An Update On CIL: Reform Promised, Meanwhile Continuing & Increasingly Expensive Uncertainties

Well done for getting past the heading.

Someone recently asked me whether the Government ever changes its proposals as a result of a consultation process. For an example of just such a thing, I was able to point to the Government response to supporting housing delivery through developer contributions: a summary of consultation responses and the Government’s view on the way forward (29 October 2018). The proposals set out in the Government’s March 2018 consultation paper (summarised in my 10 March 2018 blog post Developer Contributions, CIL, Viability: Are We Nearly There Yet?) have been modified significantly as a result of consultation, mostly for the better in my view at least.

This blog post focuses on the changed proposals and then looks at some looming issues facing phased developments in areas where charging authorities are looking to increase rates (I’m focusing on the Mayor of London’s MCIL2 but I’m sure the issue is of wider application).

The Government response

The document acknowledges some of the flaws of the current system:

The complexity and uncertainty of the current system of developer contributions is acting as a barrier to the delivery of housing. The system does not react quickly to changes in market conditions or allow local authorities to effectively secure the contributions needed to support new development. It is also not as transparent as it should be; local communities are not clear what infrastructure is provided alongside new development. And the current system could also be more effective in securing funding towards strategic infrastructure and supporting cross boundary planning.”

The Government intends to consult on draft regulations “later this year” to implement the changes set out in the March 2018 consultation document, as now modified. It is important to note that the Government will “also consider whether changes could be made to the Community Infrastructure Levy to incentivise the build out of developments.” (perhaps something that Sir Oliver Letwin might have looked at but…).

The Government has now modified its proposed changes as follows:

1. The previous proposal to replace charging authorities’ current statutory consultation requirements, in relation to proposed charging schedules, with self-certification as to whether it has sought “an appropriate level of engagement” has been amended. The Government “intends to take forward a modified proposal to ensure that regulations continue to require charging authorities to consult on draft charging schedules, whilst removing the current statutory requirement for two separate rounds of consultation in every circumstance.”

2. The pooling restriction will now be removed in its entirety in all areas. Hooray! Although of course there is the risk that tariff-type section 106 contribution requirements will again become more prevalent, in my view the pooling restriction led to many unnecessary problems and uncertainties, which would have continued under the Government’s March 208 idea of only removing the restriction in in areas where specified criteria were met.

3. The Government had intended to introduce a two month grace period for developers to submit a commencement notice in relation to exempted development, to address disproportionately severe problems arising for eg self-builders who, if they fail to meet procedural requirements, find not only that they fail to qualify for any exemption but that all CIL due has become immediately payable. The Government will not now introduce the grace period (which local authorities considered could lead to practical complications) but instead will be “making changes to the penalties associated with the failure to submit a Commencement Notice prior to development being started. This will ensure that any penalty is set at a proportionate level and will not result in the whole liability becoming payable immediately.”

There may also be more guidance as to potential exemptions: “A number of responses sought additional exemptions to address the unintended viability impacts of Levy liabilities on particular forms of development. The Government will consider how guidance could be used to manage these effects by encouraging authorities to take account of these issues when setting Levy rates and choosing how they use existing powers for discretionary social housing relief. In addition, the Government has already committed to bring forward legislation to exempt Starter Homes from the Community Infrastructure Levy.”

4. The complicated proposal in the March 2018 consultation document that charging schedules might be set with reference to the existing use of land has been dropped. “However, the Government has reviewed this proposal and considers there are existing flexibilities in the Community Infrastructure Levy Regulations that, through the use of differential Levy rates, will allow local authorities to go some way towards achieving the objective of the proposed reform. The Government therefore proposes to make changes to guidance to support local authorities to set differential rates more effectively.

5. At the time that it publishes the draft amendment regulations, the Government intends to “consult on changes to indexation of Levy rates and the way in which it would be implemented“. Its current preference is to index CIL rates “for residential development to the House Price Index using local-level data on an annual basis” and to index rates for non-residential development to the Consumer Price Index. It recognises the transitional issues that will arise.

6. The Government still intends to remove the restriction in relation to section 106 obligations that relate to an infrastructure project or type of infrastructure that is set out in the authority’s Regulation 123 list. “New reporting standards, which are set out in the Infrastructure Funding Statement, will address concerns about double dipping by ensuring that there is transparency over how developer contributions from both CIL and section 106 planning obligations are being used, rather than by placing formal restrictions in regulations.” We need to watch this one with care!

In relation to one specific issue that often leads to wrangles: “The Government also recognises the need to address existing uncertainty around using section 106 planning obligations to collect monitoring sums. The Government therefore intends to take forward proposals to make clear that local authorities can seek a fee from applicants towards monitoring planning obligations. In developing these proposals, the Government will consider how best to ensure that monitoring sums are set at an appropriate level.”

7. The Government had intended to give combined authorities and joint committees with strategic planning powers the ability to charge a Strategic Infrastructure Tariff. “The Government has decided to take forward a modified proposal, to enable Combined Authorities with strategic planning powers to take forward a Strategic Infrastructure Tariff, and to encourage groups of charging authorities to use existing powers to more effectively support the delivery of strategic infrastructure through the pooling of their local Community Infrastructure Levy receipts. In the longer term, the Government will bring forward proposals for allowing joint planning committees to charge the tariff, and will review options for giving other groups the power to levy a Tariff.”

The Government had also included a final “catch all” question seeking any other comments. Particular issues that were raised in responses included “the definition of gross internal area, implementation of the Levy in particular circumstances (such as in relation to development that takes place in a number of phases or there is a change of use), and the operation of exemptions and reliefs, indexation and in-kind payment.

Issues such as these are indeed causing much uncertainty.

The implications of increased rates/MCIL2

Whilst we wait for eventual reform of the system, of more immediate focus are the implications of gradual increases by charging authorities in CIL rates.

In London, the Mayor of London is waiting for the inspector’s report following the examination into the draft charging schedule for MCIL2. MCIL2 is proposed to part-fund Crossrail 2, in the way that MCIL1 (together with a related policy of seeking section 106 contributions in relation to some areas and types of development) is part-funding Crossrail 1.

The charging schedule for MCIL1 was adopted on 1 April 2012 (which is why there are many section 106 agreements and permissions dated March 2012, as developers and boroughs scrambled to ensure that permissions were not subject to the levy!).

This table sets out borough by borough the significant sums of money that MCIL1 has now raised:

The section 106 contributions policy for Crossrail (set out in the Mayor’s Crossrail Funding SPG, updated March 2016) predated MCIL1 and provided for section 106 contributions based on the following table and plans:

The standardised wording included in relevant section 106 agreements provides that any MCIL1 which is payable reduces the contributions which are required to be made under the relevant section 106 agreement.

As long as the inspector’s report is received on time and gives it a clean bill of health, MCIL2 will be adopted on 1 April 2019. The changes in rates, compared to where the 2012 rates currently sit with indexation applied, are mostly not huge, but they are significant in some areas. In areas where the increases are material, I am sure we will see a similar rush to beat the deadline.

One uncertainty is of course whether the examination inspector will accept a charging schedule that is predicated on Crossrail 2 coming forward. Little has progressed on the project since my 1 July 2017 blog post, Crossrail 2: Where Are You? We are all still awaiting outcome of an independent affordability review being chaired by Mike Gerrard. The Mayor is hedging his bets, simply indicating:

Should the Crossrail 2 project not be taken forwards, the Mayor would be able to apply the MCIL 2 proceeds to fund other strategic infrastructure.”

Assuming that MCIL2 is waved through and the charging schedule is adopted on 1 April, the relevant point at which it takes effect is determined by everyone’s least favourite phrase in the CIL Regulations: “at the time planning permission first permits the chargeable development“.

For a non-phased permission, this is the date of the permission – easy.

For a phased outline permission, this is either “the date of final approval of the last reserved matter associated with that phase” or “if earlier, and if agreed in writing by the collecting authority before commencement of any development under that permission, on the day final approval is given under any pre-commencement condition associated with that phase“.

For a phased full permission, this is either “the day final approval is given under any pre-commencement condition associated with that phase” or “where there are no pre-commencement conditions associated with that phase, on the day planning permission is granted“.

It will be seen that (1) the revised charging schedule is liable to bite in respect any phase of an existing phased permission if sufficient progress has not been made in relation to reserved matters or discharging pre-commencement conditions in relation to that phase and (2) that there are inherent uncertainties in the drafting, eg

⁃ What does “associated with that phase” mean?

⁃ Does “any” mean “any” or, in fact, “all“?

As a final example of the inadequacies of the legislation: where there is a phased permission and a revised charging schedule is subsequently adopted, the only indexation that applies is of the amount arising from the initial charging schedule up to the end of the year prior to the date of the permission. There is no further indexation through to commencement of development or any indexation of the revised charging schedule insofar as it applies to the phases! Would it not be simpler and more predictable if indexation were not to stop at the initial grant of the permission and instead to continue through to final approval (or even commencement of development) in relation to each phase, but if the potential application of revised charging schedules were removed?

In case anyone has made it down this far…

In conclusion:

⁃ the proposed reforms, and most recent proposals, look to be mainly positive

⁃ but the whole regime really does still need simplifying: to state the obvious, significant liabilities can unexpectedly arise for the unwary – and large sums of money can turn on uncertain issues of interpretation.

Simon Ricketts, 9 November 2018

Personal views, et cetera

Author: simonicity

Partner at boutique planning law firm, Town Legal LLP, but this blog represents my personal views only.

One thought on “An Update On CIL: Reform Promised, Meanwhile Continuing & Increasingly Expensive Uncertainties”

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: