M’lud On The Tracks: HS2

Great Bob Dylan album, almost.

This post collects together in one place some of the recent planning, environmental and compulsory purchase litigation in relation to the High Speed Two rail project.

R (Keir) v Natural England (16 April 2021, Lang J; further hearing before Holgate J, 23 April 2021, judgment reserved)

This is the interim injunction granted by Lang J preventing HS2 and its contractors from varying out works at Jones’ Hill Wood, Buckinghamshire, until either the disposal of the claim or a further order.

The claim itself has Natural England as the defendant and seeks to challenge its grant of a licence under the Conservation of Habitats Regulations 2017 in relation to works that may disturb a protected species of bat.

The question as to whether the injunction should be maintained came back to court yesterday, 23 April, before Holgate J, as well as whether permission should be granted in the claim itself, and he has reserved judgment until 2pm on 26 April.

Secretary of State for Transport v Curzon Park Limited (Court of Appeal hearing, 21 and 22 April 2021, judgment reserved)

This was an appeal by the Secretary of State for Transport against a ruling by the Upper Tribunal on 23 January 2020. My Town Legal colleagues Raj Gupta and Paul Arnett have been acting for the first respondent, landowner Curzon Park Limited, instructing James Pereira QC and Caroline Daly. Thank you Paul for this summary:

The case concerns certificates of appropriate alternative development (‘CAADs’) under the Land Compensation Act 1961. A CAAD is a means of applying to the local planning authority to seek a determination as to what the land could have been used for if the CPO scheme did not exist. Its purpose it to identify every description of development for which planning permission could reasonably have been expected to be granted on the valuation date if the land had not been compulsorily purchased. Importantly, subject to a right of appeal, the grant of a CAAD conclusively establishes that the development is what is known as ‘appropriate alternative development’. This is significant as:

• When compensation is assessed it must be assumed that planning permission for that development(s) in the CAAD either was in force at the valuation date or would with certainty be in force at some future date and

• Following reforms in the Localism Act 2001, where there is, at the valuation date, a reasonable expectation of a particular planning permission being granted (disregarding the CPO scheme and CPO) contained in a CAAD it is assumed that the planning permission is in force which converts the reasonable expectation into a certainty.

There are four adjoining sites, each compulsorily acquired by HS2 for the purposes of constructing the Curzon Street HS2 station terminus at Cuzon Street Birmingham – four different landowners and four different valuation dates (i.e. vesting dates under the GVD process). Each landowner applied for a CAAD for mixed use development including purpose-build student accommodation (PBSA). In the real world, the cumulative effects of the proposed adjoining developments (e.g. including but not limited to the proposed quantum and need for PBSA in light of a PBSA need in the local plan) would have been a material planning consideration. However, Birmingham City Council considered each CAAD application in isolation. The Secretary of State argued that they should have considered the other CAAD applications as notional planning applications and, therefore, as material considerations which would have been very likely to result in CAADs issued for smaller scale mixed-used development being issued leading to a lower total compensation award and bill for HS2. The preliminary legal issue to be determined by the Upper Tribunal and now the Court of Appeal is:

Whether, and if so how, in determining an application for a certificate of appropriate alternative development under section 17 LCA 1961 (CAAD) the decision-maker in determining the development for which planning permission could reasonably have been expected to be granted for the purposes of section 14 LCA 1961 may take into account the development of other land where such development is proposed as appropriate alternative development in other CAAD applications made or determined arising from the compulsory acquisition of land for the same underlying scheme’.

The Upper Tribunal had rejected the landowners’ argument that the scheme cancellation assumption (i.e. disregarding the CPO scheme) under the Land Compensation Act 1961 required CAAD applications on other sites to be disregarded. However, critically, the Tribunal agreed with the landowners’ that CAAD applications were not a material planning consideration and that there was no statutory basis for treating them as notional planning applications as the Secretary of State has argued. The Tribunal also disagreed with the Secretary of State that the landowners’ interpretation of the statutory scheme would lead to excessive compensation pointing out that the landowners’ ability to develop their own land in their own interests was taken away when their land was safeguarded for HS2 and from November 2013 when the HS2 scheme was launched until 2018 when the land interests were finally acquired by HS2 any planning permissions for these sites would have been determined in the shadow of the HS2 scheme and safeguarding of the land. The Secretary of State appealed the Upper Tribunal decision and the Court of Appeal granted permission to appeal in July 2020 noting that the appeal raises an important point on the principle of equivalence (i.e. the principle underpinning the CPO Compensation Code) that a landowner should be no worse off but no better off in financial terms after the acquisition than they were before) which may have widespread consequences for the cost of major infrastructure projects.

A judgment from the Court of Appeal (Lewison LJ, Lindblom LJ and Moylan LJ) is expected in the next month or so.

Sarah Green v Information Officer & High Speed Two Limited (First Tier Tribunal, 19 April 2021)

This was an appeal against the refusal by HS2 Limited to disclose, pursuant to the Environmental Information Regulations 2004, information as to the potential effect of its works on chalk aquifers in the Colne Valley. The information requested was as follows:

What risk assessments have taken place, of the potential increased risk to controlled waters as a result of imminent works by HS2 contractors along the Newyears Green bourne and surrounding wetland?

Are any of the risk assessments independent from the developers (HS2) and where are the risk assessment (sic) accessible to the public?

By the time of the hearing before the First Tier Tribunal, three reports had been disclosed, redacted. The Tribunal summarised the issues before it as follows:

“(1) whether HS2 correctly identified the three reports as being the environmental information which Ms Green requested and whether there was further material held which came within the request;

(2) whether at the time of Ms Green’s request the three reports were “still in the course of completion” or comprised “unfinished documents” and, if so, whether the public interest in maintaining the regulation 12(4)(d) exception outweighed that in disclosure;

(3) whether disclosure of those parts of the three reports which have been redacted in reliance on regulation 12(5)(a) would have adversely affected “public safety” and, if so, whether the public interest in maintaining the regulation 12(5)(a) exception outweighed the public interest in their disclosure.”

The Tribunal found, expressing its reasoning in strong terms, that the public interest in disclosure outweighed the public interest in maintaining any exemption.

“The reports in question in this case concern a major infrastructure project which gives rise to substantial and legitimate environmental concerns. They specifically relate to the risks of contamination to the drinking water supplied to up to 3.2 million people resulting from the construction of the HS2 line. This is clearly environmental information of a fundamental nature of great public interest.”

HS2 appeared to be concerned that “if the versions of the reports current in January 2019 were made public they “… could have been used to try and impact work undertaken in finalising the information”.

“It seems to us that such an approach almost entirely negates the possibility of the public having any input on the decision-making process in this kind of case, which goes against a large part of the reason for allowing public access to environmental information.

The suggestion that public officials concerned in making enquiries and freely discussing options to mitigate environmental problems might be discouraged or undermined by early disclosure of their work seems to us rather fanciful and was not supported by any kind of evidence; the case is not comparable in our view to that of senior officials indulging in “blue sky” thinking about policy options. We accept that the material is “highly technical” but we cannot see why a lack of understanding on the part of the public would have any negative impact on HS2’s work; if a member of the public or a pressure group wanted to contribute to the debate in a way that was likely to have any effect on the decision-making process they would no doubt have to engage the services of someone like Dr Talbot, who would be able to enter the debate in a well- informed and helpful way.”

“HS2’s second main point, that the Environment Agency will be approving and supervising everything, does not seem to us of great weight. Of course the Environment Agency is there to act in the public interest in relation to the environment but its involvement cannot be any kind of answer to the need for public knowledge of and involvement in environmental decisions. The EA is itself fallible and should be open to scrutiny. If the public could simply entrust everything to it there would be no need for the EIR.

HS2’s third main point is that if inchoate information is released it could be misleading and they would incur unnecessary expense correcting false impressions. We were not presented with any specific evidence or examples to illustrate how this problem might have been encountered in practice. It does not seem to us a very compelling point.”

R (Maxey) v High Speed 2 Limited (Steyn J, 10 February 2021)

This was an interim ruling in an application for judicial review, made only nine days previously, of the decision by HS2 Limited to extract the protesters that were occupying the tunnel under Euston Square Gardens and alleging a failure to safely manage Euston Square Gardens in a manner compatible with HS2 Limited’s obligations under the European Convention of Human Rights. It followed a rejection of an application by Mr Maxey for an interim injunction and followed an order made requiring him to cease any further tunnelling activity, to provide certain categories of information to HS2 Limited or others and to leave the tunnel safely, with which he had not complied.

At the hearing, Mr Maxey was renewing his “application for orders requiring (a) the cessation of operations to extract the protesters from the tunnel and (b) to implement an exclusion zone. In addition, the Claimant has expanded the interest relief he seeks to include provision forthwith by the Defendant of (a) oxygen monitoring equipment; (b) a hard-wired communication method; (c) food and drinking water for the Claimant and the protesters; and (d) to make arrangements for the removal of human waste from the tunnel.” He was also seeking to overturn the orders against him.

The judge rejected Mr Maxey’s arguments:

While I accept that the Defendant is (or at the very least there is a good argument that the Defendant is) currently under a duty to take all reasonable steps to protect those in the tunnel under the site (including the Claimant) from death or serious injury, on the evidence before me there is no realistic prospect of the Court finding that the Defendant is breaching its duty. In my judgment, the claim for interim relief does not meet the first test.

That suffices to dispose of the interim relief application. But if it were necessary to consider the balance of convenience, I would have to bear in mind the strong public interest in permitting a public authority’s decision (here a decision to proceed with the operation and a decision as to the necessary safeguards) to remain in force pending a final hearing of the application for judicial review, so the party applying for interim relief must make out a strong case for the grant of interim relief. The Claimant has not come close to establishing a strong enough case to justify the Court stopping the operations to remove those who are in the tunnel, given the compelling evidence as to how dangerous it is for them to remain there.”

R (Packham) v Secretary of State for Transport (Court of Appeal, 31 July 2020)

I summarised this case in my 9 January 2021 blog post Judges & Climate Change. It was Chris Packham’s failed challenge to the Government’s decision to continue with the HS2 project following the review carried out by Douglas Oakervee, the grounds considered by the Court of Appeal being “whether the Government erred in law by misunderstanding or ignoring local environmental concerns and failing to examine the environmental effects of HS2 as it ought to have done” and “whether the Government erred in law by failing to take account of the effect of the project on greenhouse gas emissions between now and 2050, in the light of the Government’s obligations under the Paris Agreement and the Climate Change Act 2008”.

R (London Borough of Hillingdon) v Secretary of State for Transport (Court of Appeal, 31 July 2020)

This case was heard consecutively with the Packham appeal. It related to Hillingdon’s challenge to the Secretary of State’s decision to allow (against his inspector’s recommendations) an appeal against Hillingdon’s refusal to grant HS2 Limited’s application for approval, under the Act authorising the relevant stage of the HS2 project, of plans and specifications for proposed works associated with the creation of the Colne Valley Viaduct South Embankment wetland habitat ecological mitigation. HS2 Limited had refused to provide Hillingdon with information so that an assessment could be made as to the effect of the proposed works on archaeological remains, HS2 Limited’s position being that it was “under no obligation to furnish such information and evidence. It says that this is because it will, in due course, conduct relevant investigations itself into the potential impact of the development upon any archaeological remains and take all necessary mitigation and modification steps. HS2 Ltd says that it will do this under a guidance document which forms part of its contract with the Secretary of State for Transport which sets out its obligations as the nominated undertaker for the HS2 Project.”

Lang J had upheld the Secretary of State’s decision but this was overturned by the Court of Appeal:

“The key to this case lies in a careful reading of Schedule 17 and the powers and obligations it imposes upon local authorities and upon HS2 Ltd. In our judgment, the duty to perform an assessment of impact, and possible mitigation and modification measures under Schedule 17, has been imposed by Parliament squarely and exclusively upon the local authority. It cannot be circumvented by the contractor taking it upon itself to conduct some non-statutory investigation into impact. We also conclude that the authority is under no duty to process a request for approval from HS2 Ltd unless it is accompanied by evidence and information adequate and sufficient to enable the authority to perform its statutory duty.”

[Subsequent note: Please also see London Borough of Hillingdon v Secretary of State for Transport (Ouseley J, 13 April 2021), “Hillingdon 2” where on the facts Ouseley J reached a different conclusion, holding that an inspector had not acted unlawfully in determining an appeal without information sought by the council from HS2 Limited as to the lorry routes to be used by construction lorries to and from the HS2 construction sites within its area].

R (Granger-Taylor) v High Speed Two Limited (Jay J, 5 June 2020)

This was a judicial review claim brought by the owner of a listed Georgian building near Regents Park. The property was separated by a large retaining wall, built in 1901, from the perimeter of the existing railway. “It rests approximately 17 metres from the front of the property and the drop from the level of the road to the railway below is approximately 10 metres. Unsurprisingly, given that the substrate is London clay, the wall has suffered periodic movement and shows signs of cracking. The Claimant’s expert says that it is “metastable”.”

The claimant was concerned as to the engineering solution arrived at for that section of the route, which was known as the Three Tunnels design. “This judicial review challenge is directed to the safety of the Three Tunnels design in the specific context of the outbound tunnel travelling so close to the base of the retaining wall. It is contended on the back of expert engineering evidence that this aspect of the design has engendered an engineering challenge which is insurmountable: in the result, the design is inherently dangerous. The risk is of catastrophic collapse of the retaining wall, either during the tunnelling works or subsequently, which would if it arose cause at the very least serious damage to the Claimant’s property. Consequently, the Claimant asserts a breach of section 6 of the Human Rights Act 1998 because her rights under Article 8 and A1P1 of the Convention have been violated.”

The judge boiled the questions down to the following:

has the Claimant demonstrated that she is directly and seriously affected by the implementation of the Three Tunnels design, given the risk of catastrophic collapse identified by Mr Elliff? In my view, that question sub-divides into the following:

(1) should I conclude on all the evidence that the Three Tunnels design is so inherently flawed in the vicinity of the retaining wall that no engineering solution could be found to construct it safely? and

(2) have the Defendants already committed themselves to implement the Three Tunnels design regardless of any further work to be undertaken under Stage 2?

After detailed consideration of expert engineering expert on both sides, the judge rejected the claim.

Anixter Limited v Secretary of State for Transport (Court of Appeal, 30 January 2020)

This was a compulsory purchase case, about whether an owner of four units on the Saltley Business Park in Birmingham, faced with compulsory purchase of one of them, had served counter-notices in time such as to trigger its potential ability to require acquisition of its interests in all four buildings. The court ruled that it had not.

It certainly seems an age since R (HS2 Action Alliance) v Secretary of State for Transport (Supreme Court, 22 January 2014) where in a previous law firm life I acted for the claimant, instructing David Elvin QC and Charlie Banner (now QC). The case concerned whether the publication by the Government of its command paper, “High Speed Rail: Investing in Britain’s Future – Decisions and Next Steps” engaged strategic environmental assessment requirements and whether the hybrid bill procedure would comply with the requirements of the Environmental Impact Assessment Directive (for more on the HS2 hybrid bill procedure, see my 30 July 2016 blog post HS2: The Very Select Committeehttps://simonicity.com/2016/07/30/hs2-the-very-select-committee/). The loss still grates. And in consequence of that ruling…

There’s a slow, slow train comin’.

Simon Ricketts, 24 April 2021

Personal views, et cetera

Thank you to my Town Legal colleague Lida Nguyen for collating a number of these cases.

Our clubhouse Planning Law, Unplanned session at 6pm on 27 April will follow a similar theme, so if you are interested in issues relating to HS2 or in wider questions as to judicial review, interim injunctions, access to information or compulsory purchase compensation, do join us, whether to contribute to the discussion or just listen in. As always, contact me if you would like an invitation to the clubhouse app (which is still iphone only I’m afraid).

Detail from Bob Dylan’s painting Train Tracks

Double Exposure – Holborn Studios Win Again: Viability, Transparency

The next time you hear someone reprise Dominic Cummings’ February 2020 riff on the need for “urgent action on the farce that judicial review has become”, it’s worth thinking back to cases like R (Holborn Studios) v London Borough of Hackney (No 2) (Dove J, 11 June 2020). Sometimes it’s only the pesky lawyers (here Richard Harwood QC and solicitor Susan Ring, as well of course as a switched on judge) who, via judicial review, are finally able to cut through the sheer fudge and obfuscation of the planning application process.

This was the second time around for Holborn Studios, described in the judgment as “the leaseholder of 49-50 Eagle Wharf Road where they run one of the largest photographic studio complexes in Europe”. The studios have long campaigned against the proposed redevelopment of their building (for instance see What will become of Holborn Studios? (Londonist, 25 August 2017)).

The first planning permission which the London Borough of Hackney had purported to grant, in November 2016, was quashed by the High Court in R (Holborn Studios) v London Borough of Hackney (No 1) (Deputy Judge John Howell QC, 10 November 2017). The judge found that there had been an unlawful failure to consult the claimants and others on amendments made to the planning application and that the council had unfairly failed to disclose unredacted two letters on which officers had relied to support their view that proposed studio spaces in the basement were workable and that their layout was acceptable.

By the time of that first judgment a second application for planning permission had already been made. It was granted on 9 August 2019. Richard Harwood QC had indeed spoken at the planning committee meeting on behalf of Holborn Studios, seemingly to no avail. Again judicial review. The campaign against redevelopment continued (for instance see Battle to save Holborn Studios continues as celebrities and photographers line up in support (Hackney Citizen, 18 November 2019)).

When the case was heard in front of Dove J on 17 March 2020 there were three grounds of challenge but it is worth focusing on the first two, namely:

Ground one is a sequence of legal contentions related to the information provided in respect of the viability assessment for the proposed development which informed the contributions which were sought from the interested party, in particular in relation to affordable housing. It is said by the claimant that the defendant’s approach to this issue failed to comply with national planning policy in relation to the provision of information in respect of viability assessments; that the defendant’s approach was in breach of a legitimate expectation in respect of the disclosure of viability information and, finally, that as a matter of law the viability information provided was in breach of the defendant’s duties in relation to the publication of background papers to the committee report. Ground two is the allegation that the defendant’s guidance for the members of its planning committee were unlawful in so far as they precluded members from reading lobbying material submitted to them by consultees and required that instead this material was passed to officers unread.”

For a very good summary of the relevant facts, and the conclusions reached by the judge, I will now pause for two minutes whilst you read this: Access to viability assessments: Holborn Studios 2 (Richard Harwood QC, 11 June 2020).

Or even better if you have ten minutes, read the judgment itself. Summaries sometimes do not bring across the starkness of the judge’s description of events and analysis.

Some choice passages from the judgment:

On viability

A concern was raised by Mr Harwood at the planning committee meeting that “that the material on viability in the public domain appeared to demonstrate that the interested party’s consultants had undertaken the exercise on the basis of a residualised value, rather than taking an existing use value plus approach which was what was required by policy” and the point was also taken up by a councillor. Dove J chooses to relate the following, including a verbatim quotation of the meaningless response that councillors received:

Mr Robert Carney, who had been one of the defendant’s officers and who had been involved with the consideration and negotiation of the viability of the development (albeit that by the time he attended the committee meeting he was working for a consultancy) was called upon to address these concerns, and in particular whether or not a residualised value approach had been taken to the viability exercise. His observations in respect of this issue, as recorded on the transcript contained within the court’s papers, were as follows:

“Perhaps I’ll deal with the specifics of the, the values of where- of where they have been reported and Stuart will want to talk about, uh, the transparency of the information in the public domain. So I just want to clarify, we’ve used an existing use value plus approach in accordance with all guidance and the- what that approach- that approach forms was known as benchmark land value, that’s referred to in the table at 5.3.62. Uh, you have the applicant’s proposed benchmark land value and then the independent assessor’s benchmark land value. And what you do is you, uh, look at the residual land value and the appraisal, basically, given them the residual land value, show them the appraisal equals or is more than the benchmark- benchmark land value, the scheme is viable. Because what that means is that a hypothetical, uh, developer can purchase the site at a figure above the benchmark land value. And we see in appraisal it’s just shy of that benchmark land value. But basically, um, through our negotiations we accepted that the scheme had maximised, uh, it’s viability with the, um, agreed contributions.”

On the failure to make all of the viability appraisal information as background papers to the committee report;

“The first point raised is whether or not the defendant complied with its obligations under the 1972 Act in relation to the provision and listing of background papers. In short, I have no doubt that the defendant failed to comply with its obligations under section 100 D of the 1972 Act, not simply in relation to listing background papers but also in failing to provide them for inspection. It is clear from the evidence which has been set out above, including in particular the evidence of Mr Carney, that there was a significant quantity of documentation bearing upon the viability issues generated both before and especially after those documents that were published in relation to viability on the defendant’s website. It appears clear from Mr Carney’s evidence that, after the material from September 2018 which the defendant published, there was a significant volume of further technical work addressing ground rents and their impact on existing use value, the derivation of figures for the planning obligations and CIL and also the identification of a benchmark land value. Whilst not all of this material needed to be produced and listed it is simply inconceivable that none of this material would have qualified under section 100 D (5) of the 1972 Act. Clearly the contents of the committee report dealing with the viability exercise and its ultimate conclusions as to the affordable housing contribution which could legitimately be required, depended upon the contents of this material. There was, therefore, information which should have been listed and of which copies should have been provided for inspection.”

On the approach that should be taken to viability appraisal:

“In my view there are some clear principles set out in the Framework and the PPG to which it refers. Firstly, in accordance with the Framework viability assessments (where they are justified) should reflect the approach set out in PPG, and be made publicly available. Secondly, and in following the approach recommended in the Framework and the PPG, standardised inputs should be used including, for the purpose of land value, a benchmark land value based upon existing use value plus as described in the PPG. Thirdly, as set out in the PPG, the inputs and findings of a viability assessment should be set out “in a way that aids clear interpretation and interrogation by decision-makers” and be made publicly available save in exceptional circumstances. As the PPG makes clear, the preparation of a viability assessment “is not usually specific to that developer and thereby need not contain commercially sensitive data”. Even if some elements of the assessment are commercially sensitive, as the PPG points out, they can be aggregated in a published viability assessment so as to avoid disclosure of sensitive material.”

On whether elements of viability information should be treated as exempt from disclosure:

“As Mr Harwood pointed out in his submissions, there is an exception to the definition of exempt information contained in paragraph 10 of Schedule 12 to the 1972 Act where “the public interest in maintaining the exemption outweighs the public interest in disclosing the information.” In my judgment the existence of the policy contained in the Framework and the guidance contained in the PPG have an important bearing on the consideration of whether or not there is a public interest in disclosing the information contained in a viability assessment (even if it is properly to be characterised as commercially sensitive, bearing in mind the observations in the PPG about the extent to which information in such an assessment would be specific to a particular developer). It is clear from the material in the Framework and the PPG that save in exceptional circumstances the anticipation is that viability assessments, including their standardised inputs, will be placed in the public domain in order to ensure transparency, accountability and access to decision-taking for communities affected by development. The interests which placing viability assessments into the public domain serve are clearly public interests, which in my view support the contention that such assessments are not exempt information unless the exceptional circumstances spoken to by the PPG arise and solely an executive summary should be put in the public domain. It is unclear to me based on the material before the court how, if ever, the defendant ever considered the question of the public interest in relation to this exemption in the context of the relevant national planning policy. I am, therefore, unable to accept the submission advanced on behalf of the defendant that their failure to comply with section 100 D of the 1972 Act was a matter justified by the contention that the material withheld was exempt information. “

As to whether the viability information publicly available was comprehensive and coherent:

“In my view there are critical elements of the material in the public domain in relation to viability, set out in the documentation published on the defendant’s website and in the committee report, which are opaque and unexplained.”

If you deal regularly with viability appraisal you then need to read in full paragraphs 67 to 70 for an account by the judge of some of the deficiencies.

Drawing the threads together:

““Drawing the threads together, the material contained in the public domain at the time when the decision was taken by the planning committee to resolve to grant planning permission was inconsistent and opaque. It contained figures which differed in relation to, for instance, benchmark land value and the differences between the figures were not explained. No explanation was provided as to how the benchmark land value had been arrived at in terms of establishing an existing use value and identify a landowner’s premium as was asserted to have been case. Read against the background of the policy and guidance contained in the Framework and the PPG it was not possible to identify from the material in the public domain standardised inputs of the existing use value and landowner’s premium, and the purpose of the policy to secure transparency and accountability in the production of viability assessment was not served. In particular, it was plain from the material available at the time of the decision (in particular in terms of the material inconsistencies in the material produced in September 2018 and the differences from the material in the committee report) that there was substantial additional background material on which the committee report was based which was neither listed nor available for inspection in accordance with the requirements of the 1972 Act. In my view the principles identified in the case of Joicey by Cranston J at paragraph 47 are clearly on point, since the purpose of having a legal obligation to confer a right to know in relation to material underpinning a democratic decision-taking process is to enable members of the public to make well-informed observations on the substance of the decision. The failure to provide the background material underpinning the viability assessment in the present case, in circumstances where such material as was in the public domain was opaque and incoherent, was a clear and material legal error in the decision-taking process. In reality, in my judgment, the material with which the public was provided failed Mr Fraser-Urquhart’s own test of being adequate to enable the member of the public to make a sensible response to the consultation on the application.”

On the council’s attempt to prevent the direct lobbying of councillors

“… bearing in mind the importance of the decisions which the members of the planning committee are making, and the fact that they are acting in the context of a democratically representative role, the need for the communication of views and opinions between councillors and the public whom they represent must be afforded significant weight. In my view, it would be extremely difficult to justify as proportionate the discouragement, prohibition or prevention of communication between public and the councillors representing them which was otherwise in accordance with the law.”

“Receiving communications from objectors to an application for planning permission is an important feature of freedom of expression in connection with democratic decision-taking and in undertaking this aspect of local authority business. Whilst it may make perfect sense after the communication has been read for the member to pass it on to officers (so that for instance its existence can be logged in the file relating to the application, and any issues which need to be addressed in advice to members can be taken up in a committee report), the preclusion or prevention of members reading such material could not be justified as proportionate since it would serve no proper purpose in the decision-taking process. Any concern that members might receive misleading or illegitimate material will be resolved by the passing of that correspondence to officers, so that any such problem of that kind would be rectified. In my view there is an additional issue of fairness which arises if members of the planning committee are prevented from reading lobbying material from objectors and required to pass that information unread to their officers. The position that would leave members in would be that they would be reliant only on material from the applicant placed on the public record as part of the application or the information and opinions summarised and edited in the committee report. It is an important feature of the opportunity of an objector to a planning application to be able to present that objection and the points which they wish to make in the manner which they believe will make them most cogent and persuasive. Of course, it is a matter for the individual councillor in the discharge of his responsibilities to choose what evidence and opinion it is that he or she wishes to study in discharging the responsibility of determining a planning application, but the issue in the present case is having the access to all the material bearing upon the application in order to make that choice. If the choice is curtailed by an instruction not to read any lobbying material from members of the public that has a significant impact on the ability of a member of the public to make a case in relation to a proposed development making the points that they wish to make in the way in which they would wish to make them.”

“The standard correspondence clearly advised against members of the public writing directly to members of the committee; there was no warrant for that advice or discouragement and it impeded the freedom of expression of a member of the public who was entitled to write to a member of the planning committee setting out in his or her own terms the points they wish to be considered in respect of an application and expect that the member would have the opportunity to read it. It appears that Councillor Stops was under the impression that he was to resist being lobbied by either an applicant or member of the public, and Councillor Snell had apparently taken legal advice to the effect that he should refrain from reading any lobbying letter and forward it on to officers. Neither of these approaches reflects the defendant’s Code, nor does it reflect the entitlement to freedom of expression in accordance with the legal principles set out above.”

Concluding remarks

The case is a really helpful reminder to all of us of a few lessons:

Don’t get blinded by bad science. Good science is clear. Yes, viability appraisal includes some maths and you need to make sure that you understand the structure of the policy as to how viability appraisals should be conducted for the purposes in relation to the determination of planning applications. Subject to those points, if you don’t understand what is being said, you need to probe. A good viability appraisal does make sense and does tie in with policy and indeed common sense. And the process of arriving at an agreed viability appraisal should not be a behind the scenes negotiation. Memories of the R (Rainbird) v London Borough of Tower Hamlets (Deputy Judge John Howell QC, 28 March 2018) line of cases on daylight and sunlight – if the specialist input is not clear, and carried out in accordance with the relevant technical guidance such that the decision maker is not significantly misled, or if the detail that is needed for anyone to make sense of the position is held back, there is a plain risk of the resultant planning permission being struck down.

The approach to be taken to viability, both in terms of methodology and openness, has changed as a result of Government policy, and that is recognised by the courts.

Recognise that the value of having decisions taken at planning committee by elected councillors rests both in their being properly briefed by officers and also in their role as democratic representatives, not shielded from appropriate lobbying as if they were some jury.

However upsetting it may be for those whose decisions are overturned (and I recognise that there can be unwelcome consequences), without judicial review decision makers would pretty much be free to operate with impunity, to hell with the evidence (see also Westferry Printworks). That would be a farce.

Simon Ricketts, 13 June 2020

Personal views, et cetera

The Latest on Viability Disclosure

Each September LD Events’ annual Viability and Planning conference comes around. My regular slot at the event covers ”transparency in the viability process – access to information” and it’s always interesting how the climate has changed over the previous 12 months. This blog post provides links to some of the key decisions and policy developments, supplementing my 27 September 2016 presentation. 

Information Tribunal

In the same way that previous years have been dominated by the Information Tribunal’s decisions in London Borough of Southwark v Information Commissioner, Lend Lease and Glasspool  (9 May 2014, Heygate Estate) and Royal Borough of Greenwich v Information Commissioner and Brownie  (30 January 2015, Greenwich Peninsula), this year there has been another big Information Tribunal decision: Clyne v Information Commissioner and London Borough of Lambeth  (14 June 2016, Streatham Megabowl).


Clyne is important because the Tribunal go in detail through all of the following elements of the viability appraisal, justifying item by item, their decision to order disclosure:

 • Private residential values broken down by individual unit size/location within the development?

• Affordable housing average values per square foot?

• Gross development value?

• Marketing budget?

• Construction costs?

• Professional fees?

• Projected costs : contingency percentage?

• Projected costs : letting/sale agent and legal fees?

• Benchmark land value?

• Surplus/deficit figure?

• Other : performance measures?

 This was a case where the figure allowed for developer’s profit had already been disclosed.

 Information Commissioner

 There has also this year been a plethora of decisions by the Information Commissioner. Each very much turns on its facts. However, the following basic principles are commonly set out:

 – The four necessary criteria set out in Bristol City Council v Information Commissioner and Portland and Brunswick Squares Association  (24 May 2010) to get to first base ie establishing that the information is commercially confidential for the purposes of Regulation 12(5)(e) of the Environmental Information Regulations 2004:

(i) Is the information commercial or industrial in nature?

(ii) Is confidentiality provided by law? This will include confidentiality imposed on any person by the common law of confidence, contractual obligation, or statute.

(iii) Does the confidentiality protect a legitimate economic interest? Where the arguments refer to the economic interests of a third party, it will not be sufficient for a public authority to speculate on the potential harm attached to disclosure. Instead, the public authority must have evidence that demonstrates the arguments genuinely reflect the concerns of the third party.

(iv) The confidentiality would be adversely affected by disclosure. Although this is a necessary condition, the Information Tribunal in the Bristol City Council case considered that the disclosure of truly confidential information into the public domain would invariably harm the confidential nature of that information. As such, if the preceding three stages of the test are fulfilled, it will follow that the exception is engaged. Where this is found to be the case, a public authority must next go on to assess whether the balance of the public interest required disclosure

– It is not sufficient that harm “might” be caused by disclosure. It is necessary to show that on the balance of probabilities it would be caused.

– Those resisting disclosure on the basis of the harm that would be caused need to show a specific link between precise categories of withheld information and the stated harm.

– Detailed consideration as to whether the public interest in maintaining the exemption is outweighed by the public interest in disclosure.

 These are some of the decisions from the last 12 months:

Sweets Way Estate  (Barnet, 9 August 2016) – disclosure.

Doone  (East Hampshire, 16 June 2016) – disclosure.

Aylesbury Estate  (Southwark, 25 April 2016) – disclosure. 

Bishopsgate Goodsyard  (Tower Hamlets, 22 March 2016) – disclosure.

Heygate Estate  (Southwark, 15 February 2016) – redactions of DVS reports upheld equivalent to what was withheld in Glasspool, ie proposed commercial values, financial gearing rates, base inflation percentages for the delivery period set against assumed regeneration inflation figures, cost analysis summaries and construction costs. 

Tuke School, Peckham  (Southwark, 13 January 2016) – overage provisions in sale contract withheld.

 Chase Farm Hospital site  (Enfield: 9 December 2015) – withheld: forecasted residential land sale receipts and assumed value of land associated with a new school. Sensitive negotiation position of NHS Trust.

Brentford FC new stadium  (Hounslow: 22 October 2015) – all disclosed except specific appraisal information relevant to subsequent negotiations.

 Silver Hill  (Winchester, 17 September 2015) – withheld: development value of individual elements of the scheme, breakdown of individual costs and resultant net development value and profit, estimated rental value of commercial property, percentage of estimated rental values which the proposed ground rents would represent, budget for acquiring third party land, estimated construction costs for individual blocks, letting and marketing costs, interest rate on financing.

 London boroughs turning up the heat

Ahead of any updated London-wide guidance from Sadiq Khan (and his promised team of viability specialists), different boroughs are taking different approaches. For example the Hounslow local validation list  October 2015 and Greenwich local validation list  January 2016 both now require unredacted viability appraisals, which will be publically available. Other boroughs have been adopting development viability SPDs, for example Islington’s January 2016 SPD  and Southwark’s March 2016 SPD  , both of which require justification for exempting any elements of an appraisal from disclosure. Other boroughs take a more traditional approach to treatment of commercially sensitive material – who knows, perhaps even heeding the advice at paragraph 4.3 of the RICS guidance on financial viability in planning  :

 “Pre-application discussions usually proceed on the basis of treating commercial information provided by a developer (applicant) or their consultant as confidential. In order to encourage openness and transparency in the viability process both at pre- and post- application, it is also often the case that the viability reports submitted to a local planning authority are required to be classified as confidential in part or as a whole. This is to encourage the applicant to disclose the maximum amount of information, which can then be reviewed and reported upon. LPAs should therefore be asked to treat and hold this information on a similarly reciprocal basis and respect that disclosure of confidential information could be prejudicial to the developer (applicant) if it were to enter the public domain. Information will usually be disclosed to the LPA adviser but not to the general public as it may be commercially sensitive.

 Simon Ricketts 26.9.16

Personal views, et cetera