tuesday evening’s Planning Law, Unplanned Clubhouse session (6pm, 1 June) takes on a more general subject: “Has work taken over your life? Life hacks, work hacks”. Do come along and share your views, or just listen to the chat. An invitation to the app is here.

Whitechapel Bell Foundry: Facts, Media, Politics

Government approves plan to turn Whitechapel Bell Foundry into boutique hotel (The Standard, 17 May 2021). Well, what do we think about that?

Bell foundry that cast Big Ben can be turned into boutique hotel, UK government says – Decision has drawn wave of criticism from culture and heritage professionals, accusing government of ‘money-grabbing philistinism’ (The Art Newspaper, 14 May 2021). Crumbs.

From the piece:

Andrew Wilson, a curator at Tate, wrote on Twitter that this is “another example of the normalisation of money-grabbing philistinism that this government promotes”. Writing on his blog, Charles Saumarez-Smith, the former chief executive of the Royal Academy of Arts in London, says that the government “is play-acting, [putting] a superficial veneer over rather brutal capitalists, who are happy to use British history for their own purposes… a hotel for foreign tourists is more important than a bit of living history”.

Saumarez-Smith also criticises the heritage body Historic England, which backed the boutique hotel project, saying: “I hope that the Commissioners of Historic England, who have so conspicuously failed in their public duty, might consider what went wrong: why they did nothing; why they have allowed this to happen in such a conspicuously supine way.” Historic England said in a statement: “We believe that the proposals have the makings of a successful heritage regeneration scheme, and would provide a sustainable future for this important group of listed buildings.”

Whitechapel Bell Foundry to be turned into a hotel, after Government greenlights plans (The Telegraph, 14 May 2021) – a piece that also quotes the tweets from Andrew Wilson and Charles Saumarez-Smith (Saumarez-Smith then writing a long piece in the same newspaper on 18 May 2021, If Robert Jenrick doesn’t act now, the Whitechapel Bell Foundry will be lost for good – A priceless piece of our heritage is on the brink of being turned into a hotel. Why won’t our public institutions protect it? ).

Bell tolls for historic Whitechapel foundry that created Big Ben (The Times, 14 May 2021), a piece which starts:

The housing secretary has ordered a review of planners’ approach to heritage after a decision was made to allow a 450-year-old bell foundry that cast Big Ben to be turned into a boutique hotel.”

Away from the traditional media, there has inevitably also been much tweeting and perhaps it is apt that the Secretary of State took to twitter to announce that review, the announcement so far taking the form just of the final sentence of this thread of tweets:

The one thing you get from the newspaper headlines is that the foundry is being turned into a hotel. Isn’t it interesting/worrying how these stories take on a life of their own, reduced to compelling headlines.? Of course, it’s inevitable – who has the time to read even the Secretary of State’s 13 May 2021 decision letter and accompanying inspector’s report, let alone any of the underlying documents? The foundry is not being turned into a hotel.

To take a step back…

First, what was the site? As described by the inspector:

“2.2 The entry in the statutory list provides a great deal of information about the Whitechapel (or what it terms the Church) Bell Foundry. It suffices to set out here that it is a Grade II* listed building. However, the situation is complicated, to a degree, by the fact that parts of the overall foundry site are specifically excluded from the listing.

2.3 Put simply, the application site has three main elements. Firstly, there is the front range (including 32 and 34 Whitechapel Road and 2 Fieldgate Street). Secondly, behind that front range, lie the courtyard and old stables and thirdly, beyond those, are the old foundry and former cottages. Together, these elements comprise the Grade II* listed building.

2.4 Beyond that lies what has been termed the 1980s building. This building is specifically excluded from the listing. Beyond and adjacent to the 1980s building are two areas of car park and hardstanding which were not part of the Whitechapel Bell Foundry but are parcels of land that have been assembled by the applicant.”

The foundry use had ceased in 2017.

What are the proposals by the applicant, Raycliff Whitechapel LLP? Again, as described by the inspector:

4.1 In simple terms, there are two main components of the proposals that can loosely be classified as the listed building and the new building. In terms of the listed building itself, it would play host to a modern foundry, interpretation spaces, a café and events space, workspaces and workshops. The proposed uses and improved circulation are intended to allow the maximum number of people to access and experience the building.

4.2 The new building would be home to a hotel, with 103 bedrooms, a restaurant, a bar, and a roof-top terrace and pool, and a workspace at ground floor level.

4.3 The ground floor across both the listed building and the new building would be open to the public, with the foundry, interpretation spaces and the café in the historic building, the restaurant bar and hotel reception in the new building. The main entrance to the buildings would be common to both.”

Tower Hamlets Council resolved to grant planning permission and listed building consent on the advice of its officers on 14 November 2019 and the Secretary of State then issued a holding direction on 2 December 2019.

Remember Rory Stewart’s campaign to be London Mayor? Back in December 2019, his campaigning included support for the Save the Whitechapel Bell Foundry campaign (Rory Stewart Declares His Support To Save The Whitechapel Bell Foundry, Spitalfields Life, 19 December 2019).

Photo courtesy of Spitalfields Life website

The applications were called in by the Secretary of State on January 2020. There was an early hiccup in the process when housing and planning minister Chris Pincher mistakenly told MPs in a debate on 11 June 2020 (seeking to defend the Secretary of State’s position in relation to another scheme in Tower Hamlets, Westferry – now incidentally back at inquiry for redetermination but that’s another story):

“I am obliged to the hon. Gentleman for his question. As I said, it is not unusual for Ministers to look at and call in significant applications, and for them to come to a different conclusion from that of the Planning Inspectorate. My right hon. Friend’s reasons for his decision were clearly outlined in his decision letter of 14 January. He makes it clear that one reason for his decision to allow the application was the very significant number of homes that were going to be built as a result of it, including affordable homes. I might say in response to the hon. Gentleman that in the same week, in an application to the same authority, my right hon. Friend came to a very different conclusion when he refused a planning application made by and supported by the local authority to demolish the Whitechapel Bell Foundry, the one that created Big Ben and the Liberty bell. The local authority, the well-known tribunes of the people in Tower Hamlets, wanted to demolish it and build a luxury boutique hotel. My right hon. Friend will always come down on an application based on its merits and in the interests of the people. That is what he did on this occasion and that is what he will always do.”

He later apologised for his mistake – it had only been called in by the Secretary of State, not refused, but an unhelpfully politically charged note in the process for sure.

An inquiry took place, which opened on 6 October 2020 and sat for nine days. The main objectors to the proposals were a group known as Re-Form Heritage, which appeared at the inquiry as a Rule 6 Party, represented by Rupert Warren QC and Matthew Dale-Harris, who called four witnesses including professional evidence on heritage and planning – no “David and Goliath” contest this). Tower Hamlets Council was in support of the proposals (Alexander Booth QC appearing), as was Historic England. David Elvin QC appeared for the applicant.

(Thanks to my Town Legal colleague Tom Brooks for much of the following summary, although any views expressed are mine).

Re-Form argued that:

– Raycliff’s proposals were unacceptable in heritage terms, and would cause, in the language of the NPPF (paras 193-196), “substantial harm” to the significance of the listed building; and

– Re-Form’s alternative vision for the future of the site, as a working foundry for casting both bells and other artistic commissions, was less harmful, so the applications should be refused.

Raycliff’s position was that only a low level of less than substantial harm would be caused by the proposals, that this would be outweighed by their public benefits (heritage and otherwise), and that Re-Form’s idea was undeliverable and unviable.

The inspector concluded that the listed building was “of profound significance” (IR 12.14), noting that all agreed there were elements of the proposals that would cause harm to that significance (IR 12.17), whether substantial (leading to NPPF 194-195) or less than substantial (leading to NPPF 196).

As spelt out by the inspector: the end of the bell foundry business in 2017 was unconnected to the present proposals (“Traditional bell founding on the site…ended for economic reasons mainly to do with a drop in demand for tower bells, and the difficulties, both operational and environmental, the business encountered in operating from a Central London address”); and therefore the starting point for the assessment was a “largely vacant Grade II* listed building that formerly housed traditional bell founding…It is not a situation where a traditional bell foundry is to be closed in order to be replaced by something else”. IR 12.23).

Following the inspector’s conclusion that the proposals cannot be taken to cause harm to the listed building as a result of the closure of the business, the only harm possible was any arising from the physical works now proposed. No harm was found to the other heritage asset in this case, the Whitechapel Conservation Area, and that the hotel extension was said by the inspector to be a “subtle and pleasingly understated” addition (IR 12.52).

The inspector concluded that the harm to the listed building “would be very much at the lower end of the scale of less than substantial” (IR 12.44), would be outweighed by the public benefits of the scheme (albeit with some non-consequential discussion as to how this balancing should be carried out – see below), and so planning permission and listed building consent should be granted.

This advice was accepted by the Secretary of State.

There are some interesting issues arising:

– Obviously, there is no planning control whatsoever to preserve as operational the specific use that was said to be significant in heritage terms – as a “large church bell foundry” (IR 8.46) – clearly the planning system cannot require a business to continue to operate or indeed to prevent other industrial uses of the site, or uses which may be possible by way of permitted development. The Secretary of State concluded that “the end of traditional bell making on the site has…nothing whatsoever to do with the proposals at issue”.

– Re-Form argued that that Raycliff needed to demonstrate that its scheme was the “optimum viable use” of the site (following the reference in NPPF 196). This suggestion was dismissed by the inspector: optimum viable use is an example of the public benefits that are to be weighed against harm in the balancing process, but in such “a situation where the heritage and other public benefits of the proposals so far outweigh the harm they would cause, it appears to me unnecessary” (IR 12.82).

– The inspector followed Bramshill at first instance (Waksman J, 16 December 2019) that not much detail of an alternative scheme for a heritage asset is needed for that scheme to be a relevant consideration. Nonetheless, he found Re-Form’s scheme to be “somewhat sketchy, and lacking in detail [with…] far too many uncertainties” (IR 12.92). Moreover, even if it had been shown to be viable, “the mere presence of an alternative scheme offers no justification to resist a proposal that is otherwise acceptable, and statute and policy compliant” (IR 12.77).

– One of the more surprising aspects of the decision is the inspector going out of his way to endorse the so-called “internal heritage balance” method of assessing heritage harm following Palmer (Court of Appeal, 4 November 2016), despite numerous subsequent judgments emphasising that such an approach should be used with caution (see recently the Court of Appeal judgment on Bramshill which I covered in my 12 March 2021 post).

While the inspector was at pains to make his view clear that such an “internal heritage balance” approach was “perfectly legitimate”, and this was endorsed in the Secretary of State’s letter, it actually made no difference to the conclusion reached.

The inspector thus carried out an initial balancing exercise of heritage harm against heritage benefits, prior to the NPPF 196 test considering the wider public benefits. In doing so, he found that “there would be no harm caused to the special architectural and historic interest of the listed building […and] no need to consider paragraphs 195 or 196 because considered in the round, the proposals would cause no harm to the significance of the designated heritage asset affected” (IR 12.75-12.76).

What the inspector had done, though, was exactly the same as carrying out the NPPF 196 test, and simply stopping after the heritage benefits because the scales were already tipped in their favour, and so there was no need to include the wider public benefits too. In fact, the inspector then carried out the NPPF 196 test doing this anyway (at IR 12.78-12.81), leaving it unclear as to why the “internal heritage balance” approach was taken in the first place.

It’s certainly a topical issue. In the middle of my writing this post, judgment was handed down in Juden v London Borough of Tower Hamlets (Sir Duncan Ouseley, 21 May 2021) – another social media cause celebre, the “mulberry tree” case. See discussion at paragraphs 59 to 87 on ground 3 (“inclusion of heritage benefits when assessing the level of heritage harm”).

– It is common, thanks partly to the shared application form these days, for applications for planning permission and listed building consent to share the same description of development. Unusually, in this case, the inspector sought during the inquiry to understand exactly which works should be the subject of each application, resulting in an amendment to the description for the listed building consent – a useful reminder of the proper scope of listed building consent in section 7 of the Act (for “works which would affect its character as a building of special architectural or historic interest”), and that despite their often parallel consideration by planning authorities, they are separate regimes with separate legislative and policy considerations.

Here was a proposal that was supported by Tower Hamlets officers and members, supported by Historic England, recommended for approval by an independent inspector and approved by the Secretary of State (the decision apparently taken by another minister but “on behalf of” the Secretary of State). In the meantime, commentary in social media and the broadsheet newspapers continues to attack the conclusions reached, repeating arguments that have already been rejected throughout this process.

There are plenty of participants to go at of course – the Secretary of State mentions the Planning Inspectorate (why?); Charles Saumarez-Smith (who appeared at the inquiry) alleges that Historic England “conspicuously failed in their public duty” (how?), and as always everyone has a go at the developer, without putting forward any realistic alternative proposals.

What has led to the Secretary of State’s announcement of a “review of how the Planning Inspectorate and planning policy considers and defends heritage”? An attempt to appease, without implementing substantive changes to the current system, those who wish that somehow a different decision could have been reached? Or something more fundamental? If the latter (and I’m struggling to visualise what form that might take), it needs to get hitched pretty quickly to the planning white paper bandwagon.

Finally, I of course recommend Zack Simons’ 19 May 2021 blog post Old buildings: what’s new in heritage planning? – a brilliant analysis as always.

Simon Ricketts, 21 May 2021

Personal views, et cetera

This week’s 6pm Tuesday 25 May #PlanningLawUnplanned Clubhouse session, provocatively titled, looks more widely at the treatment of planning issues in the media, already with a fascinating list of guest contributors in addition to our usual panel. Invitation to the app here (and, hooray, no longer limited to iphone users).

Have We Got No Planning Bill News For You

Nine months on from that planning white paper, we have seen no external signs of progress.

All eyes on the Queen’s Speech on 11 May 2021. Was there to be a narrowing down of previous options; a reflection on the consultation process; a programme set out of further work to be carried out ahead of the proposed Planning Bill, perhaps some new thinking following longer reflection?

Laws to modernise the planning system, so that more homes can be built, will be brought forward…

Turning to the background notes, there is literally nothing in the section on the proposed Planning Bill could not have been written back at the time of the white paper in August 2020 or that gives any indication as to ministers’ current thinking.

“The purpose of the Bill is to:

Create a simpler, faster and more modern planning system to replace the current one that dates back to 1947, and ensuring we no longer remain tied to procedures designed for the last century.

Ensure homes and infrastructure – like schools and hospitals – can be delivered more quickly across England.

Transform our planning system from a slow document-based one to a more efficient and easier to use digital and map-based service, allowing more active public engagement in the development of their local area.

Help deliver vital infrastructure whilst helping to protect and enhance the environment by introducing quicker, simpler frameworks for funding infrastructure and assessing environmental impacts and opportunities.

The main benefits of the Bill would be:

Providing more certainty for communities and developers, particularly smaller developers, about what is permitted where, through clear land allocations in local plans and stronger rules on design.

Simpler, faster procedures for producing local development plans, approving major schemes, assessing environmental impacts and negotiating affordable housing and infrastructure contributions from development.

Establishing a framework which focuses on positive outcomes, such as environmental opportunities and better designed places.

Digitising a system to make it more visual and easier for local people to meaningfully engage with.

The main elements of the Bill are:

Changing local plans so that they provide more certainty over the type, scale and design of development permitted on different categories of land.

Significantly decrease the time it takes for developments to go through the planning system.

Replacing the existing systems for funding affordable housing and infrastructure from development with a new more predictable and more transparent levy.

Using post-Brexit freedoms to simplify and enhance the framework for environmental assessments for developments.

Reforming the framework for locally led development corporations to ensure local areas have access to appropriate delivery vehicles to support growth and regeneration.

Territorial extent and application

The Bill will extend to the whole of the UK, however the majority of provisions will apply to England.”

In my view there can only be two possible reasons for this “no news” approach:

1. The Government may not yet have reached the necessary decisions – for instance as to how many zoning categories there will be, whether all land will be zoned or just parts of areas; or how this Infrastructure Levy will work. Quite possible. But come on! Nine months, and nothing?

2. Alternatively, the Government may not yet ready to take the political flak from its own that any specific proposals will attract. Despite the lack of any new information the reaction was surprisingly hostile, and even amongst the development industry I only hear at best muted, hedged and qualified support for elements of the white paper: are many politicians or business leaders prepared to be the cheer-leaders for these changes when, inevitably, the going gets politically tough? This will need a plan.

The only “new” element that caught my eye was that the long-flagged proposal to reform environmental assessment processes will now be within the Bill. It is another area where an announcement is overdue. Environment minister George Eustice indicated in his 20 July 2020 speech:

“Later this autumn we will be launching a new consultation on changing our approach to environmental assessment and mitigation in the planning system.”

The consultation never happened. Whether the legislation will indeed not only simplify but “enhance the EU derived framework of environmental assessments for developments” partly depends on what happens with a separate proposal within the forthcoming Judicial Review Bill:

Giving the courts the power to suspend quashing orders in Judicial Review cases, so as to allow defects to be remedied. This will enable the courts to have more flexibility in Judicial Review cases. This may help ensure that, for example, a large infrastructure project is not delayed because an impact assessment has not been properly done”

Steve Quartermain and Lord Matthew Taylor have written about what the Government could now be doing to deliver on many of the objectives of the white paper, without legislation, in their article Government’s Planning White Paper is a slow road to the future (The Independent, 24 March 2021) and I have written about the areas where planning law reform is genuinely needed (but overlooked in the white paper) in my article Please sir, please can we have more planning legislation? (Estates Gazette, 21 November 2020).

I hope we are not now faced with a Bill that is either a fait accompli, given the various areas which genuinely need a great deal more work and engagement, or (as likely) an empty legislative shell, leaving the difficult work for secondary legislation in due course.

Incidentally, as a topical reminder that how the system is operated is as important as how is how it is structured, in the same week as the traditional parading of the Government’s forthcoming legislative programme, we have seen yet another example of the delays to the system that are caused when the Government intervenes in relation to planning applications: the ministerial decision on 13 May 2021 to approve the Whitechapel Bell Foundry application called in on 22 January 2020. Almost 16 months’ unnecessary delay, not to mention much unnecessary cost. Never mind new laws: how much could be achieved by the Secretary of State simply deciding not to call in applications or recover appeals!

But I will leave more detailed commentary on that decision, and on the Secretary of State’s enigmatic subsequent statement on twitter this afternoon, until next week’s thrilling blog post.

Simon Ricketts, 15 May 2021

Personal views, et cetera

This Tuesday we held a #PlanningLawUnplanned Queen’s Speech Clubhouse session. If you attended I hope you found it useful. This Tuesday we’re going to run an essential session about the Clubhouse app itself and how to get the most out of it. All will become clear! Do join us (iphone invitation here if you are not yet a member).

Choiceplace, Wrong Place

Choiceplace Properties Limited v Secretary of State (Dove J, 27 April 2021) amounts to a short and sharp lesson for applicants and their advisers: make sure your application plans are accurate, not just in relation to your development proposals but as to the relationship of the proposals to the existing streetscape or landscape, particularly if a condition of the permission requires that development is to be carried out in accordance with those (scaled) plans.

Planning permission had been granted for a small block of flats to be built in north London. Condition 1 required the development to be carried out in accordance with a set of approved plans. The set included drawing “P.04, street elevations”.

This is an extract from the plan:

Courtesy of London Borough of Barnet planning portal

To quote from Dove J:

“Not long after the permission had been granted the claimant mobilised in order to implement the development. In December 2018, the claimant was advised by the architect that it had retained to prepare detailed construction drawings that the street scene drawing P.04 was inaccurate. In essence, the drawing, which was one of those listed in condition 1 along with the other drawings forming part of the pack accompanying the application, was in error in purporting to show that the proposed development would have a ridge height lower than the neighbouring building 159 Holden Road, when in fact the ridge height of the proposed building would be higher. Whereas the street scene in drawing P.04 showed the buildings stepping down in height from 159 via the proposal to 157, where the ridge height of 157 Holden Road was shown to be lower than the application site proposed building, in fact the proposed building was taller than both of them.”

I suspect that it is quite unusual that an error such as this is spotted pre-construction. The stakes are even higher for all concerned if the discrepancy is spotted at a later stage.

The local planning authority, London Borough of Barnet, took the position that the permitted development could not be lawfully implemented. The parties waved opposing counsel’s opinions at each other. The applicant, Choiceplace, made an application for a certificate of lawfulness of proposed use or development under section 192 of the Town and Country Planning Act 1990 to seek to make good its position. The application was refused by Barnet and the subsequent appeal was dismissed by an inspector.

Some extracts from the inspector’s decision letter:

“In my view the starting point is that when interpreting a condition it should be asked what a reasonable reader would understand the words to mean. In this case it clear to me the development should be built in accordance with the plans. At its simplest this is impossible because to build it in accordance with P.03 and P.06 the building will not look like the building shown in P.04. In other words the plans are inconsistent. The condition doesn’t require the development to be in accord with some of the plans, or parts of the plans, but with the approved plans, and I think it reasonable to imply the word “all” there, again on the basis that is what an ordinary reading of the condition implies.

Starting from this point, it could be argued that the P.04 is merely illustrative, the buildings either side could change shape or size or even be demolished, but that seems to me to be rather missing the point. Firstly, P.04 is clearly not illustrative, it is not a simple sketch purporting to show a view, but is an allegedly scale drawing with the heights of the neighbour at No 159 drawn on to specifically compare to the proposal. Secondly, whether the neighbours can change is irrelevant. The drawing shows the proposed building in a relationship to the neighbours at the time the application was made regardless of any theoretical future changes. That relationship should have been replicable on site on the date the permission was granted and it was not.

If we delve further into the extrinsic evidence to see if there is anything else to suggest that reliance on P.04 would be excessive or in some way unreasonable then it becomes clear, for the reasons given in the Council’s opinion, that the streetscene drawing was important in the determination of the application, which was only allowed by the committee by a narrow margin. Furthermore it is only by detailed analysis of various spot heights across several of the drawings that the errors are revealed. The Council should be able to rely on accurately scaled drawings, especially when the drawing in question is important to determining the acceptability of the proposal.”

Dove J agreed with the inspector:

“In my judgment, there is no reason why the depicted heights of the existing buildings should be regarded as illustrative or somehow excluded from the requirements of condition 1 on the planning consent. As was pointed out during the course of argument, a relationship between a proposed development and the existing height of either adjacent structures or indeed adjacent ground levels is a matter to be accurately depicted on plans accompanying planning permission for good reason. It is at the very least to be assumed to be an accurate depiction, in the absence of any specific text on the drawing indicating that elements of it are not to scale. The Inspector was correct in pointing out that the drawing showed a relationship between the proposed development and surrounding buildings which should have been capable of replication on the site at the time permission was granted and it was not. In short, the development is not capable of being implemented in accordance with the approved drawings because it is not capable of being implemented in a manner which replicates the street elevations both longitudinally and axially which are purported to be shown to scale on drawing P.04. To reach that conclusion does not involve any suggestion that the planning application granted might be capable of controlling the scale or appearance of adjacent dwellings beyond the application on site; it is simply a reflection of the inaccuracy in the plans leading to an inability to construct a development which accords with that which is depicted upon them.”

A simple case but with some potentially far-reaching conclusions for applicants:

1. Of course, be careful that all drawings, plans and written descriptions of your development proposal are accurate, are internally consistent and describe accurately the surrounding environment – particularly where by condition you are required to build in accordance with what has been set out. If there need to be caveats as to accuracy, include them.

2. To what extent has someone, at some remove from the detail, audited whether this is in fact the case and confirmed it, such that you can rely on that confirmation if an issue subsequently arises? It’s not the local planning authority’s job.

3. Always check that you will be able to comply with plans and other details that are set out in planning conditions. The condition here was all encompassing: “The development hereby permitted shall be carried out in accordance with the following approved plans: Site Location Plan; Drawing no. P.01 Rev C; Drawing no. P.02 Rev C; Drawing no. P.03 Rev B; Drawing no. P.04; Drawing no. P.05; Drawing no. P.06 Rev A; Landscaping Scheme Drawing no. TH/A3/1497/LS; Arboricultural Impact Assessment & Method Statement by Trevor Heaps Arboricultural Consultancy Ltd Ref: TH 1497 dated 11th December 2017 including drawing no. TH/A3/1497/TPP; Sustainability Statement by Henry Planning; Planning statement by Henry Planning; Document titled “Holden Road, London, N12 8SP – Part M4(2) Category 2 Accessible and Adaptable Dwellings”. I am always wary of such an approach. For instance, why were documents listed that were not even “plans” and precisely which elements of those statements were to be incorporated into the condition?

Simon Ricketts, 7 May 2021

Personal views, et cetera

NB Next Tuesday’s Queen’s Speech should be interesting, in terms of whether we will see any detail released as to the contents of the proposed Planning Bill and the Government’s proposed way forward, and what else is on the Government’s agenda impacting upon our little world. No surprise that this will be our main clubhouse #PlanningLawUnplanned topic for 6pm that evening. I hope you can join us – if you have an iPhone, here is an invitation.