Great Bob Dylan album, almost.
This post collects together in one place some of the recent planning, environmental and compulsory purchase litigation in relation to the High Speed Two rail project.
R (Keir) v Natural England (16 April 2021, Lang J; further hearing before Holgate J, 23 April 2021, judgment reserved)
This is the interim injunction granted by Lang J preventing HS2 and its contractors from varying out works at Jones’ Hill Wood, Buckinghamshire, until either the disposal of the claim or a further order.
The claim itself has Natural England as the defendant and seeks to challenge its grant of a licence under the Conservation of Habitats Regulations 2017 in relation to works that may disturb a protected species of bat.
The question as to whether the injunction should be maintained came back to court yesterday, 23 April, before Holgate J, as well as whether permission should be granted in the claim itself, and he has reserved judgment until 2pm on 26 April.
Secretary of State for Transport v Curzon Park Limited (Court of Appeal hearing, 21 and 22 April 2021, judgment reserved)
This was an appeal by the Secretary of State for Transport against a ruling by the Upper Tribunal on 23 January 2020. My Town Legal colleagues Raj Gupta and Paul Arnett have been acting for the first respondent, landowner Curzon Park Limited, instructing James Pereira QC and Caroline Daly. Thank you Paul for this summary:
The case concerns certificates of appropriate alternative development (‘CAADs’) under the Land Compensation Act 1961. A CAAD is a means of applying to the local planning authority to seek a determination as to what the land could have been used for if the CPO scheme did not exist. Its purpose it to identify every description of development for which planning permission could reasonably have been expected to be granted on the valuation date if the land had not been compulsorily purchased. Importantly, subject to a right of appeal, the grant of a CAAD conclusively establishes that the development is what is known as ‘appropriate alternative development’. This is significant as:
• When compensation is assessed it must be assumed that planning permission for that development(s) in the CAAD either was in force at the valuation date or would with certainty be in force at some future date and
• Following reforms in the Localism Act 2001, where there is, at the valuation date, a reasonable expectation of a particular planning permission being granted (disregarding the CPO scheme and CPO) contained in a CAAD it is assumed that the planning permission is in force which converts the reasonable expectation into a certainty.
There are four adjoining sites, each compulsorily acquired by HS2 for the purposes of constructing the Curzon Street HS2 station terminus at Cuzon Street Birmingham – four different landowners and four different valuation dates (i.e. vesting dates under the GVD process). Each landowner applied for a CAAD for mixed use development including purpose-build student accommodation (PBSA). In the real world, the cumulative effects of the proposed adjoining developments (e.g. including but not limited to the proposed quantum and need for PBSA in light of a PBSA need in the local plan) would have been a material planning consideration. However, Birmingham City Council considered each CAAD application in isolation. The Secretary of State argued that they should have considered the other CAAD applications as notional planning applications and, therefore, as material considerations which would have been very likely to result in CAADs issued for smaller scale mixed-used development being issued leading to a lower total compensation award and bill for HS2. The preliminary legal issue to be determined by the Upper Tribunal and now the Court of Appeal is:
‘Whether, and if so how, in determining an application for a certificate of appropriate alternative development under section 17 LCA 1961 (CAAD) the decision-maker in determining the development for which planning permission could reasonably have been expected to be granted for the purposes of section 14 LCA 1961 may take into account the development of other land where such development is proposed as appropriate alternative development in other CAAD applications made or determined arising from the compulsory acquisition of land for the same underlying scheme’.
The Upper Tribunal had rejected the landowners’ argument that the scheme cancellation assumption (i.e. disregarding the CPO scheme) under the Land Compensation Act 1961 required CAAD applications on other sites to be disregarded. However, critically, the Tribunal agreed with the landowners’ that CAAD applications were not a material planning consideration and that there was no statutory basis for treating them as notional planning applications as the Secretary of State has argued. The Tribunal also disagreed with the Secretary of State that the landowners’ interpretation of the statutory scheme would lead to excessive compensation pointing out that the landowners’ ability to develop their own land in their own interests was taken away when their land was safeguarded for HS2 and from November 2013 when the HS2 scheme was launched until 2018 when the land interests were finally acquired by HS2 any planning permissions for these sites would have been determined in the shadow of the HS2 scheme and safeguarding of the land. The Secretary of State appealed the Upper Tribunal decision and the Court of Appeal granted permission to appeal in July 2020 noting that the appeal raises an important point on the principle of equivalence (i.e. the principle underpinning the CPO Compensation Code) that a landowner should be no worse off but no better off in financial terms after the acquisition than they were before) which may have widespread consequences for the cost of major infrastructure projects.
A judgment from the Court of Appeal (Lewison LJ, Lindblom LJ and Moylan LJ) is expected in the next month or so.
Sarah Green v Information Officer & High Speed Two Limited (First Tier Tribunal, 19 April 2021)
This was an appeal against the refusal by HS2 Limited to disclose, pursuant to the Environmental Information Regulations 2004, information as to the potential effect of its works on chalk aquifers in the Colne Valley. The information requested was as follows:
“What risk assessments have taken place, of the potential increased risk to controlled waters as a result of imminent works by HS2 contractors along the Newyears Green bourne and surrounding wetland?
Are any of the risk assessments independent from the developers (HS2) and where are the risk assessment (sic) accessible to the public?”
By the time of the hearing before the First Tier Tribunal, three reports had been disclosed, redacted. The Tribunal summarised the issues before it as follows:
“(1) whether HS2 correctly identified the three reports as being the environmental information which Ms Green requested and whether there was further material held which came within the request;
(2) whether at the time of Ms Green’s request the three reports were “still in the course of completion” or comprised “unfinished documents” and, if so, whether the public interest in maintaining the regulation 12(4)(d) exception outweighed that in disclosure;
(3) whether disclosure of those parts of the three reports which have been redacted in reliance on regulation 12(5)(a) would have adversely affected “public safety” and, if so, whether the public interest in maintaining the regulation 12(5)(a) exception outweighed the public interest in their disclosure.”
The Tribunal found, expressing its reasoning in strong terms, that the public interest in disclosure outweighed the public interest in maintaining any exemption.
“The reports in question in this case concern a major infrastructure project which gives rise to substantial and legitimate environmental concerns. They specifically relate to the risks of contamination to the drinking water supplied to up to 3.2 million people resulting from the construction of the HS2 line. This is clearly environmental information of a fundamental nature of great public interest.”
HS2 appeared to be concerned that “if the versions of the reports current in January 2019 were made public they “… could have been used to try and impact work undertaken in finalising the information”.
“It seems to us that such an approach almost entirely negates the possibility of the public having any input on the decision-making process in this kind of case, which goes against a large part of the reason for allowing public access to environmental information.
The suggestion that public officials concerned in making enquiries and freely discussing options to mitigate environmental problems might be discouraged or undermined by early disclosure of their work seems to us rather fanciful and was not supported by any kind of evidence; the case is not comparable in our view to that of senior officials indulging in “blue sky” thinking about policy options. We accept that the material is “highly technical” but we cannot see why a lack of understanding on the part of the public would have any negative impact on HS2’s work; if a member of the public or a pressure group wanted to contribute to the debate in a way that was likely to have any effect on the decision-making process they would no doubt have to engage the services of someone like Dr Talbot, who would be able to enter the debate in a well- informed and helpful way.”
“HS2’s second main point, that the Environment Agency will be approving and supervising everything, does not seem to us of great weight. Of course the Environment Agency is there to act in the public interest in relation to the environment but its involvement cannot be any kind of answer to the need for public knowledge of and involvement in environmental decisions. The EA is itself fallible and should be open to scrutiny. If the public could simply entrust everything to it there would be no need for the EIR.
HS2’s third main point is that if inchoate information is released it could be misleading and they would incur unnecessary expense correcting false impressions. We were not presented with any specific evidence or examples to illustrate how this problem might have been encountered in practice. It does not seem to us a very compelling point.”
R (Maxey) v High Speed 2 Limited (Steyn J, 10 February 2021)
This was an interim ruling in an application for judicial review, made only nine days previously, of the decision by HS2 Limited to extract the protesters that were occupying the tunnel under Euston Square Gardens and alleging a failure to safely manage Euston Square Gardens in a manner compatible with HS2 Limited’s obligations under the European Convention of Human Rights. It followed a rejection of an application by Mr Maxey for an interim injunction and followed an order made requiring him to cease any further tunnelling activity, to provide certain categories of information to HS2 Limited or others and to leave the tunnel safely, with which he had not complied.
At the hearing, Mr Maxey was renewing his “application for orders requiring (a) the cessation of operations to extract the protesters from the tunnel and (b) to implement an exclusion zone. In addition, the Claimant has expanded the interest relief he seeks to include provision forthwith by the Defendant of (a) oxygen monitoring equipment; (b) a hard-wired communication method; (c) food and drinking water for the Claimant and the protesters; and (d) to make arrangements for the removal of human waste from the tunnel.” He was also seeking to overturn the orders against him.
The judge rejected Mr Maxey’s arguments:
“While I accept that the Defendant is (or at the very least there is a good argument that the Defendant is) currently under a duty to take all reasonable steps to protect those in the tunnel under the site (including the Claimant) from death or serious injury, on the evidence before me there is no realistic prospect of the Court finding that the Defendant is breaching its duty. In my judgment, the claim for interim relief does not meet the first test.
That suffices to dispose of the interim relief application. But if it were necessary to consider the balance of convenience, I would have to bear in mind the strong public interest in permitting a public authority’s decision (here a decision to proceed with the operation and a decision as to the necessary safeguards) to remain in force pending a final hearing of the application for judicial review, so the party applying for interim relief must make out a strong case for the grant of interim relief. The Claimant has not come close to establishing a strong enough case to justify the Court stopping the operations to remove those who are in the tunnel, given the compelling evidence as to how dangerous it is for them to remain there.”
R (Packham) v Secretary of State for Transport (Court of Appeal, 31 July 2020)
I summarised this case in my 9 January 2021 blog post Judges & Climate Change. It was Chris Packham’s failed challenge to the Government’s decision to continue with the HS2 project following the review carried out by Douglas Oakervee, the grounds considered by the Court of Appeal being “whether the Government erred in law by misunderstanding or ignoring local environmental concerns and failing to examine the environmental effects of HS2 as it ought to have done” and “whether the Government erred in law by failing to take account of the effect of the project on greenhouse gas emissions between now and 2050, in the light of the Government’s obligations under the Paris Agreement and the Climate Change Act 2008”.
R (London Borough of Hillingdon) v Secretary of State for Transport (Court of Appeal, 31 July 2020)
This case was heard consecutively with the Packham appeal. It related to Hillingdon’s challenge to the Secretary of State’s decision to allow (against his inspector’s recommendations) an appeal against Hillingdon’s refusal to grant HS2 Limited’s application for approval, under the Act authorising the relevant stage of the HS2 project, of plans and specifications for proposed works associated with the creation of the Colne Valley Viaduct South Embankment wetland habitat ecological mitigation. HS2 Limited had refused to provide Hillingdon with information so that an assessment could be made as to the effect of the proposed works on archaeological remains, HS2 Limited’s position being that it was “under no obligation to furnish such information and evidence. It says that this is because it will, in due course, conduct relevant investigations itself into the potential impact of the development upon any archaeological remains and take all necessary mitigation and modification steps. HS2 Ltd says that it will do this under a guidance document which forms part of its contract with the Secretary of State for Transport which sets out its obligations as the nominated undertaker for the HS2 Project.”
Lang J had upheld the Secretary of State’s decision but this was overturned by the Court of Appeal:
“The key to this case lies in a careful reading of Schedule 17 and the powers and obligations it imposes upon local authorities and upon HS2 Ltd. In our judgment, the duty to perform an assessment of impact, and possible mitigation and modification measures under Schedule 17, has been imposed by Parliament squarely and exclusively upon the local authority. It cannot be circumvented by the contractor taking it upon itself to conduct some non-statutory investigation into impact. We also conclude that the authority is under no duty to process a request for approval from HS2 Ltd unless it is accompanied by evidence and information adequate and sufficient to enable the authority to perform its statutory duty.”
[Subsequent note: Please also see London Borough of Hillingdon v Secretary of State for Transport (Ouseley J, 13 April 2021), “Hillingdon 2” where on the facts Ouseley J reached a different conclusion, holding that an inspector had not acted unlawfully in determining an appeal without information sought by the council from HS2 Limited as to the lorry routes to be used by construction lorries to and from the HS2 construction sites within its area].
R (Granger-Taylor) v High Speed Two Limited (Jay J, 5 June 2020)
This was a judicial review claim brought by the owner of a listed Georgian building near Regents Park. The property was separated by a large retaining wall, built in 1901, from the perimeter of the existing railway. “It rests approximately 17 metres from the front of the property and the drop from the level of the road to the railway below is approximately 10 metres. Unsurprisingly, given that the substrate is London clay, the wall has suffered periodic movement and shows signs of cracking. The Claimant’s expert says that it is “metastable”.”
The claimant was concerned as to the engineering solution arrived at for that section of the route, which was known as the Three Tunnels design. “This judicial review challenge is directed to the safety of the Three Tunnels design in the specific context of the outbound tunnel travelling so close to the base of the retaining wall. It is contended on the back of expert engineering evidence that this aspect of the design has engendered an engineering challenge which is insurmountable: in the result, the design is inherently dangerous. The risk is of catastrophic collapse of the retaining wall, either during the tunnelling works or subsequently, which would if it arose cause at the very least serious damage to the Claimant’s property. Consequently, the Claimant asserts a breach of section 6 of the Human Rights Act 1998 because her rights under Article 8 and A1P1 of the Convention have been violated.”
The judge boiled the questions down to the following:
“has the Claimant demonstrated that she is directly and seriously affected by the implementation of the Three Tunnels design, given the risk of catastrophic collapse identified by Mr Elliff? In my view, that question sub-divides into the following:
(1) should I conclude on all the evidence that the Three Tunnels design is so inherently flawed in the vicinity of the retaining wall that no engineering solution could be found to construct it safely? and
(2) have the Defendants already committed themselves to implement the Three Tunnels design regardless of any further work to be undertaken under Stage 2?
After detailed consideration of expert engineering expert on both sides, the judge rejected the claim.
Anixter Limited v Secretary of State for Transport (Court of Appeal, 30 January 2020)
This was a compulsory purchase case, about whether an owner of four units on the Saltley Business Park in Birmingham, faced with compulsory purchase of one of them, had served counter-notices in time such as to trigger its potential ability to require acquisition of its interests in all four buildings. The court ruled that it had not.
It certainly seems an age since R (HS2 Action Alliance) v Secretary of State for Transport (Supreme Court, 22 January 2014) where in a previous law firm life I acted for the claimant, instructing David Elvin QC and Charlie Banner (now QC). The case concerned whether the publication by the Government of its command paper, “High Speed Rail: Investing in Britain’s Future – Decisions and Next Steps” engaged strategic environmental assessment requirements and whether the hybrid bill procedure would comply with the requirements of the Environmental Impact Assessment Directive (for more on the HS2 hybrid bill procedure, see my 30 July 2016 blog post HS2: The Very Select Committeehttps://simonicity.com/2016/07/30/hs2-the-very-select-committee/). The loss still grates. And in consequence of that ruling…
There’s a slow, slow train comin’.
Simon Ricketts, 24 April 2021
Personal views, et cetera
Thank you to my Town Legal colleague Lida Nguyen for collating a number of these cases.
Our clubhouse Planning Law, Unplanned session at 6pm on 27 April will follow a similar theme, so if you are interested in issues relating to HS2 or in wider questions as to judicial review, interim injunctions, access to information or compulsory purchase compensation, do join us, whether to contribute to the discussion or just listen in. As always, contact me if you would like an invitation to the clubhouse app (which is still iphone only I’m afraid).
