Pace Making: Progress At PINS

The Planning Inspectorate has certainly been moving at pace to improve its inquiry appeal processes following Bridget Rosewell’s independent review of planning appeal inquiries, which I covered in detail in my 15 March 2019 blog post Accelerated Planning.

The move to a system of imposing inquiry dates has predictably created the greatest fuss, although is possibly the change that will have the most positive effect in terms of cutting out hiatuses caused by the inevitable sparring between parties as to counsel, team and venue availability. The Planning Inspectorate’s latest 3 May 2019 update addresses that issue head-on:

The Planning Inspectorate is continuing to make good progress with taking forward the recommendations in the Independent Review of Planning Appeal Inquiriesand have now begun increasing the number of inquiry appeals being placed into this new way of working. There are clear benefits in progressing with implementing some of the recommendations and we thought it would be helpful to all concerned to explain our reasons.

To begin with, there can be little doubt that the principal thrust of the Review – to significantly shorten the time between receipt of an inquiry appeal and its final decision – is a significant improvement. To this end, we have been able to appoint more Inspector resource to inquiry appeals, than was envisaged in March when we announced the “pilot”, which has enabled us to bring most of these appeals into the process.

Some parties to the appeals have questioned why we have imposed inquiry dates when informing them of the ‘Start’ of the appeal and the name of the appointed Inspector. These letters are sent to the appeal parties as soon as possible after receipt of an inquiry appeal and have generally set the inquiry date to be between 13-16 weeks of the ‘Start’ date. This has been a significant innovation of the new process and provides the parties with clarity as to timescales from the outset.

To implement the recommendations of the Rosewell Review we must move away from our “bespoke” arrangements which gave specific provision for the parties to agree an inquiry date after an appeal had been submitted. Instead, now we are taking the lead in setting an inquiry date at the earliest opportunity, and this has led some parties to ask if there could be a degree of flexibility after the date had been fixed, or whether they could be given time to negotiate a new date.

We appreciate that this new procedure, for affected appeals, is very different to the way inquiry appeals were managed previously, and that some of the recommendations may be challenging, for everyone involved in the appeal. But it would be difficult to deny the significant advantages that an early inquiry date – and thus an early decision date – will bring to all concerned with the process. We will of course consider whether wholly exceptional circumstances are demonstrated by the parties to explain the unreasonableness of the inquiry date that has been set, but at the same time momentum must be maintained if the Review is to pay the dividends it promises.

The inquiry dates that are now being set give confidence to expect that those appeals will be decided in accordance with the timescales set out in Recommendation 21 of the Rosewell Report.

Recommendation 21 was as follows:

“21.The Planning Inspectorate should adopt the following targets for the effective management of inquiry appeals from receipt to decision

(a) Inquiry appeals decided by the inspector
Receipt to decision – within 24 weeks – 90% of cases Receipt to decision – within 26 weeks – remaining 10% of cases

(b) Inquiry appeals decided by the Secretary of State
Receipt to submission of inspector’s report – within 30 weeks – 100% of cases”

If we can move to a situation where these targets are met, I will have a lot of happy clients. In recent years, the unpredictability has been difficult to explain.

In the current pilot cases, PINS is seeking for inquiries to commence within a 13 to 16 week window of the start date.

And what if your advocate or a particular witness is not available? First, we are going to need to factor that into our pre-inquiry preparations: Who is the sub? Has someone else, a good junior, been shadowing everything such that they can step in or assist with the briefing of someone else? Secondly, surely we need to move away from the cult of personality. I suspect the fact that the system is so unfathomable for many clients increases their sense that as long as they hang onto X, Y or Z QC and A, B or C expert witness they will get through it. All credit to X, Y and Z, and A, B and C, but there are plenty of good barristers and advocates, and of course expert witnesses, at all levels. I suspect there may be a problem with your case if only one advocate (and only one “independent” expert witness) is capable of winning it. Additional costs in double-handling or re-briefing should still be outweighed by the overall cost and time savings if we all get this right.

Of course, speedier inquiry dates represent only one aspect of the changes. The Planning Inspectorate’s Independent Review of Planning Appeal Inquiries – Action Plan (April 2019 update), a document which will be regularly updated, sets out comprehensively the other changes being introduced, many of them with immediate effect.

The biggest ones for people to be aware of at the moment include:

⁃ the firm advice that appellants need to be notifying the relevant local planning authority, copying in PINS, at least ten days before submitting an appeal where they consider that the appeal should be dealt with by way of inquiry. This is important because PINS then requests a view from the authority on whether an inquiry is appropriate, within one day of receiving the appeal (in the current interim stage of bringing in the reforms this is within three days). In turn PINS can then issue the start date for the appeal, from which procedural deadlines flow, within five working days of receipt of the appeal rather than the average of seven weeks taken in 2017/2018! After six months of monitoring whether appellants are routinely giving ten days’ advance notice, the Government may take steps to introduce legislation to make it mandatory, so I think we should all play nicely?

⁃ early case management engagement from the inspector, within seven weeks of the start date, which will increasingly be by way of a conference call between the inspector and the parties (informed by a pre-conference note and agenda), followed by the inspector issuing “clear directions to the parties about the final stages of preparation and how evidence will be examined” no later than eight weeks after the start date.

⁃ the inspector’s directions to include identifying the “key matters in contention, where cross-examination of witnesses is required“, and decisions as to whether a topic by topic approach to the calling of evidence is required. We can expect a range of issues to be dealt with by way of roundtable sessions, without cross-examination.

⁃ encouragement for potential rule 6 parties to be identified at an earlier stage.

⁃ consultation is taking place so as to achieve improved and timely statements of common ground so that they can properly inform preparation of proofs of evidence.

⁃ greater focus on deadlines and indeed “MHCLG will look at the policy for the award of costs to see whether it can be extended to include a fine type of award, such as when evidence is not submitted on time“.

Christopher Young QC wrote an interesting post on LinkedIn this week, setting out his, favourable, experiences of and reactions to what he believes to have been the first Rosewell pilot case, an appeal by Bloor Homes in Penkridge, South Staffordshire. There is nothing unusual about the 3 May 2019 decision letter but the inspector had provided a pre-inquiry note indicating that issues relating to landscape impact and loss of agricultural land should be dealt with by roundtable session, and indicating that she would “prepare an agenda for those sessions based on the submitted proofs of evidence, focusing on the areas where there is disagreement“.

I’m not sure whether this was a formal PINS Rosewell pilot, as the pre-inquiry note predated the publication of the final report and the PINS announcement as to its pilot, but clearly this is a sign of things to come. As Chris notes, roundtable sessions will inevitably become more common. Chris’ inquiry was programmed for four days but only took two and a half days (with the final half day being taken up by closing submissions) – an indication perhaps of how a more directed approach by an inspector can cut timescales and therefore cost.

Incidentally, this is not meant as any reflection on Chris, who is one of the absolute best at nailing points comprehensively whilst quickly, but…

Do advocates’ closing submissions need to be quite so long? If the inspector were to impose a sensible word limit, would that not serve to reduce the current arms race? I was at an inquiry a few years ago when our counsel prepared 70 pages of closing submissions, which he then read out, in full. Very different from my memories of the late Roy Vandermeer QC, who famously regularly made his closing submissions without notes (after a long housing inquiry, as a pupil barrister I once had the impossible task of constructing a note of his submissions to provide them afterwards to the inspector. I looked at my scribble and despaired). I know it is the opportunity to encapsulate the party’s final position on all of the relevant issues and to make sure the inspector has one final chance to indicate if anything is not clear, but surely a little nudge from the inspector sometimes would not go amiss? The closing submissions process also places an enormous burden on the advocate, usually entailing lengthy overnight work which is not usually even separately charged!

For a broader summary of the current appeals system, I also recommend the 22 March 2019 House of Commons briefing paper Planning appeals in England.

There is also now a PINS video explaining how to take part in a planning inquiry (23 May 2019).

And that is this week’s news. Oh and our Prime Minister, for whom the housing crisis was apparently the “number one domestic priority” resigned.

Simon Ricketts, 25 May 2019

Personal views, et cetera

Slow Claim Coming: Limiting JRs

To live outside the law, you must be honest

(Bob Dylan)

This blog post covers:

⁃ the principles to be applied in relation to bringing a late claim for judicial review

⁃ the Environmental Audit Committee’s scrutiny of the enforcement and JR aspects of the draft Environment (Principles and Governance) Bill

⁃ The Supreme Court’s ruling on legislative provisions that seek to exclude the right to legal challenge.

Exciting, not?

Late JR claims

My 7 April 2018 blog post Fawlty Powers: When Is A Permission Safe From Judicial Review? looked at the whole question of JR time limits and referred to the High Court’s ruling in the Thornton Manor case, where the court allowed a claimant to bring a claim for judicial review more than five and a half years after the decision complained of.

That ruling has now been upheld in R (Thornton Hall Hotel Limited) v Wirral MBC (Court of Appeal, 30 April 2019).

Do read my previous blog post, or more reliably the judgment itself, for an account of the exceptional facts with which the court was faced. In deciding whether the judge was wrong to extend time for the claim to be brought, the Court of Appeal helpfully set out the principles to be applied:

(1) When a grant of planning permission is challenged by a claim for judicial review, the importance of the claimant acting promptly is accentuated. The claimant must proceed with the “greatest possible celerity” – because a landowner is entitled to rely on a planning permission granted by a local planning authority exercising its statutory functions in the public interest.”

(2)  When faced with an application to extend time for the bringing of a claim, the court will seek to strike a fair balance between the interests of the developer and the public interest (see Sales L.J. in Gerber, at paragraph 46). Where third parties have had a fair opportunity to become aware of, and object to, a proposed development – as would have been so through the procedure for notification under the Town and Country Planning (General Development Management Procedure) Order 2010 (“the 2010 Order”) – objectors aggrieved by the grant of planning permission may reasonably be expected to move swiftly to challenge its lawfulness before the court. Landowners may be expected to be reasonably alert to proposals for development in the locality that may affect them. When “proper notice” of an application for planning permission has been given, extending time for a legal challenge to be brought “simply because an objector did not notice what was happening” would not be appropriate. To extend time in such a case “so that a legal objection could be mounted by someone who happened to remain unaware of what was going on until many months later would unfairly prejudice the interests of a developer who wishes to rely upon a planning permission which appears to have been lawfully granted for the development of his land and who has prudently waited for a period before commencing work to implement the permission to ensure that no legal challenge is likely to be forthcoming …” (see Sales L.J. in Gerber, at paragraph 49). When planning permission has been granted, prompt legal action will be required if its lawfulness is to be challenged, “unless very special reasons can be shown ...””

“(3)  Developers are generally entitled to rely on a grant of planning permission as valid and lawful unless a court has decided otherwise (see Sales L.J. in Gerber, at paragraph 55). A developer is not generally required “to monitor the lawfulness of the steps taken by a local planning authority at each stage of its consideration of a planning application””.

“(4)  What is required to satisfy the requirement of promptness “will vary from case to case”, and “depends on all the relevant circumstances”. If there is a “strong case for saying that the permission was ultra vires”, the court “might in the circumstances be willing to grant permission to proceed”, but “given the delay, it requires a much clearer-cut case than would otherwise have been necessary” (see Keene L.J. in Finn-Kelcey, at paragraphs 25 to 29).”

“(5)  The court will not generally exercise its discretion to extend time on the basis of legal advice that the claimant might or should have received.”

“(6)  Once the court has decided that an extension of time for issuing a claim is justified and has granted it, the question cannot be re-opened when the claim itself is heard.”

“(7)  The court’s discretion under section 31(6)(b) requires an assessment of all relevant considerations, including the extent of hardship or prejudice likely to be suffered by the landowner or developer if relief is granted, compared with the hardship or prejudice to the claimant if relief is refused, and the extent of detriment to good administration if relief is granted, compared with the detriment to good administration resulting from letting a public wrong go unremedied if relief is refused…8)  It being a matter of judicial discretion, this court will not interfere with the first instance judge’s decision unless it is flawed by a misdirection in law or by a failure to have regard to relevant considerations or the taking into account of considerations that are irrelevant, or the judge’s conclusion is clearly wrong and beyond the scope of legitimate judgment

“(8)  It being a matter of judicial discretion, this court will not interfere with the first instance judge’s decision unless it is flawed by a misdirection in law or by a failure to have regard to relevant considerations or the taking into account of considerations that are irrelevant, or the judge’s conclusion is clearly wrong and beyond the scope of legitimate judgment”

Applying these principles:

The extension of time sought in this case – an extension of more than five years from the date of the challenged decision – is, to use the judge’s word, “extreme”. That is undeniable. As the authorities show, it would only be in the most unusual circumstances that such an extension would ever be granted (see, for example, Schiemann L.J. in Corbett, at paragraph 14; and Hobhouse L.J. in ex p. Oxby, at pp.294 to 296 and 302 to 303). It is, in our view, very important to emphasise this. One cannot say, however, that the court’s power to extend time is automatically extinguished after any given period has elapsed. We are concerned here with a judicial discretion, not a fixed statutory limitation. A clear theme in the relevant case law, as one would expect, is that in every case where delay has occurred the court must look closely at all the relevant facts in the round. The facts will vary widely from case to case. In Corbett a total delay of six years was not in itself fatal to the granting of relief, but it was held that there was no longer a need to quash the planning permissions because they had in the meantime been modified by an order under section 100 of the 1990 Act, made by the Secretary of State, and a quashing order would deny the landowners the compensation due to them for the modification. In ex p. Oxby this court granted relief after a delay of about two years, during which the existence and facts of the unlawfulness infecting the local planning authority’s decision emerged. Generally, of course, very late challenges will not be entertained. However, as Sales L.J. said in Gerber (at paragraph 49), in a particular case there may be “special reasons” to justify the extension sought. To say, as this court did in Connors (at paragraph 87), that an exercise of judicial discretion to allow “very late challenges” to proceed in planning cases will “rarely be appropriate” implies that sometimes it may be appropriate – and necessary in the interests of justice.

There can be no doubt that the circumstances of this case, viewed as a whole, are extremely unusual. Indeed, we would go further. They are unique. The question for us, however, is whether, in combination, they can properly be said to amount to an exceptional case for extending time to allow the challenge to be brought before the court. In our view, in agreement with the judge, they clearly can.”

Factors in this case:

“The first point to be made, and a crucial one, is that the scope of the proceedings in this case is not the usual scope of a claim for judicial review in the planning context. As Mr Alan Evans for the council accepted, and as the judge recognised, it is beyond dispute that the planning permission under challenge ought not to have been issued without its conditions. It was issued in that form without lawful authority.

“This is not a case […] in which the practical effect of the unlawfulness was immediate upon the grant of planning permission.”

“We accept, as all three parties submit, that the council acted unlawfully in concealing its error. It initially attempted to put matters right by generating a fictitious decision notice and manipulating the planning register. Whether its intention was to reverse its error or to obscure it, the effect of the action it took was only to disguise what it had in fact done. It has not, however, resisted the claim. It could, of course, have done a good deal more than it has. It might, for example, have made use of its statutory power of revocation under section 97 of the 1990 Act, or its power to make a discontinuance order under section 102 – though this could have given rise to a claim for compensation by Thornton Holdings. It might have been able to deploy its powers of enforcement at an appropriate stage. It might have brought the matter before the court itself by a timely claim for judicial review issued in the name of a councillor – as was done, for example, in ex p. Oxby. It did none of those things, and even now it shows no such inclination. However, it now acknowledges that the decision notice it issued on 20 December 2011 was, and remains, clearly invalid. Far from resisting the challenge, or adopting a neutral stance, it has actively supported the claim, urged the judge to quash the planning permission, and has appeared in this court to resist the appeal. That is another highly abnormal feature of these proceedings.”

It is also, we think, a factor of considerable weight in this case that Thornton Holdings were well aware from the outset that the planning permission had been wrongly issued, and knew precisely what the council’s error had been.”

“In the circumstances, contrary to the argument presented to us by Mr Christopher Lockhart- Mummery Q.C. for Thornton Holdings, we cannot accept that they have suffered any material hardship or prejudice as a result of the delay in the claim being issued. Indeed, if anything, the delay worked in their favour, in the sense that it enabled them to take advantage of an unrestricted grant of planning permission that they knew the council had never resolved to grant. That too is a most unusual feature of this case, in sharp distinction to others – such as Finn-Kelcey, Gerber and Connors – where the court has rejected lengthy extensions of time. The reality is that, from December 2011 until the judge’s order, Thornton Holdings had the benefit of a more generous grant of planning permission than would have been so if the council had not mistakenly issued the decision notice it did. If at any stage they were concerned about the risk of the council’s error being discovered and a claim for judicial review being made, they decided to operate in the knowledge of that risk, and in spite of it.”

The late claim was allowed. But the court has set out its reasoning carefully, such that I cannot see that the ruling will in any way open the floodgates to a greater risk of late, unexpected, challenges.

OEP JRs

My 22 December 2018 blog post The Office For Environmental Protection covered DEFRA’s draft Environment (Principles and Governance Bill) and in particular the proposal in the draft Bill that the Office for Environmental Protection once established could bring judicial reviews in its own right, outside usual judicial review timescales.

The House of Commons Environmental Audit Committee has now published its report on its pre-legislative scrutiny of the draft Bill (25 April 2019). On the proposed judicial review procedure there is this passage in relation to the OEP’s proposed enforcement powers, including potential to seek judicial review:

The UK Environmental Law Association (UKELA) told us the proposed notice procedures are very slow, with two-month time periods for response. It said that if a breach is serious or ongoing, this could be too long a delay before court action can be taken by the OEP. Tim Buley agreed that since the time limit for judicial review is very strict, “three months ordinarily, six weeks in some environmental contexts”, it would not be appropriate to have it at the end of the process while the OEP has been conducting its investigation and the harm may have already happened. UKELA supported the OEP having a power to make an emergency application for judicial review and Tim Buley said the OEP should have the ability to bring a judicial review at the start of the process. Professor Macrory outlined that it would be helpful for the OEP to have an additional power to be able to intervene in environmental judicial reviews undertaken by other parties. He said that the Equality and Human Rights Commission (EHRC) which has such powers under Equality Act 2006, has made very effective use of them.”

The Committee recommended as follows:

We recommend that:

The Bill should allow the Office for Environmental Protection to bring a judicial review at the start of the process in rare cases where a delay could cause further environmental harm.

The Bill should specify that the Office for Environmental Protection bringing enforcement proceedings does not prevent others who wish to bring a judicial review.

The Office for Environmental Protection should be given the power to act as an intervener in environmental judicial reviews undertaken by other parties.

Clauses 22 and 23 should be amended to include an obligation on the Office for Environmental Protection to act on responses to information or decision notices, or to explain to the complainant why no further action has been taken. This would provide a ratcheting approach to enforcement.

Overall, the enforcement procedure lacks imagination and the Government must consider alternative mechanisms. We have heard compelling evidence that there should be an expanded role for the First-tier Tribunal. This would help to resolve more cases before the need to apply for judicial review.

We recommend the Government looks further into a bespoke enforcement procedure and an expansion of the role and remit of the General Regulatory Chamber in the First-tier Tribunal. For example, where the Office for Environmental Protection is able to issue notices (at first advisory, then latterly binding) with a range of compliance recommendations, to which the public authority must then comply, or set out proportionate reasons why not. The Office for Environmental Protection would then be able to challenge a decision not to comply with the notice at the tribunal. The tribunal would undertake a substantive review of the authority’s decision not to comply with the notice. Any failure to comply with a decision should amount to contempt and be referable to the Upper Tribunal. Section 202 of the Data Protection Act 2018 provides a useful guide as to how this could be achieved in the legislation.”

Ouster clauses

Finally, superficially away from planning law but very relevant to bear in mind for any future re-framing of the system, the Supreme Court handed down judgment last week in R (Privacy International) v Investigatory Powers Tribunal (Supreme Court, 15 May 2019), a significant public law case as the legal effectiveness (or not) of “ouster” clauses in legislation, which seek to limit or remove rights to challenge in the courts matters carried out pursuant to the particular legislation. The strict six week time limit in judicial review in relation to decisions made pursuant to town and country planning legislation is of course a limitation. Such limitations have been held to be reasonable and permissible, as opposed to outright exclusions – held not to be legally effective by a 3 – 2 majority in the House of Lords in the 1968 Anisminic v Foreign Compensation Commission case.

The Privacy International case concerned the legal effectiveness or not of Parliament’s attempt in legislation to prevent legal challenges to decisions of the tribunal which hears complaints about, amongst other matters, general warrants granted to government agencies to intercept electronic communications.

The Investigatory Powers Tribunal (“IPT”) is a special tribunal established under the Regulation of Investigatory Powers Act 2000 (“RIPA”) with jurisdiction to examine, among other things, the conduct of the Security Service, the Secret Intelligence Service and the Government Communications Headquarters (“the intelligence services”). Section 67(8) provides:

“Except to such extent as the Secretary of State may by order otherwise provide, determinations, awards, orders and other decisions of the Tribunal (including decisions as to whether they have jurisdiction) shall not be subject to appeal or be liable to be questioned in any court.””

“There is an obvious parallel with the “ouster clause” considered by the House of Lords in the seminal case of Anisminic Ltd v Foreign Compensation Commission [1969] 2 AC 147 (“Anisminic”). Section 4(4) of the Foreign Compensation Act 1950 provided:

“The determination by the commission of any application made to them under this Act shall not be called in question in any court of law.””

In the course of lengthy discussion in the judgments as to the extent of the courts’ power to override legislative limitations as to legal challenge, the planning system gets a quick specific mention:

“...the courts have not adopted a uniform approach, but have felt free to adapt or limit the scope and form of judicial review, so as to ensure respect on the one hand for the particular statutory context and the inferred intention of the legislature, and on the other for the fundamental principles of the rule of law, and to find an appropriate balance between the two. Even if this was not always the way in which the decisions were justified at the time, it may be seen as providing a sounder conceptual basis. Thus in the planning cases, it having been accepted that the statutory grounds cover all the traditional ground of judicial review, there is no difficulty in holding that the six-week time-limit provides a proportionate balance between effective judicial review, and the need for certainty to enable such decisions to be acted on with confidence.”

The Supreme Court held by a 4 – 3 majority that the absolute prohibition on legal challenge in the Regulation of Investigatory Powers Act was not legally effective.

No doubt a blow to any future governments looking to sidestep the undoubted inconvenience to their activities that judicial review represents. But fundamentally important for all of us who worry how tempting it would be for the courts’ role as a check on the unjustified use of state power, to be neutralised in various areas of legislation.

Interesting to see that the Policy Exchange think tank, with its free market views on the planning system, popped up to denigrate the Supreme Court for allowing the appeal:

Professor Richard Ekins, head of thinktank Policy Exchange’s Judicial Power Project, said the ruling ‘undermines the rule of law and violates the sovereignty of parliament’.  He said: ‘A majority of the court has chosen to misinterpret an ouster clause – the statutory provision which expressly limits the High Court’s jurisdiction to review decisions of the Investigatory Powers Tribunal. Parliament chose to limit judicial review by creating a specialist tribunal to consider complaints against the intelligence services. It is not the Supreme Court’s place to unravel this choice.'” (Law Society Gazette, 15 May 2019).

You don’t need a weatherman to know which way the wind blows.

Simon Ricketts, 18 May 2019

Personal views, et cetera

Pic courtesy Bob Dylan

Far Far Away: Slade Green SRFI

Two years after my 6 May 2017 blog post Slow Train Coming: Strategic Rail Freight Interchanges In The South East, progress remains slow.

I referred in my blog post to the ongoing saga of the Howbury Park (now known as Slade Green), strategic rail freight interchange scheme promoted initially by Prologis (who obtained a, now time expired, permission on appeal in 2007) and now by Roxhill.

The site straddles the boundaries of the London Borough of Bexley and Dartford Borough Council. (The effective boundary is the River Cray, with the elements of the scheme within Dartford’s administrative boundaries being an access road and bridge over the river). At the time of my blog post, Dartford had resolved to refused planning permission. Bexley had resolved to grant planning permission but the Mayor of London was considering whether to intervene.

The Mayor on 17 July 2017 directed Bexley to refuse the application, on this ground:

The proposal is inappropriate development in the Green Belt and very special circumstances have not been demonstrated which would clearly outweigh the harm to the Green Belt by reason of inappropriateness, and any other harm. The development is therefore contrary to Policy 7.16 of the adopted London Plan 2016 and the National Planning Policy Framework 2012.”

Dartford’s reasons for refusal additionally related to the likely effects of additional traffic on air quality and congestion detrimental to the quality of life of the community in Deptford.

Roxhill appealed. The appeals were recovered for the Secretary of State’s own determination on 7 November 2017 for the reason that they related to proposals for significant development in the Green Belt. An inquiry was held over 18 days between June and September 2018.

The Secretary of State issued his decision letter on 7 May 2019. He dismissed the appeals. He found that the scheme was not in accordance with the relevant development plans. “He has gone on to consider whether there are material considerations which indicate that the proposal should be determined other than in accordance with the development plan.

25.In this case the Secretary of State considers that the harm to the Green Belt from inappropriate development carries substantial weight against the scheme and the effect on the character and appearance of the local area carries significant weight along with the adequacy of the proposed rail link and the effect on existing/future passenger rail services. Significant weight is also given to the effect on the convenience of highway users.

26.The Secretary of State considers that the provision of social economic benefits of the scheme has overall limited weight and the resulting net biodiversity gain has moderate weight.

27.The Secretary of State considers that the benefits of the scheme do not outweigh the harm to the Green Belt by reason of inappropriateness and any other harm, and so very special circumstances do not exist. He considers that the adverse impacts of the proposal significantly and demonstrably outweigh the benefits. Overall, he considers that there are no material considerations which indicate that the proposal should be determined other than in accordance with the development plan.

28.The Secretary of State therefore concludes that the appeal is dismissed, and planning permission is refused.”

In terms of the availability of alternative sites:

“18.The Secretary of State agrees with the Inspector that in the 2007 decision it was identified that there was no alternative development site, a finding which attracted considerable weight in favour of that scheme (IR4.2). However, since 2007 the London Gateway, a brownfield site not located in the Green Belt, has been developed. For the reasons given in IR15.8.18 to 15.8.24, the Secretary of State agrees with the Inspector’s conclusions that the London Gateway site has the potential to provide an alternative development option for the provision of a SRFI to serve the same part of London and the South East as the appeals proposal (IR15.8.26)

The Inspector’s conclusions, set out in section 15 of his report, are also worth delving into.

His findings ahead of his overall conclusions relied upon by the Secretary of State included the following:

The proposal would have a substantial adverse effect on the openness of the Green Belt and the introduction of this massive development beyond the built limits of Slade Green would constitute urban sprawl.”

[G]iven the requirement of the NPSNN [National Policy Statement on National Networks] that ‘as a minimum, a SRFI should be capable of handling 4 trains per day’, it follows that in order for the proposed rail link to be considered ‘adequate’, it would be necessary for it to be capable of accommodating 4 trains/day as a minimum…Based on the evidence presented, in my judgement, the number of trains that could be pathed to/from the appeals site, having regard to the current timetable, would be likely to fall well short of 4 per day (each way)

Unlike the circumstances in 2007, there is no longer a formally identified requirement for 3 or 4 SRFIs around London [4.2, 7.2.6, 8.5.1, 11.2.12, 11.2.14.f.]. The Government approach set out in the NPSNN is to support the realisation of the forecast growth by encouraging the development of an expanded network of large SRFIs across the regions [11.2.9]. Furthermore, ‘…SRFI capacity needs to be provided at a wide range of locations…There is a particular challenge in expanding rail freight interchanges serving London and the South East’. ”

Overall, I am content that there is a need and market for SRFIs to serve London and the South East [11.2.2-3]. I turn then to consider the extent to which the appeals scheme would be likely to meet the requirements of SRFIs set out in the NPSNN. ”

However, “the appeals scheme would not be well qualified to meet the identified need for SRFIs to serve London and the South East”

[T]he appellant’s ‘very special circumstances case’ included the assertion thatno alternative development options exist for SRFIs to serve this part of London and the South East…this represents a material consideration of very considerable weight’ ”

London Gateway, a brownfield site, has the potential to provide an alternative development option for the provision of a SRFI to serve the same part of London and the South East as the appeals proposal. Under these circumstances, even if the appeals scheme was also well qualified to meet that need, in my view, the weight attributable to this would be limited.”

Finally, the inspector also had significant concerns in relation to the traffic modelling that had been relied upon by the local authorities, including Transport for London and concluded that “the residual cumulative impact of the development on the local road network would be severe, with particular reference to congestion.

How uncertain, expensive and slow this process is. And how valuable it would be have been to have kept the 2007 Howbury Park permission alive.

Simon Ricketts, 11 May 2019

Personal views, et cetera

Lessons From The Heathrow Cases

In my 15 October 2016 blog post Airports & Courts I made the obvious prediction that publication by the Secretary of State for Transport of the Airports National Policy Statement (“ANPS”) would inevitably lead to litigation. The ANPS is important because under the Planning Act 2008 it sets the policy basis for a third runway at Heathrow to the north west of the current runways (the “NWR Scheme”).

It was always going to be important for the High Court to be able to rise to the (in a non-legal sense) administrative challenge of disposing of claims efficiently and fairly. The purpose of this blog post is to look at how that was achieved (no easy feat) and what we can learn more generally from the court’s approach to the litigation

The ANPS was designated on 26 June 2018 and five claims were brought seeking to challenge that decision:

⁃ A litigant in person, Neil Spurrier (a solicitor who is a member of the Teddington Action Group)

⁃ A group comprising the London Borough of Richmond-upon-Thames, the Royal Borough of Windsor and Maidenhead, the London Borough of Hammersmith and Fulham, Greenpeace and the Mayor of London

⁃ Friends of the Earth

⁃ Plan B Earth

⁃ Heathrow Hub Limited and Runway Innovations Limited [unlike the other claimants above, these claimants argue for an extension of the current northern runway so that it can effectively operate as two separate runways. This scheme was known as the Extended Northern Runway Scheme (“the ENR Scheme”)]

Arora Holdings Limited joined as an interested party to each set of proceedings in pursuance of their case for a consolidated terminal facility to the west of the airport.

The Speaker for the House of Commons intervened in the Heathrow Hub Limited claim to object to various statements made to Parliament and Parliamentary Committees being admitted in evidence.

The first four claims raised 22 separate grounds of challenge. The fifth claim raised a further five grounds of challenge.

As Planning Liaison Judge, ie effectively lead judge within the Planning Court, Holgate J in my view has played an extremely effective role. Following a directions hearing, ahead of a subsequent pre-trial review three months later, he laid down a comprehensive set of directions on 4 October 2018 which provided for:

⁃ the first four claims to be heard at a single rolled up hearing, followed by the fifth claim

⁃ the cases to be heard by a Divisional Court (ie two or more judges, normally a High Court Judge and a Lord Justice of Appeal. In the event, the four claims were heard by a Divisional Court comprising Hickinbottom LJ and Holgate J. The fifth claim was heard immediately afterwards by a Divisional Court comprising Hickinbottom LJ, and Holgate and Marcus Smith JJ.)

⁃ video link to a second court room and (paid for jointly by the parties in agreed proportions) live searchable transcripts of each day’s proceedings

⁃ procedure to be followed in relation to expert evidence sought to be submitted in support of the first claim

⁃ statements of common ground

⁃ amended grounds of claim, with strict page limits and against the background of a request from the judge to “review the extent to which they consider that any legal grounds of challenge previously relied upon remain properly arguable in the light of the Acknowledgments of Service“, and with specific claimants leading on individual issues

⁃ bundles and skeleton arguments complying with strict page limits and other requirements

⁃ payment of security for costs by Heathrow Hub Limited in the sum of £250,000

⁃ cost capping in the other claims on Aarhus Convention principles

The main proceedings were heard over seven days in March, with the Heathrow Hub proceedings then taking a further three days (followed by written submissions). As directed by Holgate J, hearing transcripts were made publicly available.

Less than six weeks after close of the Heathrow Hub hearing, judgment was handed on 1 May 2019 in both case:

R (Spurrier & others) v Secretary of State (Divisional Court, 1 May 2019)

R (Heathrow Hub Limited & Runway Innovations Limited) v Secretary of State (Divisional Court, 1 May 2019)

The transcript of the first judgment runs to 184 pages and the transcript of the second judgment runs to 72 pages.

I am not going to summarise the judgments in this blog post but happily there is no need as the court at the same time issued a summary, which serves as a helpful précis of the claims and the court’s reasoning for rejecting each of them.

The Divisional Court found that all but six grounds were unarguable (the six being two Habitats Directive grounds from the first case, two SEA grounds from the first case and two from the second case (legitimate expectation and anti-competition). “All the other grounds were not considered not to have been arguable: the claimants may apply for permission to appeal against the Divisional Court’s decision concerning those grounds to the Court of Appeal within 7 days. The remaining six grounds were ultimately dismissed. The claimants may apply to the Divisional Court for permission to appeal within 7 days. If the Divisional Court refuses permission to appeal to the Court of Appeal, the claimants may re-apply directly to the Court of Appeal.”

The Secretary of State for Transport gave a written statement in the House of Commons on the same day, welcoming the judgments.

The two judgments will be essential reading in due course for all involved in similar challenges; the 29 grounds, and various additional preliminary points, cover a wide range of issues frequently raised in these sorts of cases and each is carefully dealt with, with some useful textbook style analysis.

In the Spurrier judgment:

– the scope for challenge of an NPS (paras 86 to 90)

⁃ relationship between the NPS and DCO process (paras 91 to 112)

⁃ extent of duty to give reasons for the policy set out in the NPS (paras 113 to 123)

⁃ consultation requirements in relation to preparation of an NPS (paras 124 to 140)

⁃ standard of review in relation to each of the grounds of challenge (paras 141 to 184)

⁃ the limited circumstances in which expert evidence is admissible in judicial review (paras 174 to 179)

⁃ whether updated information should have been taken into account (paras 201 to 209)

⁃ whether mode share targets were taken into account that were not realistically capable of being delivered (paras 210 to 219)

⁃ the relevance of the Air Quality Directive for the Secretary of State’s decision making (paras 220 to 285)

⁃ compliance with the Habitats Directive (paras 286 to 373)

⁃ compliance with the Strategic Environmental Assessment Directive (paras 374 to 502)

⁃ whether consultation was carried out with an open mind (paras 503 to 552)

⁃ whether the decision to designate the ANPS was tainted by bias (paras 553 to 557)

⁃ the relevance of the Government’s commitments to combat climate change (paras 558 to 660)

⁃ whether there was a breach of the European Convention on Human Rights (paras 661 to 665)

In the Heathrow Hub judgment:

⁃ legitimate expectation (paras 113 to 138)

⁃ use of Parliamentary material in the context of Article 9 of the Bill of Rights (paras 139 to 152)

⁃ competition law (paras 157 to 209).

As we wait to see whether any of these claims go further, I note that Arora has commenced pre application consultation ahead of submitting a draft DCO for a “consolidated terminal facility to the west of the airport, which we are calling Heathrow West, related infrastructure and changes to the nearby road and river network.” Now that is going to be another interesting story in due course. I’m not sure we have previously seen duelling DCOs…

Simon Ricketts, 4 May 2019

Personal views, et cetera