What Are The Non-Airport Implications Of The Heathrow Ruling?

The Court of Appeal’s approach to the issues in the Heathrow cases last month was certainly a surprise to many.

The court found in the main “Plan B” ruling (27 February 2020) that the Secretary of State had acted unlawfully when, following the procedure in section 5 of the Planning Act 2008, on 26 June 2018 he designated the Airports National Policy Statement. The court’s basis for its finding was that the Secretary of State had not complied with section 5(8):

(7) A national policy statement must give reasons for the policy set out in the statement.

(8) The reasons must (in particular) include an explanation of how the policy set out in the statement takes account of Government policy relating to the mitigation of, and adaptation to, climate change.”

The question was what was “Government policy” in relation to climate change as at 26 June 2018. The court found that the Secretary of State had acted unlawfully in not taking into account “its own firm policy commitments on climate change under the Paris Agreement”.

This is somewhat surprising given that at first instance the Divisional Court (Hickinbottom LJ and Holgate J, no slouches) had found that this submission was unarguable:

In our view, given the statutory scheme in the [Climate Change Act 2008] and the work that was being done on if and how to amend the domestic law to take into account the Paris Agreement, the Secretary of State did not arguably act unlawfully in not taking into account that Agreement when preferring the NWR Scheme and in designating the ANPS as he did. As we have described, if scientific circumstances change, it is open to him to review the ANPS; and, in any event, at the DCO stage this issue will be re-visited on the basis of the then up to date scientific position.” (paragraph 648 of the main judgment at first instance, known as “Spurrier” after the then first claimant, who had represented himself at first instance but had dropped out by the time of the appeal, which is why you will hear the appeal ruling called “Plan B” after the lead appellant, campaign group Plan B Earth).

(For a wider summary of the proceedings at first instance see my 4 May 2019 blog post Lessons From The Heathrow Cases).

The Court of Appeal has ordered that the Airports National Policy Statement “is of no legal effect unless and until the Secretary of State has undertaken a review of it in accordance with the relevant provisions of the Planning Act 2008.”

Heathrow Airport Limited has applied to the Supreme Court to appeal from the ruling although the Secretary of State has not (meaning that any appeal could be fairly irrelevant if the Secretary of State decides to review the NPS in any event). Whether permission to appeal is granted depends on whether the Supreme Court considers that there is an arguable point of law of general public importance.

So this is all significant as regards the proposal for a third runway at Heathrow. According to the Planning Inspectorate website the application for a development consent order under the Planning Act 2008 NSIP procedure is/was expected to be submitted in Q4 2020.

The main function of the NPS was to give formal national policy support to the proposal at Heathrow. The way that the Planning Act 2008 works is that, under section 104, the Secretary of State must decide a DCO application in accordance with any relevant national policy statement “except to the extent that one or more of subsections (4) to (8) applies.

(4) This subsection applies if the Secretary of State is satisfied that deciding the application in accordance with any relevant national policy statement would lead to the United Kingdom being in breach of any of its international obligations.

(5) This subsection applies if the Secretary of State is satisfied that deciding the application in accordance with any relevant national policy statement would lead to the Secretary of State being in breach of any duty imposed on the Secretary of State by or under any enactment.

(6) This subsection applies if the Secretary of State is satisfied that deciding the application in accordance with any relevant national policy statement would be unlawful by virtue of any enactment.

(7) This subsection applies if the Secretary of State is satisfied that the adverse impact of the proposed development would outweigh its benefits.

(8) This subsection applies if the Secretary of State is satisfied that any condition prescribed for deciding an application otherwise than in accordance with a national policy statement is met.

(9) For the avoidance of doubt, the fact that any relevant national policy statement identifies a location as suitable (or potentially suitable) for a particular description of development does not prevent one or more of subsections (4) to (8) from applying.

So the first thing to note is that the NPS would not have given Heathrow Airport Limited a free pass to a consent – in determining the application the Secretary of State would need to determine whether, notwithstanding the June 2018 NPS, the proposal is not in accordance with, for instance, up to date treaty obligations or domestic legislation – exactly the point made by the Divisional Court in the passage I quoted earlier.

This is relevant because the issue in the Heathrow cases very much turned on an historical question – what was the Government’s climate change policy as at 26 June 2018. Legislation and policy has plainly moved on since then, and will continue to move on. I referred in my 10 August 2019 blog post The Big CC to Theresa May’s tightening in June 2019 of the Government’s commitment to reduce greenhouse gas emissions, by making the Climate Change Act 2008 (2050 Target Amendment) Order 2019 which changed the duty of the Secretary of State under the Climate Change Act 2008 from being to ensure that the net UK carbon account for the year 2050 is at least 80% lower than the 1990 baseline, to being at least 100% lower, ie net zero. The target does not include international aviation or shipping: paragraph 10.5 of the explanatory notes published with the order states that there is a “need for further analysis and international engagement through the international networks. For now, therefore we will continue to leave headroom for emissions from international aviation and shipping in carbon budgets…” By the time that any Heathrow DCO application is to be/would have been determined, the Secretary of State would have to take into account climate change legislation and international commitments at the time.

It can all of course get messy/political, as demonstrated by former Energy Secretary Andrea Leadsom’s approval last year, against her inspectors’ recommendations, of the Drax gas-fired power stations DCO, a decision which is now being challenged in the High Court by ClientEarth (see Drax legal case: We’re taking the UK government to court over Europe’s largest gas plant, ClientEarth, 30 January 2020).

Although it would be a risky strategy to adopt, given it would entail acknowledging loss of any formal statutory policy support for Heathrow as the favoured option, Heathrow Airport could in theory decide to proceed with a DCO application without the support of an NPS (this appears to be Gatwick’s strategy with its proposed northern runway). In the absence of an NPS, section 105 applies:

(2) In deciding the application the Secretary of State must have regard to—

(a) any local impact report (within the meaning given by section 60(3)) submitted to the Secretary of State before the deadline specified in a notice under section 60(2),

(b) any matters prescribed in relation to development of the description to which the application relates, and

(c) any other matters which the Secretary of State thinks are both important and relevant to the Secretary of State’s decision.”

How even to begin to scope the appropriate approach to decision-making in that situation…

Any wider relevance?

So does this ruling have repercussions away from Heathrow and airports?

People threaten to bring judicial review proceedings, and often end up bringing them for all sorts of reasons. Lord Reed, President of the Supreme Court, made some topical comments to the House of Lords Constitution Committee last week:

Judges are very well aware of the risk of challenges being brought in what are political rather than legal grounds. They are repelling them and are careful to avoid straying into what are genuine political matters. When this is a matter that is to be considered it should not start from the premise that judges are eager to pronounce on political issues. The true position is actually quite the opposite.” (Law Society Gazette, 4 March 2020).

Since the ruling we have seen these stories:

Environmentalists follow Heathrow ruling by calling on government to end fossil fuel developments (Ecotricity, 4 March 2020) (The Secretary of State has a discretion in section 6 of the 2008 Act as to whether and when to review NPSs, and indeed since June 2019 Government climate change targets have been clear regardless of what the position was at June 2018 – which is surely the only relevance of the Heathrow rulings – if the point made by the prospective claimants is a good one, it has been a good one for some time now).

HS2 legal challenge launched by Chris Packham (Guardian, 3 March 2020) (There is surely no duty on a minister to take into account Government climate change targets in making a decision to continue with the construction of an existing project which has already, phase 1 at least, been authorised by Parliament).

What did it for the Secretary of State in relation to the Heathrow NPS was the specific statutory duty to take into account “government policy” on climate change mitigation and adaptation.

Regardless of whether the Court of Appeal was right to determine that Government support for the Paris Agreement (international) targets could be construed as government policy for any particular domestic targets, there is not the same statutory duty when it comes to the Town and Country Planning Act system.

When it comes to plan-making, section 19(1A) of the Planning and Compulsory Purchase Act 2004 imposes a statutory duty on local planning authorities that development plan documents must include policies that contribute to mitigation and adaptation to climate change, and this duty is reflected in paragraph 149 of the National Planning Policy Framework, stating in footnote 48 that policies should be “in line with the objectives and provisions of the Climate Change Act 2008”.

There are no specific equivalent requirements in relation to decision making, just the general statement in paragraph 148, stating that the “planning system should support the transition to a low carbon future in a changing climate” and “should help to: shape places in ways that contribute to radical reductions in greenhouse emissions”.

Beware those who wave about the Heathrow ruling as some kind of game changer in relation to the battle against climate change. It is certainly a game changer in relation to Heathrow Airport’s aspirations, as to project timescale at the very least, but, wider than that? The Court of Appeal determined that a specific statutory duty, peculiar to the making of NPSs, was breached. The question of whether there was a breach depended on determining what government policy on climate change was in June 2018, when it was not as advanced as it is now. Finally, it is not obvious to me that the Court of Appeal’s conclusions would be safe against an appeal to the Supreme Court – but of course all that could well be largely hypothetical, depending upon what steps the Government now takes.

The awaited national infrastructure plan, which was to be published alongside the budget on 11 March, is to be delayed but reportedly could still be “before May” (Government delays Budget infrastructure plan, BBC, 5 March 2020). It will be interesting to see whether any hints are dropped in our new Chancellor’s budget statement as to the Government’s direction of travel.

Simon Ricketts, 7 March 2020

Personal views, et cetera

Lessons From The Heathrow Cases

In my 15 October 2016 blog post Airports & Courts I made the obvious prediction that publication by the Secretary of State for Transport of the Airports National Policy Statement (“ANPS”) would inevitably lead to litigation. The ANPS is important because under the Planning Act 2008 it sets the policy basis for a third runway at Heathrow to the north west of the current runways (the “NWR Scheme”).

It was always going to be important for the High Court to be able to rise to the (in a non-legal sense) administrative challenge of disposing of claims efficiently and fairly. The purpose of this blog post is to look at how that was achieved (no easy feat) and what we can learn more generally from the court’s approach to the litigation

The ANPS was designated on 26 June 2018 and five claims were brought seeking to challenge that decision:

⁃ A litigant in person, Neil Spurrier (a solicitor who is a member of the Teddington Action Group)

⁃ A group comprising the London Borough of Richmond-upon-Thames, the Royal Borough of Windsor and Maidenhead, the London Borough of Hammersmith and Fulham, Greenpeace and the Mayor of London

⁃ Friends of the Earth

⁃ Plan B Earth

⁃ Heathrow Hub Limited and Runway Innovations Limited [unlike the other claimants above, these claimants argue for an extension of the current northern runway so that it can effectively operate as two separate runways. This scheme was known as the Extended Northern Runway Scheme (“the ENR Scheme”)]

Arora Holdings Limited joined as an interested party to each set of proceedings in pursuance of their case for a consolidated terminal facility to the west of the airport.

The Speaker for the House of Commons intervened in the Heathrow Hub Limited claim to object to various statements made to Parliament and Parliamentary Committees being admitted in evidence.

The first four claims raised 22 separate grounds of challenge. The fifth claim raised a further five grounds of challenge.

As Planning Liaison Judge, ie effectively lead judge within the Planning Court, Holgate J in my view has played an extremely effective role. Following a directions hearing, ahead of a subsequent pre-trial review three months later, he laid down a comprehensive set of directions on 4 October 2018 which provided for:

⁃ the first four claims to be heard at a single rolled up hearing, followed by the fifth claim

⁃ the cases to be heard by a Divisional Court (ie two or more judges, normally a High Court Judge and a Lord Justice of Appeal. In the event, the four claims were heard by a Divisional Court comprising Hickinbottom LJ and Holgate J. The fifth claim was heard immediately afterwards by a Divisional Court comprising Hickinbottom LJ, and Holgate and Marcus Smith JJ.)

⁃ video link to a second court room and (paid for jointly by the parties in agreed proportions) live searchable transcripts of each day’s proceedings

⁃ procedure to be followed in relation to expert evidence sought to be submitted in support of the first claim

⁃ statements of common ground

⁃ amended grounds of claim, with strict page limits and against the background of a request from the judge to “review the extent to which they consider that any legal grounds of challenge previously relied upon remain properly arguable in the light of the Acknowledgments of Service“, and with specific claimants leading on individual issues

⁃ bundles and skeleton arguments complying with strict page limits and other requirements

⁃ payment of security for costs by Heathrow Hub Limited in the sum of £250,000

⁃ cost capping in the other claims on Aarhus Convention principles

The main proceedings were heard over seven days in March, with the Heathrow Hub proceedings then taking a further three days (followed by written submissions). As directed by Holgate J, hearing transcripts were made publicly available.

Less than six weeks after close of the Heathrow Hub hearing, judgment was handed on 1 May 2019 in both case:

R (Spurrier & others) v Secretary of State (Divisional Court, 1 May 2019)

R (Heathrow Hub Limited & Runway Innovations Limited) v Secretary of State (Divisional Court, 1 May 2019)

The transcript of the first judgment runs to 184 pages and the transcript of the second judgment runs to 72 pages.

I am not going to summarise the judgments in this blog post but happily there is no need as the court at the same time issued a summary, which serves as a helpful précis of the claims and the court’s reasoning for rejecting each of them.

The Divisional Court found that all but six grounds were unarguable (the six being two Habitats Directive grounds from the first case, two SEA grounds from the first case and two from the second case (legitimate expectation and anti-competition). “All the other grounds were not considered not to have been arguable: the claimants may apply for permission to appeal against the Divisional Court’s decision concerning those grounds to the Court of Appeal within 7 days. The remaining six grounds were ultimately dismissed. The claimants may apply to the Divisional Court for permission to appeal within 7 days. If the Divisional Court refuses permission to appeal to the Court of Appeal, the claimants may re-apply directly to the Court of Appeal.”

The Secretary of State for Transport gave a written statement in the House of Commons on the same day, welcoming the judgments.

The two judgments will be essential reading in due course for all involved in similar challenges; the 29 grounds, and various additional preliminary points, cover a wide range of issues frequently raised in these sorts of cases and each is carefully dealt with, with some useful textbook style analysis.

In the Spurrier judgment:

– the scope for challenge of an NPS (paras 86 to 90)

⁃ relationship between the NPS and DCO process (paras 91 to 112)

⁃ extent of duty to give reasons for the policy set out in the NPS (paras 113 to 123)

⁃ consultation requirements in relation to preparation of an NPS (paras 124 to 140)

⁃ standard of review in relation to each of the grounds of challenge (paras 141 to 184)

⁃ the limited circumstances in which expert evidence is admissible in judicial review (paras 174 to 179)

⁃ whether updated information should have been taken into account (paras 201 to 209)

⁃ whether mode share targets were taken into account that were not realistically capable of being delivered (paras 210 to 219)

⁃ the relevance of the Air Quality Directive for the Secretary of State’s decision making (paras 220 to 285)

⁃ compliance with the Habitats Directive (paras 286 to 373)

⁃ compliance with the Strategic Environmental Assessment Directive (paras 374 to 502)

⁃ whether consultation was carried out with an open mind (paras 503 to 552)

⁃ whether the decision to designate the ANPS was tainted by bias (paras 553 to 557)

⁃ the relevance of the Government’s commitments to combat climate change (paras 558 to 660)

⁃ whether there was a breach of the European Convention on Human Rights (paras 661 to 665)

In the Heathrow Hub judgment:

⁃ legitimate expectation (paras 113 to 138)

⁃ use of Parliamentary material in the context of Article 9 of the Bill of Rights (paras 139 to 152)

⁃ competition law (paras 157 to 209).

As we wait to see whether any of these claims go further, I note that Arora has commenced pre application consultation ahead of submitting a draft DCO for a “consolidated terminal facility to the west of the airport, which we are calling Heathrow West, related infrastructure and changes to the nearby road and river network.” Now that is going to be another interesting story in due course. I’m not sure we have previously seen duelling DCOs…

Simon Ricketts, 4 May 2019

Personal views, et cetera

Hillingdon JR: Lucky Strike Out?

In R (London Borough of Hillingdon & others) v Secretary of State  (Cranston J, 30 January 2017) the Government achieved an impressive strike out of the first challenge to the proposed third runway at Heathrow, following the Government’s 25 October 2016 announcements. My 15 October 2016 blog post Airports & Courts wins no prizes for predicting a series of such challenges.  
Following the strike out, the draft Airports NPS  was promptly published on 2 February for a 16 weeks’ consultation period. 
However, was this somewhat of a lucky win? The Government’s position, accepted by Cranston J, was that the effect of section 13(1) of the Planning Act 2008 was that there can be no legal challenge of a Government announcement of a decision to publish a draft NPS, but that any challenge instead has to be made within a six week window following final designation of the NPS.
Section 13(1) provides as follows: 
“A court may entertain proceedings for questioning a national policy statement or anything done, or omitted to be done, by the Secretary of State in the course of preparing such a statement only if –



(a) the proceedings are brought by a claim for judicial review, and

(b) the claim form is filed [before the end of] the period of 6 weeks beginning with [the day after] —

 
(i) the day on which the statement is designated as a national policy statement for the purposes of this Act, or



(ii) (if later) the day on which the statement is published.”

So was the 25 October 2016 announcement something done “in the course of preparing” an NPS? Hmm.
Was the operation of section 13(1) intended to be so different from sections 23 and 25 of the Acquisition of Land Act 1981, which provide for a six week deadline for challenging a compulsory purchase order from publication of notice of its confirmation and the exclusion that a CPO otherwise “shall not, either before or after it has been confirmed, made or given, be questioned in any legal proceedings whatsoever“? So, according to the 1981 Act, no challenges before the CPO has been made but the Supreme Court in R (Sainsbury’s Supermarkets Limited) v Wolverhampton City Council  (12 May 2010) has entertained a judicial review of a council’s resolution to make a compulsory purchase order. Is the drafting within the 2008 Act distinguishable from the 1981 Act? Even if it is, where is the logic? With CPOs the widely understood risk of JR of the resolution to make a CPO, before section 25 cuts in to prevent further challenges until the order has been finally confirmed or rejected, is the reason why acquiring authorities commonly seek to leave as little time as possible between that final resolution and making the order. There is no reference in Cranston J’s judgment to this (surely) analogous process

.

Whatever the rights and wrongs, the decision to go for a strike out – always high stakes, given the risk of adding to the time needed to dispose finally of the challenge or at least the risk of egg on face – has so far proved to be the right one, although I do not know whether the claimant local authorities plan to appeal. Even if cleared for take off, the proceedings would in any event face a bumpy ride give that judicial review is a remedy of last resort and it could be said that the claimant authorities should first be making representations to the draft NPS before resorting to litigation?
It was a good week all round for Heathrow. By a decision letter dated 2 February 2017  the Secretaries of State for Communities and Local Government and Transport allowed an appeal by the airport, permitting enabling works to allow it to implement “full runway alternation during easterly operations” (ie, basically, regular easterly departures from the northern runway), after a June 2015 (yes 2015) inquiry and initial refusal by Hillingdon Council in March 2014 (yes 2014) of the airport’s planning application.  
Finally, a post script on challenges to CPO decisions, and to my 22 September 2016 blog post Regeneration X: Failed CPOs. Local Government Lawyer reports that after an oral hearing Collins J has granted Southwark Council permission to challenge the Secretary of State’s decision not to confirm the Aylesbury Estate CPO, Dove J having previously refused permission on the papers. Collins J apparently also “proposed that a meeting should be held between the two parties before any litigation began, considered that it would be unlawful for Southwark to offer more than was allowed under the Compensation Code, and recognised that the decision had significant knock-on effects for other schemes“. It would be no surprise at all to me if the decision is eventually overturned. 
You may now unfasten your seat belts.

Simon Ricketts 4.2.17

Personal views, et cetera

Airports & Courts

The Government’s long awaited decision on airport expansion in the south east, following its interim 10 December 2015 statement, finally seems imminent. A Guardian 9 October 2016 story speculates that the decision will be taken at a cabinet meeting on 17 October (presumably meaning an announcement the following day) and that Heathrow will be favoured, in which case, according to an Independent story the same day, Gatwick will pursue expansion in any event.
New Civil Engineer on the hand speculates that both Heathrow and Gatwick will get the go ahead:
“It is believed that the announcement will be made on 18 October, with government giving the green light to a third runway at Heathrow immediately and also allowing Gatwick to expand with a second runway within the next five years.

Gatwick’s 30-year agreement with local authorities not to expand is due to expire in 2019.

It is also understood that government will urge Birmingham airport to advance its proposals for an additional runway.”

Whatever the timing and content of the announcement, two things are sure:

1. The process of turning the announcement into reality will be a slow and complex process. The Government confirmed in its 10 December 2015 statement that the DCO rather than Hybrid Bill process would be used. The first step will be an Airports national policy statement to form the policy basis for a DCO application or applications to be made in due course. Once the announcement is made I will cover in a future blog post the potential complexities, which would be acute were both Heathrow and Gatwick to proceed, in terms of the coordination required between competing promoters, but equally difficult if only one airport is favoured leaving the other to object, challenge and seek to promote its own proposals independently. 

2. There will inevitably be litigation at each administrative step of the process, particularly ahead of the formal submission of any DCO application (because any challenges to that process, once it is underway, can only be brought once it has concluded). The litigation will be entangled with (1) ongoing issues as to the Government’s non-compliance with the EU Air Quality Directive (2) a slowly changing basis over coming years as to the extent to which UK environmental laws are underpinned by EU legislation (3) continuing efforts by the Government to speed up the judicial review process and discourage unmeritorious claims. 

Aside from the potential for the airport operators themselves to resort to litigation in response to the forthcoming decision, a number of campaign groups have also made their positions clear. For instance: 
– Teddington Action Group has restated on 11 October its threat of judicial review should one of the two Heathrow options be chosen, alleging bias on the part of the chair of the Airports Commission, Sir Howard Davies.
– Gatwick Area Conservation Campaign has written to the Secretary of State for Transport on 4 August 2016 threatening judicial review, referring to John Steel QC having advised that “there are a number of potential grounds able to be considered which are sound, including that a decision to choose Gatwick as the location for additional runway capacity in the South East, if based on political expediency, would be irrational”. They assert that they expect to be supported by “two County Councils and seven Borough and District Councils” as well as a number of MPs. 


Of course, resorting to the courts to try to stop airport expansion is nothing new. For instance:
R (Hillingdon LBC) v Secretary of State for Transport  (Carnwath LJ, 26 March 2010) – the challenge by various local authorities to the Government’s 2009 decision (abandoned following the 2010 General Election) to proceed with a third runway at Heathrow. 
R (Sanders) v Airports Commission and Secretary of State for Transport  (Patterson J, 2 December 2013) – Stop Stansted Expansion’s unsuccessful challenge to Airport Commission’s sift criteria on which its shortlist was to be based, again alleging bias on the part of a member of the Commission.

R (Stop Stansted Expansion) v Secretary of State for Transport  (Sir Thayn Forbes, 13 March 2009) – the same group’s unsuccessful challenge to the Secretary of State’s decision in 2009 to allow planning appeals increasing the cap on passenger numbers to 35m per annum (a cap which Stansted Airport’s owner MAG is currently planning to apply to increase, according to a Telegraph September 2016 piece ).

R (Griffin) v London Borough of Newham  (Court of Appeal, 20 January 2011) – Fight The Flights’ unsuccessful challenge to Newham Council’s 2009 decision to increase the number of permitted flights to up to 120,000 per annum (since when of course the Secretary of State has now allowed a planning appeal for expansion of the airport in a decision letter dated 27 July 2016).

RSPB and Lydd Airport Action Group v Secretary of State and London Ashford Lydd Airport  (Ouseley J, 16 May 2014) – unsuccessful challenges to the Secretary of State’s 2013 decision to allow a planning appeal for expansion of London Ashford Airport at Lydd. 

– R (Barraud) v CAA (2015), an unsuccessful challenge by campaign group Gatwick Absolutely NOT, again advised by John Steel QC, to the Civil Aviation Authority’s decision to implement airspace changes, on the basis of lack of consultation, referred to in a 39 Essex chambers update, where an appeal to the Court of Appeal appears to be in abeyance according to the campaign group’s website.

 This list should be depressing for all of us. From one perspective, these cases, largely unsuccessful in achieving anything but delaying projects (and perhaps unnecessarily raising the hopes of those asked to crowdfund the appointed lawyers) demonstrate the dead hand of the judicial review process on controversial decision and projects. How can we make progress with any real pace when political sclerosis is then followed by years of public law litigation? On the other hand, how can we balance economic, environmental and transportation priorities in a way that does not lead to entrenched opposition and allegations of inconsistency? And, taboo question, are some projects so huge and so political that the unwritten legal burden of proof on the part of a claimant becomes almost impossibly high? Establishment of the Davies Commission was a valiant attempt to de-politicise what was always going to be a controversial process. Unfortunately we are back where we always were: mired in politics, lawyers at hand. 

Simon Ricketts 15.10.16
Personal views, et cetera