A Helpful Case On The Scope Of Section 73

I was pleased to read Finney v Welsh Ministers (Sir Wyn Williams, 15 November 2018), or the Rhydcwmerau wind turbines case, as I hope we’ll call it for ease.

Sir Wyn Williams provides the answer to a question I raised in my 3 March 2018 blog post, A Change Is Gonna Come (But Should It Really Need A Fresh Planning Permission?): can you use a section 73 application when the changes to conditions that you are seeking also entail a change to the description of development on the previous permission?

The implied answer from Singh J in R (Wet Finishing Works Limited) v Taunton Deane Borough Council (20 June 2017) was yes but the point was not specifically addressed in his judgment. Sir Wyn Williams has to deal with the point head-on as it was one of the two grounds of challenge.

In the Rhydcwmerau wind turbines case there was a planning permission granted where the description of the development that was thereby approved was as follows:

Installation and 25 year operation of two wind turbines, with a tip height of up to 100m, and associated infrastructure including turbine foundations, new and upgraded tracks, crane hardstandings, substation, upgraded site entrance and temporary construction compound upon a site situated to the north of the village of Rhydcwmerau, Carmarthenshire

The description of development appears simply to have been incorporated in the permission by reference to the description of development on the application form, but I don’t think anything turns on that.

The permission was subject to a number of conditions. Condition 2 provided that the development was to be carried out in accordance with a number of approved plans and documents which were specified. One such was a “figure” described as “3.1 Typical Wind Turbine Elevation 1:500 @ A3“. It is common ground that this showed a wind turbine with a tip height of 100m.”

The promoter of the project then made an application under section 73 of the Town and Country Planning Act 1990 to substitute plan 3.1 with a plan showing a wind turbine with a tip height of 125m. The local planning authority treated the application as valid but refused it. An inspector allowed the promoter’s appeal.

The claimant challenged the inspector’s decision:

“It is argued that the Inspector should not have allowed the appeal because she had no power under section 73 to amend a condition pursuant to which a prior planning permission had been granted which had the effect of directly contradicting the description of the development permitted in that earlier permission. Further or alternatively, the Claimant asserts that the Inspector failed to consider at all (as she should have done in accordance with established legal principles) whether the application before her constituted a “fundamental alteration” of the prior permission“.

On the first ground of challenge, Sir Wyn Williams held that “the only proper interpretation of the judgment in Wet Finishing Works, is that a variation pursuant to section 73 can be lawful notwithstanding that it may necessitate a variation to the terms of the planning permission which preceded the section 73 application.” The section 73 permission was not unlawful simply because necessarily the permission entailed a change to the original description of development which had referred to a tip height of 100m rather than 125m.

He also referred to the test formulated by Sullivan J in R v Coventry City Council, ex p. Arrowcroft Group plc (2001): “the council is able to impose different conditions upon a new planning permission, but only if they are conditions which the council could lawfully have imposed upon the original planning permission in the sense that they do not amount to a fundamental alteration of the proposal put forward in the original application.”

Applying that test to the decision letter:

Although I am not entirely convinced that the Inspector had in mind that it was necessary for her to consider in terms whether the variation sought would create a fundamental alteration to the original proposal I am prepared to conclude, on balance, that she was aware of that obligation and considered it.”

But even if she had not, it was highly likely that the decision would have been the same. “I have no doubt that had the Inspector considered whether the variation to the condition would have constituted a fundamental alteration to the original proposal she would have concluded that it did not. The whole tenor of her decision letter leads inexorably, in my judgment, to that conclusion as a careful reading of it makes abundantly clear.”

So, a pretty clear signpost for us all to follow – particularly a number of local planning authorities which presently take a plainly too restrictive approach to the use of section 73.

Simon Ricketts, 24 November 2018

Personal views, et cetera

Town Library, New Wing: Decision Letters

Town announcement

One of the joys of starting up Town Legal with colleagues has been the opportunity to play with technology so as to see how up to date information relevant to planners and planning lawyers can be made more readily available, with a little bit of focus on where the gaps are. We have constantly asked ourselves what may be useful to increase people’s understanding and ability to predict outcomes, but which may not be fully accessible?

That was the rationale for the Planning Court Judgments weekly update (with its click through to a full, searchable, list of Planning Court judgments since 2014), announced in my 2 August 2018 blog post . The update now has around 370 subscribers. The latest update, for the week ending 16 November 2018, is at this link. Free subscription is still available via this link. I am really grateful for the hard work of Susie Herbert and other Town associates in preparing, to a weekly deadline, the various case summaries.

We can now announce another Town Library service: a weekly list of decision letters issued in the preceding week by the Secretary of State or Planning Inspectorate. The list comprises section 77 and 78 appeals in relation to proposals for major development that have been determined following a public inquiry, rather than informal hearing or written representations. The latest update, for the week ending 16 November 2018 is at this link. Free subscription is available via this link.

This latest service goes beyond the Planning Court judgments service in that it is fully automated. It was again devised by us in association with legal engineers Wavelength Law, drawing upon the Planning Inspectorate’s website. We are grateful to the Planning Inspectorate for its online service and hope that our weekly updates will assist people both in accessing its content and in generally gaining a better understanding of likely appeal outcomes. Not part of the free update service but with Wavelength’s help we can re-cut the PINS data (which we have in a searchable database going back to 2012) in all manner of ways for individual requirements – if this would be useful for a particular project that we are acting on do let me know – or another Town partner.

Please bear with us as we continue to experiment with update formats and continue to iron out various issues but, as always, comments and suggestions are very welcome. We have plenty more strands of development underway.

I have always loved libraries.

Simon Ricketts, 22 November 2018

Personal views, et cetera

Big EU News! (Latest CJEU Case on Appropriate Assessment & A Draft Withdrawal Agreement)

The European Court of Justice is certainly turning the screws this year via various cases in relation to the Republic of Ireland, with now three rulings against its Planning Board, An Bord Pleanála. Following People Over Wind (see my 20 April 2018 blog post EU Court Ruling: Ignore Mitigation Measures In Habitats Screening) and Grace, Sweetman (see the second half of my 18 August 2018 blog post What Is Mitigation?) we now have Holohan (CJEU, 7 November 2018).

In basic summary:

People Over Wind has removed the ability for the competent authority to screen out the need for appropriate assessment, under the Conservation of Habitats Regulations 2017, on the basis that a significant effect on a Special Protection Area or Special Area of Conservation is unlikely, where that conclusion is reliant on proposed mitigation measures. The result has been far more projects and plans requiring appropriate assessment to ascertain that they will not adversely affect the integrity of the relevant SPA or SAC.

Grace, Sweetman has removed the ability for the competent authority to reach a conclusion at appropriate assessment stage that there will be no adverse effect on integrity, where mitigation measures are relied on that in reality amount to compensatory measures for the loss of habitat.

Holohan now imposes more detailed requirements on the competent authority at appropriate assessment stage:

1.  […] an ‘appropriate assessment’ must, on the one hand, catalogue the entirety of habitat types and species for which a site is protected, and, on the other, identify and examine both the implications of the proposed project for the species present on that site, and for which that site has not been listed, and the implications for habitat types and species to be found outside the boundaries of that site, provided that those implications are liable to affect the conservation objectives of the site.

2.  […] the competent authority is permitted to grant to a plan or project consent which leaves the developer free to determine subsequently certain parameters relating to the construction phase, such as the location of the construction compound and haul routes, only if that authority is certain that the development consent granted establishes conditions that are strict enough to guarantee that those parameters will not adversely affect the integrity of the site.

3.   […] where the competent authority rejects the findings in a scientific expert opinion recommending that additional information be obtained, the ‘appropriate assessment’ must include an explicit and detailed statement of reasons capable of dispelling all reasonable scientific doubt concerning the effects of the work envisaged on the site concerned.

If you are relying on an appropriate assessment in relation to a project or plan, I suggest that you urgently check that it addresses these three requirements. An decision taken in reliance upon an appropriate assessment which does not cover off these points will be susceptible to legal challenge. If caught at the right time, deficiencies should be able to be addressed by some extra work. But it will be too late to rectify matters once the appropriate assessment is reached and the decision taken.

These CJEU rulings are unambiguous in their stated conclusions on the law, very different from our common law approach.

They are also likely to continue to be relevant, regardless of what happens with Brexit. After all, as set out in my 18 September 2018 blog post Planning, Brexit, Michael Gove as Secretary of State for Environment, Fisheries and Rural Affairs has committed that:

Where environmental principles are contained in specific pieces of EU legislation, these will be maintained as part of our domestic legal framework through the retention of EU law under the EU (Withdrawal) Bill. Any question as to the interpretation of retained EU law will be determined by UK courts in accordance with relevant pre-exit CJEU case law and general principles, subject to the other exceptions and restrictions within the Bill. For example, CJEU case law on chemicals, waste and habitats includes judgments on the application of the precautionary principle to those areas. This will therefore be preserved by the Bill“.

As set out in that blog post, we are still waiting for the draft Bill, required by section 16 of the EU (Withdrawal) Act to be published by Boxing Day 2018, that will set out the environmental principles to be applied post Brexit and the body that will enforce them.

What we now have seen of course is the draft withdrawal agreement published on 14 November 2018. Who knows whether it will be concluded but it envisages that the CJEU will continue to have jurisdiction in any proceedings brought against the UK during the transition period to 31 December 2020.

In the event of the backstop being triggered at the end of the transitional period if the Irish border issue hasn’t been settled, a series of commitments in relation to environmental protection will kick in, as set out in Part 2 of Annex 4 to the Protocol on Northern Ireland/Ireland (pages 356 to 360 of the overall draft agreement). The commitments include:

– Non-regression in level of environmental protection subsisting at the end of the transitional period.

– The principles to be reflected in legislation:

a)  the precautionary principle;
b)  the principle that preventive action should be taken;

c) the principle that environmental damage should as a priority be rectified at source; and
d)  the “polluter pays” principle

– The Joint Committee shall adopt decisions laying down minimum commitments for:

a)  the reduction of national emissions of certain atmospheric pollutants;
b)  the maximum sulphur content of marine fuels

c) those best available techniques, including emission limit values, in relation to industrial emissions

– Commitment to meet international obligations as to addressing climate change

– Commitment to carbon pricing and trading of allowance consistent with EU system

– Finally, although much of this is already in hand via section 16 of the EU (Withdrawal) Act and/or the subject of other international obligations, a commitment to effective enforcement of environmental laws as well as the following:

The United Kingdom shall ensure that administrative and judicial proceedings are available in order to permit effective and timely action by public authorities and members of the public against violations of its laws, regulations and practices, and provide for effective remedies, including interim measures, ensuring that any sanctions are effective, proportionate and dissuasive and have a real and deterrent effect.

The United Kingdom shall implement a transparent system for the effective domestic monitoring, reporting, oversight and enforcement of its obligations pursuant to this Article and to Article 2 by an independent and adequately resourced body or bodies…

The independent body shall have powers to conduct inquiries on its own initiative concerning alleged breaches by public bodies and authorities of the United Kingdom, and to receive complaints for the purposes of conducting such inquiries. It shall have all powers necessary to carry out its functions, including the power to request information. The independent body shall have the right to bring a legal action before a competent court or tribunal in the United Kingdom in an appropriate judicial procedure, with a view to seeking an adequate remedy.”

Professor Colin Reid’s 15 November 2018 blog post Environmental Commitments in the Withdrawal Agreement is a very good commentary on all of these provisions.

Finally, fabulous timing on the part of UKELA to have secured for next week’s annual Garner lecture Professor Juliane Kokott, Advocate General at the CJEU (who has been at the centre of so much EU case law, including the People Over Wind and Holohan cases referred to above). It will be fascinating to hear her perspective.

Simon Ricketts, 16 November 2018

Personal views, et cetera

PS David Elvin QC has since reminded me that the CJEU also on 7 November handed down its judgment in the Dutch Nitrogen Deposition case, which also contains important rulings in relation to appropriate assessment, for instance the extent to which agricultural activities amount to a “project”, as well as the extent of certainty required if conservation measures are to be relied upon as mitigation. See James Maurici QC’s blog post.

An Update On CIL: Reform Promised, Meanwhile Continuing & Increasingly Expensive Uncertainties

Well done for getting past the heading.

Someone recently asked me whether the Government ever changes its proposals as a result of a consultation process. For an example of just such a thing, I was able to point to the Government response to supporting housing delivery through developer contributions: a summary of consultation responses and the Government’s view on the way forward (29 October 2018). The proposals set out in the Government’s March 2018 consultation paper (summarised in my 10 March 2018 blog post Developer Contributions, CIL, Viability: Are We Nearly There Yet?) have been modified significantly as a result of consultation, mostly for the better in my view at least.

This blog post focuses on the changed proposals and then looks at some looming issues facing phased developments in areas where charging authorities are looking to increase rates (I’m focusing on the Mayor of London’s MCIL2 but I’m sure the issue is of wider application).

The Government response

The document acknowledges some of the flaws of the current system:

The complexity and uncertainty of the current system of developer contributions is acting as a barrier to the delivery of housing. The system does not react quickly to changes in market conditions or allow local authorities to effectively secure the contributions needed to support new development. It is also not as transparent as it should be; local communities are not clear what infrastructure is provided alongside new development. And the current system could also be more effective in securing funding towards strategic infrastructure and supporting cross boundary planning.”

The Government intends to consult on draft regulations “later this year” to implement the changes set out in the March 2018 consultation document, as now modified. It is important to note that the Government will “also consider whether changes could be made to the Community Infrastructure Levy to incentivise the build out of developments.” (perhaps something that Sir Oliver Letwin might have looked at but…).

The Government has now modified its proposed changes as follows:

1. The previous proposal to replace charging authorities’ current statutory consultation requirements, in relation to proposed charging schedules, with self-certification as to whether it has sought “an appropriate level of engagement” has been amended. The Government “intends to take forward a modified proposal to ensure that regulations continue to require charging authorities to consult on draft charging schedules, whilst removing the current statutory requirement for two separate rounds of consultation in every circumstance.”

2. The pooling restriction will now be removed in its entirety in all areas. Hooray! Although of course there is the risk that tariff-type section 106 contribution requirements will again become more prevalent, in my view the pooling restriction led to many unnecessary problems and uncertainties, which would have continued under the Government’s March 208 idea of only removing the restriction in in areas where specified criteria were met.

3. The Government had intended to introduce a two month grace period for developers to submit a commencement notice in relation to exempted development, to address disproportionately severe problems arising for eg self-builders who, if they fail to meet procedural requirements, find not only that they fail to qualify for any exemption but that all CIL due has become immediately payable. The Government will not now introduce the grace period (which local authorities considered could lead to practical complications) but instead will be “making changes to the penalties associated with the failure to submit a Commencement Notice prior to development being started. This will ensure that any penalty is set at a proportionate level and will not result in the whole liability becoming payable immediately.”

There may also be more guidance as to potential exemptions: “A number of responses sought additional exemptions to address the unintended viability impacts of Levy liabilities on particular forms of development. The Government will consider how guidance could be used to manage these effects by encouraging authorities to take account of these issues when setting Levy rates and choosing how they use existing powers for discretionary social housing relief. In addition, the Government has already committed to bring forward legislation to exempt Starter Homes from the Community Infrastructure Levy.”

4. The complicated proposal in the March 2018 consultation document that charging schedules might be set with reference to the existing use of land has been dropped. “However, the Government has reviewed this proposal and considers there are existing flexibilities in the Community Infrastructure Levy Regulations that, through the use of differential Levy rates, will allow local authorities to go some way towards achieving the objective of the proposed reform. The Government therefore proposes to make changes to guidance to support local authorities to set differential rates more effectively.

5. At the time that it publishes the draft amendment regulations, the Government intends to “consult on changes to indexation of Levy rates and the way in which it would be implemented“. Its current preference is to index CIL rates “for residential development to the House Price Index using local-level data on an annual basis” and to index rates for non-residential development to the Consumer Price Index. It recognises the transitional issues that will arise.

6. The Government still intends to remove the restriction in relation to section 106 obligations that relate to an infrastructure project or type of infrastructure that is set out in the authority’s Regulation 123 list. “New reporting standards, which are set out in the Infrastructure Funding Statement, will address concerns about double dipping by ensuring that there is transparency over how developer contributions from both CIL and section 106 planning obligations are being used, rather than by placing formal restrictions in regulations.” We need to watch this one with care!

In relation to one specific issue that often leads to wrangles: “The Government also recognises the need to address existing uncertainty around using section 106 planning obligations to collect monitoring sums. The Government therefore intends to take forward proposals to make clear that local authorities can seek a fee from applicants towards monitoring planning obligations. In developing these proposals, the Government will consider how best to ensure that monitoring sums are set at an appropriate level.”

7. The Government had intended to give combined authorities and joint committees with strategic planning powers the ability to charge a Strategic Infrastructure Tariff. “The Government has decided to take forward a modified proposal, to enable Combined Authorities with strategic planning powers to take forward a Strategic Infrastructure Tariff, and to encourage groups of charging authorities to use existing powers to more effectively support the delivery of strategic infrastructure through the pooling of their local Community Infrastructure Levy receipts. In the longer term, the Government will bring forward proposals for allowing joint planning committees to charge the tariff, and will review options for giving other groups the power to levy a Tariff.”

The Government had also included a final “catch all” question seeking any other comments. Particular issues that were raised in responses included “the definition of gross internal area, implementation of the Levy in particular circumstances (such as in relation to development that takes place in a number of phases or there is a change of use), and the operation of exemptions and reliefs, indexation and in-kind payment.

Issues such as these are indeed causing much uncertainty.

The implications of increased rates/MCIL2

Whilst we wait for eventual reform of the system, of more immediate focus are the implications of gradual increases by charging authorities in CIL rates.

In London, the Mayor of London is waiting for the inspector’s report following the examination into the draft charging schedule for MCIL2. MCIL2 is proposed to part-fund Crossrail 2, in the way that MCIL1 (together with a related policy of seeking section 106 contributions in relation to some areas and types of development) is part-funding Crossrail 1.

The charging schedule for MCIL1 was adopted on 1 April 2012 (which is why there are many section 106 agreements and permissions dated March 2012, as developers and boroughs scrambled to ensure that permissions were not subject to the levy!).

This table sets out borough by borough the significant sums of money that MCIL1 has now raised:

The section 106 contributions policy for Crossrail (set out in the Mayor’s Crossrail Funding SPG, updated March 2016) predated MCIL1 and provided for section 106 contributions based on the following table and plans:

The standardised wording included in relevant section 106 agreements provides that any MCIL1 which is payable reduces the contributions which are required to be made under the relevant section 106 agreement.

As long as the inspector’s report is received on time and gives it a clean bill of health, MCIL2 will be adopted on 1 April 2019. The changes in rates, compared to where the 2012 rates currently sit with indexation applied, are mostly not huge, but they are significant in some areas. In areas where the increases are material, I am sure we will see a similar rush to beat the deadline.

One uncertainty is of course whether the examination inspector will accept a charging schedule that is predicated on Crossrail 2 coming forward. Little has progressed on the project since my 1 July 2017 blog post, Crossrail 2: Where Are You? We are all still awaiting outcome of an independent affordability review being chaired by Mike Gerrard. The Mayor is hedging his bets, simply indicating:

Should the Crossrail 2 project not be taken forwards, the Mayor would be able to apply the MCIL 2 proceeds to fund other strategic infrastructure.”

Assuming that MCIL2 is waved through and the charging schedule is adopted on 1 April, the relevant point at which it takes effect is determined by everyone’s least favourite phrase in the CIL Regulations: “at the time planning permission first permits the chargeable development“.

For a non-phased permission, this is the date of the permission – easy.

For a phased outline permission, this is either “the date of final approval of the last reserved matter associated with that phase” or “if earlier, and if agreed in writing by the collecting authority before commencement of any development under that permission, on the day final approval is given under any pre-commencement condition associated with that phase“.

For a phased full permission, this is either “the day final approval is given under any pre-commencement condition associated with that phase” or “where there are no pre-commencement conditions associated with that phase, on the day planning permission is granted“.

It will be seen that (1) the revised charging schedule is liable to bite in respect any phase of an existing phased permission if sufficient progress has not been made in relation to reserved matters or discharging pre-commencement conditions in relation to that phase and (2) that there are inherent uncertainties in the drafting, eg

⁃ What does “associated with that phase” mean?

⁃ Does “any” mean “any” or, in fact, “all“?

As a final example of the inadequacies of the legislation: where there is a phased permission and a revised charging schedule is subsequently adopted, the only indexation that applies is of the amount arising from the initial charging schedule up to the end of the year prior to the date of the permission. There is no further indexation through to commencement of development or any indexation of the revised charging schedule insofar as it applies to the phases! Would it not be simpler and more predictable if indexation were not to stop at the initial grant of the permission and instead to continue through to final approval (or even commencement of development) in relation to each phase, but if the potential application of revised charging schedules were removed?

In case anyone has made it down this far…

In conclusion:

⁃ the proposed reforms, and most recent proposals, look to be mainly positive

⁃ but the whole regime really does still need simplifying: to state the obvious, significant liabilities can unexpectedly arise for the unwary – and large sums of money can turn on uncertain issues of interpretation.

Simon Ricketts, 9 November 2018

Personal views, et cetera

Oliver’s Twist: Letwin’s Proposals For Large Housing Sites

Sajid Javid had given Sir Oliver Letwin the following terms of reference for his review into the “build out of planning permissions into homes” that was announced in the Autumn 2017 budget.

The Review should seek to explain the significant gap between housing completions and the amount of land allocated or permissioned in areas of high housing demand, and make recommendations for closing it. The Review should identify the principal causes of the gap, and identify practical steps that could increase the speed of build out. These steps should support an increase in housing supply consistent with a stable housing market in the short term and so that over the long-term, house prices rise slower than earnings. The review will provide an interim report to the Chancellor of the Exchequer and the Secretary of State for Housing, Communities and Local Government in time for Spring Statement 2018 and a full report for Budget 2018.”

Has Letwin’s final report (published alongside the budget on 29 October 2018) twisted itself away from the examination question that he was set? In my view, read as a set along with the previous two stages of his work, it is pretty clear how his thinking has developed. But he has ended up making a surprisingly radical and, to my mind, impractical, set of recommendations that surely will not find traction with this Government and which on any reflection would surely not increase the “speed of build out“. Perhaps due to the deadline he was set, the recommendations in the final report are not accompanied by any evidence. They are also set out in some detail (see for example the tables embedded in a later part of this blog post) at the expense of any commentary on, for example, the proposals to encourage timely delivery that were set out in the February 2017 white paper.

Dear Philip and Sajid

There have been three stages to his work. In his 9 March 2018 letter to the Chancellor and Secretary of State he provided this initial analysis:

The fundamental driver of build out rates once detailed planning permission is granted for large sites appears to be the ‘absorption rate’ – the rate at which newly constructed homes can be sold into (or are believed by the house builder to be able to be sold successfully into) the local market without materially disturbing the market price. The absorption rate of homes sold on the site appears, in turn, to be largely determined at present by the type of home being constructed (when ‘type’ includes size, design, context and tenure) and the pricing of the new homes built. The principal reason why house builders are in a position to exercise control over these key drivers of sales rates appears to be that there are limited opportunities for rivals to enter large sites and compete for customers by offering different types of homes at different price-points and with different tenures.

When a large house builder occupies the whole (or even a large part) of a large site, the size and style (and physical context) of the homes on offer will typically be fairly homogeneous. We have seen examples of some variation in size, style and context on some large sites; but the variations have not generally been great. It has become apparent to us that, when major house builders talk about the absorption rates on a large site being affected by “the number of outlets”, they are typically referring not only to the physical location of different points of sale on the site, but also and more importantly to differences in the size and style (and context) of the products being offered for open market sale in different parts of the site. Even these relatively slight variations are clearly sufficient to create additional demand – and hence additional absorption, leading to a higher rate of build out.

It is also clear from our investigation of large sites that differences of tenure are critical. The absorption of the ‘affordable homes’ (including shared ownership homes) and of the ‘social rented housing’ on large sites is regarded universally as additional to the number of homes that can be sold to the open market in a given year on a given large site. We have seen ample evidence from our site visits that the rate of completion of the ‘affordable’ and ‘social rented’ homes is constrained by the requirement for cross-subsidy from the open market housing on the site. Where the rate of sale of open market housing is limited by a given absorption rate for the character and size of home being sold by the house builder at or near to the price of comparable second-hand homes in the locality, this limits the house builder receipts available to provide cross-subsidies. This in turn limits the rate at which the house builder will build out the ‘affordable’ and ‘social rented’ housing required by the Section 106 Agreement – at least in the case of large sites where the non-market housing is either mixed in with the open market housing as an act of conscious policy (as we have frequently found) or where the non-market housing is sold to the housing association at a price that reflects only construction cost (as we have also seen occurring). If freed from these supply constraints, the demand for ‘affordable’ homes (including shared ownership) and ‘social rented’ accommodation on large sites would undoubtedly be consistent with a faster rate of build out. And we have heard, also, that the demand for private rented accommodation at full open market rents (the scale of which is at present uncertain) would be largely additional to, rather than a substitute for, demand for homes purchased outright on the open market.

The interim report

His interim report in June 2018 then focused on three issues:

• what the build out rate on large sites in areas of high housing demand actually is;

• why the rate of build out on these sites is as it is; and

• which factors would be most likely to increase the rate of build out on these sites without having other, untoward effects.

The interim report is a solid document with strong analysis and a variety of conclusions, one of which being that “if either the major house builders themselves, or others, were to offer much more housing of varying types, designs and tenures (and, indeed, more distinct settings, landscapes and street-scapes) on the large sites and if the resulting variety matched appropriately the desires of the people wanting to live in each particular part of the country, then the overall absorption rates – and hence the overall build out rates – could be substantially accelerated. The policy levers required to bring this about without damaging the economics of individual sites or the financial sustainability of the major house builders are topics for the second phase of my work, on which I shall report at the time of the Budget.”

The final report

And this is precisely what he has sought in part to do in his final report, published alongside the budget on 29 October 2018. I say in part, as there is no real analysis as to whether his proposed policy levers would or would not damage “the economics of individual sites or the financial sustainability of the major house builders“.

Underlying his conclusions seems to be his scepticism as to whether the encouragement in the NPPF for “residential developments to have a mix of tenures, types and sizes which reflect local housing demand (as well as emphasising the importance of good design)“, together with the 2018 NPPF’s requirement for local authorities to encourage the sub-division of large sites, is sufficient to lead to less homogenous development or “the prospect of significant increases in the rapidity of build out on such sites“.

He gives no evidence for this assumption. Even the 2012 NPPF (as now revised) is, after all, still working through into plans and permissions.

Instead of trying to work with the grain of the existing system, he recommends that “the Government should adopt a new set of planning rules specifically designed to apply to large sites. The purpose of these rules should be to ensure that all sites in areas of high housing demand whose size exceeds a certain threshold are subject to an additional form of planning control that requires those owning such sites to provide a diversity of offerings on the site which are able to address the various categories of demand within the local housing market. This, in turn, should ensure that houses can be built at a greater rate than at present on such sites, because the absorption rate for each category of housing will be complementary, yielding, overall, a greater absorption of housing by the local market as a whole in any given period.”

Ahead of a new legislative structure (both primary and secondary legislation) and an annex to the NPPF (I suspect it would take more than an annex – he’s driving a coach and horses through the thing as far as large housing sites are concerned), he envisages that the new rules could first be brought in by a written ministerial statement, secondary legislation and the policy annex. “If, for example, the Government decides to adopt my recommendations at the end of 2018, I suggest that it should be made clear to the owners of existing large sites in areas of high housing demand, and to those who are taking such large sites through the current planning system before commencing works, that the new rules governing planning permission for large sites will come into force at the start of 2021, and will therefore govern any permissions granted for large sites on or after that date.”

The primary legislation would:

” • define large sites both in terms of a size threshold (which might, for example, be set initially at 1,500 units2) and in terms of boundaries (to ensure that a site which is allocated as a single entity in a local development plan qualifies, even if it benefits from a number of different outline planning permissions);

• require local planning authorities, when granting allocations, outline permissions or final planning permissions for any large site or any part of a large site in areas of high housing demand, to comply with the new secondary legislation and the new planning policy relating to large sites – and, in particular, to include within all outline planning permissions for large sites in areas of high housing demand a requirement that ‘housing diversification’ on such sites should be a ‘reserved matter’; and

• establish the principle that all permissions for reserved matters granted in relation to such large sites should contain diversi cation requirements in accordance with the new secondary legislation and the new planning policy for large sites.”

The secondary legislation would:

” • amend the Town and Country Planning (Development Management Procedure)(England) Order 2015 to include type, size and tenure mix (alongside the current provision for prescription of access, appearance, landscaping, layout and scale) as characteristics that can be prescribed as reserved matters for large sites in areas of high housing demand; and

• require any applicant making an outline planning application for a large site or an application for final permission for a phase of a large site in an area of high housing demand to prepare a diversification strategy, specifying the types of diversity that will be exhibited on that site or in the part of the site to which the application refers.”

The new planning policy document would set out the diversification principles that are to apply to such large sites in areas of high housing demand in the future. By diversification, he means, for example, “housing of varying types, designs and tenures including a high proportion of affordable housing“, as well as “more distinctive settings, landscapes and streetscapes“. By all means strengthen the NPPF if further strengthening is needed (is it?) but how much of this is specific to schemes of 1,500 homes plus.

Then it really starts to get weird. Because there will be “scope for disagreement about whether a particular applicant has made a genuine effort to provide sufficient diversity to address multiple markets simultaneously and hence to increase the overall absorption rate and build out rate. Accordingly, in order to minimise recourse to appeal or litigation, I recommend that the Government should establish a National Expert Committee.

The primary purpose of this Committee should be to arbitrate on whether any application that causes a disagreement between the local planning authority and the applicant (and consequently comes to appeal) satisfies the diversification requirement, and is therefore likely to cause high build out rates.

The secondary purpose of the Committee would be to offer informal advice to any developer or local planning authority that was considering a large site application. I recommend that the Housing Secretary should guide local planning authorities to consult the National Expert Committee before approving any such large site application in an area of high housing demand.”

Why on earth would a new quango such as this be created?

For sites that will already have an outline planning permission before 2021, Letwin recommends that there should be financial incentives (ie government funding) for house builders to accept changes to their existing site plans. Developers would enter into a section 106 agreement to document their continued commitment to the diversity requirements. Letwin says that he has taken legal advice and is confident that the “voluntary transaction” that he proposes will prove to be lawful – perhaps, but it would certainly be unusual. Would the local planning authority be a party? Who would enforce?

One Step Beyond

He then goes “one step further” in relation to “large sites that have yet to be allocated within a local authority’s local plan“. He recommends “that the Government should, as part of the new primary legislation, introduce a power for local planning authorities to designate particular sites within their local plans as sites which can be developed only as single large sites and which therefore automatically become subject to the new planning rules for large sites. In addition, I believe that the local planning authority should be empowered to specify, at the time of designation, strong master-planning requirements including a strict design code as well as landscaping and full and specific infrastructure requirements.”

This in part appears to be a device to ensure that “the land value of those sites is not raised as far above the alternative use value as would be the case if a site were allocated in a local plan and subsequently obtained outline permission under our current rules“. But this can already be done by local planning authorities for good planning reasons, where comprehensive development is required for reasons of, for instance, sustainability or viability. Is Letwin going further than that?

What if there is no good planning reason why the site could not be sustainably be built out in parts? And what is indeed a single development? This will all prove hugely contentious. Particularly given that he goes on to indicate that to “ensure that a reasonable balance is struck between promoting the public interest through increased diversity and faster build out rates on the one hand, and proper recognition of the value of the land on the other hand, I recommend that the Housing Secretary (when issuing updated viability guidance alongside the new planning framework) should guide local planning authorities towards insisting on levels of diversity that will tend to cap residual land values for these large sites at around ten times their existing use value.”

No evidence is given as to why the level above which land values would be expropriated by the state without compensation (which, after all, would be the effect of the proposal) is set at 10 x EUV.

Letwin recognises that significant support will be needed from Homes England: “planning rules are by their nature passive and reactive. They can prevent things from happening (if they are properly enforced); but they can only do a very limited amount to encourage applicants to follow the spirit of the rules and hence to achieve fully the outcomes the rules have been created to achieve.”

He then goes on to visualise local authorities being empowered to bring forward sites themselves via a development vehicle, in one of two ways:

(a) the local authority could use a Local Development Company (LDC) to carry out this development role by establishing a master plan and design code for the site, and then bringing in private capital through a non-recourse special purpose vehicle to pay for the land and to invest in the infrastructure, before “parcelling up” the site and selling individual parcels to particular types of builders/providers offering housing of different types and different tenures;”

(b) the local authority could establish a Local Authority Master Planner (LAMP) to develop a master plan and full design code for the site, and then enable a privately nanced Infrastructure Development Company (IDC) to purchase the land from the local authority, develop the infrastructure of the site, and promote a variety of housing similar to that provided by the LDC model described above.

He sees local authorities that use these vehicles being given “clear” compulsory purchase powers over the large sites that the authorities allocate and indicates that “it would also make sense to consider the possibility of giving local authorities such CPO powers in relation to large sites that have been allocated in their local plan in the past but which have not obtained outline permission after a long period has elapsed.”

Even when compulsory purchase compensation values have been reduced by the mechanisms requiring build out as a single site (query how that is defined in practice) and by increasing the required diversity until the 10 x uplift on EUV is not exceeded, will development (with the required diversity) be viable for a local authority to bring forward? Will any authority have the resources for the task? Will non-recourse lending really be available to the extent that would be required? Why would anyone start on the process of promoting a large site for development when it can be snaffled as part of a larger “single site” in this way?

The notions in the report could be read as moving to the public sector the role of strategic land promotion companies, which I suspect (for all that they are maligned) to be responsible for a high proportion of the major housing sites that do come forward at present. So, to misappropriate Kit Malthouse’s recent analogy that he applied to Homes England, we would lose some WD40 in the system: the companies with the incentive to identify sites, assemble them, identify and overcome infrastructure constraints, devise a viable and acceptable form of development, pursue allocation and permission, open up land with strategic infrastructure and dispose of parcels to house builders. And, going back to the original terms of reference, this will “increase the speed of build out“?

I appreciate that this report was delivered to a deadline, which it achieved, but (unlike the previous stages of Sir Oliver’s review) it seems to me to lack any robust evidential basis at all to justify the wholly new structure that it proposes for allocating, permitting and delivering schemes with 1,500 or more dwellings. Nor does the review interest itself with any more practical nudges that could be introduced into the current system. If it just goes on the “nice but radical ideas” shelf, another year will have been wasted, without any real progress towards making practical improvements that might improve build out rates. After all, Homes England is already playing a hugely positive role in unlocking large-scale housing development and indeed on 30 October 2018 published its strategic plan for 2018/2019 – 2022/2023, setting how it intends to go much further to use its “land, money, powers and influence to increase the pace, scale and quality of delivery“. When the Government responds to the Letwin report in early 2019 I will be looking to see whether any measures that are to be taken forward will pragmatically assist Homes England’s practical work – they are the ones rolling up their sleeves on all this.

Lastly, if as a consequence of implementation of these proposals we were to see the private sector focusing its attention on smaller sites, in preference to these sites which can really make a difference in terms of delivering at scale, that would in my view be inconsistent with the brief that was set.

Stick or twist?

Simon Ricketts, 3 November 2018

Personal views, et cetera

PS No sooner had I finished this post and poured some strong coffee than I saw this morning’s announcement that the Secretary of State has appointed Professor Sir Roger Scruton to chair a ‘Building Better, Building Beautiful’ Commission – no-one could criticise the current build out rate of MHCLG when it comes to reports and reviews.

LAMP lighter