Bad Timing: More On Appropriate Assessment From Court & Govt Post POW

This is intended to be an update as to appropriate assessment under the Conservation of Habitats and Species Regulations 2017 rather than a blog post on the domestic effect of EU environmental law post-Brexit.

But I’ll address that briefly first:

EU environmental law post-Brexit

The position remains pretty much as summarised in my 18 September 2018 blog post Planning, Brexit, supplemented by my 22 December 2018 blog post The Office For Environmental Protection. Whilst there is a general initial saving for EU-derived domestic legislation and whilst section 16 of the EU (Withdrawal) Act 2018 sets a process for maintaining EU environmental principles, the “no deal” risks are still that:

(1) the latter depends on an Environment Bill being laid before Parliament and enacted (we so far have only seen draft provisions of the most directly relevant parts of what is proposed), a set of draft environmental principles being consulted upon and approved and the new Office for Environmental Protection being established, all before 31 October 2019 and

(2) post-Brexit, all EU-derived domestic legislation will be reviewed as to its continuing appropriateness and the degree of protection as regards this, presently provided by the environmental principles and governance mechanism in section 16, could easily be amended, replaced or sidestepped by this or a subsequent government.

DEFRA published an Environment Bill summer policy statement on 23 July 2019 but, whilst I am sure the war cabinet talks of little else, there simply is not the time available for the environmental principles and governance machinery to be up and running by the end of October 2019. Even when the machinery is established, it is susceptible to subsequent tinkering and dismantling by way of subsequent legislation.

Appropriate assessment

The immediate implications of the European Court of Justice’s ruling in People Over Wind were covered in my 20 April 2018 blog post EU Court Ruling: Ignore Mitigation Measures In Habitats Screening.

In England and Wales the main problems caused by the judgment have revolved around:

(1) authorities being caught out through no longer being able to screen out the need for appropriate assessment by relying upon commitments to introduce mitigation measures;

(2) until the February 2019 changes to the NPPF, the disapplication of the NPPF’s “tilted balance” where appropriate assessment is required.

MHCLG has now included within its Planning Practice Guidance a specific section dealing with appropriate assessment (22 July 2019).

By coincidence, two days after the new guidance was published, two separate judgments were handed down by the High Court on different aspects of the appropriate assessment regime, both cases stemming from People Over Wind issues and both cases examples of plain bad timing.

Gladman Developments Limited v Secretary of State (Dove J, 24 July 2019) was a challenge by Gladman to the dismissal by the Secretary of State of its appeal in respect of a proposed development of 225 dwellings in Cliffe Woods, Kent.

The inquiry had been held in November 2017, pre People Over Wind. The parties agreed that the tilted balance applied in favour of the proposal as there was a shortfall in the Medway Council’s five year housing land supply. The parties also agreed that a condition requiring an environmental construction management plan was sufficient to mitigate any ecological concerns. Following an HRA screening process that took into account a financial contribution towards a strategic access management and mitigation strategy (SAMMS) “no adverse consequences were identified in respect of the impact of any additional recreational pressures on the Thames Estuary Marshes SPA/RAMSAR and the Medway Estuaries and Marshes SPA/RAMSAR sites.”

The inspector recommended approval in his report dated 29 March 2018. The People Over Wind judgment was handed down on 12 April 2018. The Secretary of State invited representations from the parties as to whether appropriate assessment was now required in the light of the judgment, and on their views as to the correct application of planning policy in the light of it – a reference to paragraph 119 in the 2012 NPPF which disapplied the tilted balance in circumstances in the case of development requiring appropriate assessment.

Gladman submitted as part of its representations a report prepared by its ecologists, information to ensure that the inspector could carry out appropriate assessment and reach a conclusion that there were no likely significant effects on the integrity of of the SPAs. It also submitted that it would be “illogical and perverse to disengage the tilted balance in these circumstances”.

Before the Secretary of State reached his decision on the appeal, more generally on 26 October 2018 he embarked a technical consultation as to potential changes to the methodology for assessing local housing need and as part of that consultation he sought views on his proposal to amend the NPPF to make it clear that the tilted balance “is disapplied only where an appropriate assessment has concluded that there is no suitable mitigation strategy in place”, having missed the opportunity to make that change in the 24 July 2018 version (within which paragraph 177 simply replicated the old paragraph 119).

The Secretary of State’s decision letter was issued on 9 November 2018. He found that appropriate assessment was required and stated that on the basis of the appropriate assessment which he had carried out he could “safely conclude that the proposed development would not adversely affect the integrity of any European site”. He noted that under paragraph 177 of the 2018 NPPF “the presumption in favour of sustainable development does not apply where development requiring appropriate assessment is being determined”. He dismissed the appeal.

Gladman challenged the decision on a number of grounds, including irrationality in his application of paragraph 177 in the circumstances of the appeal, failure to have regard to the contents of the technical consultation, failure specifically to consult Gladman in relation to the technical consultation and contending that People Over Wind was wrongly decided, requiring a reference to the CJEU to clarify the position.

Dove J rejected all of the grounds. There was nothing unlawful in the way in which the Secretary of State had applied paragraph 177. It was “applied in a straight forward and uncomplicated manner to the circumstances of the present case”. The technical consultation was only a consultation. Indeed:

I see nothing wrong, and indeed much to commend, in an approach whereby a decision-taker continues to apply existing policy whilst it is subject to review, and await the outcome of a consultation process on the review of a policy before applying any new policy which might emerge. For a consultation exercise to be lawful it must be engaged in with an open mind. That must contemplate a number of potential outcomes from the consultation process, (including, potentially, no change to the policy) which could be undermined by the premature second guessing of its outcome through the application of a policy which was being consulted upon. In my view the First Defendant’s approach in applying his existing policy in the present case was in principle entirely correct.”

There was no basis for asserting that Gladman should have been specifically consulted as part of the technical consultation and in any event they had not been prejudiced by any failure to consult.

Lastly, he was unpersuaded that there was any justification for the reference sought to the CJEU or that People Over Wind was wrongly decided: “the need for full and precise analysis removing all reasonable scientific doubt, reflects a consistent line of authority in the CJEU emphasising these features of the requirements of the Habitats Directive…Whilst there may be cases in which the existence of significant effects could be addressed by the examination of mitigating measures at the Appropriate Assessment screening stage that is not, in principle, any justification for not undertaking the Appropriate Assessment itself.” Furthermore, as also relied upon by the CJEU in People Over Wind, “the taking account of mitigation measures and exclusion of the Appropriate Assessment process may also deprive the public of a right to participate in the decision-taking process.”

The final kick in the teeth for Gladman must have come when, after the 24 July 2018 version of the NPPF missed the obvious opportunity to resolve the widespread problems caused by People Over Wind, it was finally put right in the 19 February 2019 version. So if the decision letter had been issued either at least six weeks before the 12 April 2018 ruling in People Over Wind (such that the decision was beyond the legal challenge period) or after 19 February 2019, the chances are they would have had their permission. A Secretary of State who actually wanted to see housing would surely have sorted out the policy issue more quickly – or delayed the decision letter. Bad timing indeed.

The timing was similarly awkward in R (Wingfield) v Canterbury City Council & Redrow Homes South East (Lang J, 24 July 2019). Outline planning permission was obtained on 5 July 2017 for up to 250 dwellings and associated development at Hoplands Farm, Westbere, Kent. The site is near SPAs and an SAC. On the basis of mitigation proposals, Canterbury City Council concluded, having taken advice from Natural England, that appropriate assessment was not required.

The judicial review period expired without challenge and the site was sold to the interested party, Redrow Homes. Reserved matters approval was sought in December 2017 for the first phases of development. Then came that People Over Wind ruling on 12 April 2018. In the light of the judgment, the council carried out an appropriate assessment and concluded that, with mitigation, the project would have no adverse effect on the integrity of the European protected sites. Reserved matters approval was granted on 12 February 2019.

The claimants argued that “the Council acted in breach of EU law by failing to conduct an HRA before granting outline planning permission and impermissibly taking into account mitigation measures when screening the proposed development, contrary to the CJEU judgment in the People over Wind case. The effect of the judgment of the CJEU was to render the grant of outline planning permission a nullity, which could no longer be relied upon. Further or alternatively, when the Council realised its error, it should have revoked the outline planning permission and re-considered the application. Instead, it unlawfully conducted an HRA at the reserved matters stage, when it should have been conducted at the earliest possible stage, before the grant of outline planning permission.

Lang J rejected both arguments. The submission that “the effect of the judgment of the CJEU in People Over Wind was to render the grant of outline planning permission a nullity was both contrary to authority, and wrong in principle. A decision made by a public body is valid unless and until it is quashed”. Further, “the Council could lawfully conduct an appropriate assessment at the reserved matters stage, in the circumstances of this case”.

In considering whether the Council could legitimately remedy its earlier error by conducting an appropriate assessment at reserved matters stage, instead of revoking the grant of outline planning permission, I have taken into account that the consequences of revoking planning decisions long after they have been made, and the time limits for challenge have expired, are disruptive and undermine the principle of legal certainty. As Laws J. said in R v Secretary of State for Trade and Industry, ex parte Greenpeace Ltd [1998] Env LR 415, at [424], applicants for judicial review must act promptly, so as to ensure that the proper business of government and the reasonable interests of third parties are not overborne or unjustly prejudiced by litigation brought in circumstances where the point in question could have been exposed and adjudicated without unacceptable damage.

In this case, the IP acquired its interest in the Site after outline planning permission had been granted and the time for bringing a judicial review challenged had expired. Although building operations have not yet commenced, time and money has been spent in bringing this project to fruition. The Council considers that the development will bring tangible benefits to the community, although local residents, such as the Claimant, take a different view.

In my judgment, the Council’s decision to remedy its earlier error by conducting an appropriate assessment at reserved matters stage was permissible under EU and domestic law, and it was a proportionate and effective remedy for the breach of EU law […]

Alternatively if my analysis is not correct, I would nonetheless refuse relief in this case. The Court may refuse relief where there has been a breach of EU law, if the substance of the EU right has been complied with.”

The claimant also sought to argue that the HRA was deficient. It was not:

the HRA conducted by the Council was appropriate for the task in hand, particularly bearing in mind that the Council was able to draw upon the detailed research and assessment in the ‘Report to inform a Habitats Regulations Assessment’, as well as the further reports submitted by the IP. Its findings were complete, precise and definite and there were no significant lacunae. The Council was entitled to rely upon Natural England’s endorsement of its HRA, particularly since Natural England had initially raised concerns about the evidence-base provided by the applicants, and those concerns were addressed by the further evidence produced by the IP. Natural England, as the custodian of the Stodmarsh designated sites, was particularly well placed to judge the risks from the proposed development. In my view, the Claimant’s challenge did not come close to meeting the high threshold of Wednesbury irrationality; it was primarily a disagreement with the Council’s exercise of its planning judgment.”

So bad timing in this case for the claimant, unable to take advantage of the windfall that People Over Wind appeared to represent.

Even if we leave the EU, I suspect that we will not be leaving behind these sorts of arguments for a good time yet – and it is apparent from the Gladman case that (1) the resulting trip hazards are as often those introduced by our own domestic policies and (2) when it comes to CJEU cases such as People Over Wind, however inconvenient, our domestic courts are not going to be turning the clock back.

Simon Ricketts, 2 August 2019

Personal views, et cetera

New Cabinet, Poor Doors, No Windows

La Sagrada Familia = our planning system. Never finished, it now has new architects.

I don’t know what new extrusions, reversals or pauses to expect from Robert Jenrick, Esther McVey and the rest of the MHCLG ministerial team yet to be announced.

I do know that Robert Jenrick was a member of the Commons Public Accounts Committee which published a report Planning and the broken housing market (19 June 2019). From the introduction:

The government has an ambitious target of delivering 300,000 new homes per year by the mid-2020s, but inherent problems at the heart of the housing planning system are likely to jeopardise this target. If the Government delivers 300,000 new homes per year, this would be a significant increase in the rate of house building, with the number built a year averaging only 177,000 in the period 2005–06 to 2017–18. While the Ministry of Housing, Communities and Local Government (the Department) has made some recent reforms to the planning system, much more needs to be done and it still does not have a detailed implementation plan for how it will scale-up house building.”

He knows something of the task ahead.

The report also says this:

We were concerned about poor quality in the building of new homes and of office accommodation converted into residential accommodation through permitted development rights. The Department stressed that it was critical that quality was good enough. It agreed that there are issues—particularly when dealing with large office blocks— that the number of homes created out of that office block can be too high, with inadequate space standards and build quality. The Department told us that it has committed to a review of permitted development rights which turn commercial properties into residential accommodation. This review will look at the quality of those homes and what should be built.

In the lead up to the new premiership, May’s Government seemed to have a renewed focus on the quality of homes and communities. I wanted to write something on the various strands within this theme, if only to capture a series of links to documents, before we lose the thread in a slew of new announcements.

Minimum dwelling sizes

My 23 March 2019 blog post We Have Standards referred to previous Secretary of State James Brokenshire’s March 2019 statement that he intended to “review permitted development rights for conversion of buildings to residential use in respect of the quality standard of homes delivered. […]. We will also develop a ‘Future Homes Standard’ for all new homes through a consultation in 2019 with a view, subject to consultation, to introducing the standard by 2025.”

Theresa May suggested in her 26 June speech to the Chartered Institute of Housing that, whilst it would ultimately be a matter for her successor, the nationally described space standard should apply “by regulation” to all new homes. As explained in my 23 March 2019 blog post, it is presently for each local planning authority to decide whether to incorporate the standard in their local plan as a policy requirement such that an applicant for planning permission then needs to demonstrate compliance.

I do not accept that, in 2019, we can only have sufficient and affordable housing by compromising on standards, safety, aesthetics, and space.

That is why I asked the Building Better, Building Beautiful Commission to develop proposals for embedding beautiful, sustainable and human-scale design into the planning and development process.

I look forward to reading the interim report next month.

It is why the Ministry of Housing will shortly be launching a consultation on environmental performance in new build homes, with a Future Homes Standard that will give all new homes world-leading levels of energy efficiency by 2025.

And it is why I want to see changes to regulations so that developers can only build homes that are big enough for people to actually live in.

It was the Addison Act that brought modern space standards to English housing law for the first time.

During the Bill’s second reading, the architect of the standards, Sir Tudor Walters, urged MPs to “take care that the houses planned in the future are planned with due regard to comfort, convenience, and the saving of labour”.

It is a message we would do well to return to today.

Because in the years since, the pendulum has swung back and forth between regulation and deregulation, leading to a situation today where England does have national standards – but ones that are largely unenforceable and inconsistently applied.

Some local authorities include the Nationally Described Space Standard in their local plans, making them a condition of planning permission.

But others do not.

And even where they are applied, as planning policies rather than regulations they are open to negotiation.

The result is an uneven playing field, with different rules being applied with differing levels of consistency in different parts of the country.

That makes it harder for developers to build homes where they are needed most.

And it leaves tenants and buyers facing a postcode lottery – if space standards are not applied in your area, there is no guarantee that any new homes will be of an adequate size.

Now I am no fan of regulation for the sake of regulation.

But I cannot defend a system in which some owners and tenants are forced to accept tiny homes with inadequate storage.

Where developers feel the need to fill show homes with deceptively small furniture.

And where the lack of universal standards encourages a race to the bottom.

It will be up to my successor in Downing Street to deal with this.

But I believe the next government should be bold enough to ensure the Nationally Described Space Standard applies to all new homes.

As a mandatory regulation, space standards would become universal and unavoidable.

That would mean an end to the postcode lottery for buyers and tenants.”

[Creating space for beauty: The Interim Report of the Building Better, Building Beautiful Commission was published in July 2019, sans its now reinstated chairman Sir Roger Scruton, who will be able to influence the tone of the Commission’s final report, due in December 2019. The interim report is a wide-ranging discursive read ending with 30 “policy propositions”. There is much good stuff about, in Theresa May’s words, “embedding beautiful, sustainable and human-scale design into the planning and development process”. None of its policy propositions urge prescription as to dwelling size, although there is this passage within its commentary:

Above all, polling and pricing data show that people are looking for homes that meet their needs and are in the right place. Every academic or commercial study we have been able to find has shown that, other things being held equal, bigger homes are worth more and so are better connected ones. For example, a study of every single property sale in six British cities showed that in, say, Liverpool, every additional bedroom brought an additional £15,000 of value. Similar patterns were visible in Leeds, Newcastle, Manchester, Birmingham and London. In their response to our call for evidence, the RIBA also highlighted their polling research into user needs that highlighted the importance of generosity of space, high ceilings, windows that flood principal rooms with light and detail that adds character”.]

Some I know disagree, but to my mind Theresa May’s statement missed the real target in relation to minimum dwelling sizes. At present authorities can apply the nationally described space standard if they so choose. But what authorities cannot prevent (other than by removing the relevant permitted development rights in the first place by way of Article 4 Direction) is the creation of very small dwellings pursuant to the General Permitted Development Order, the adequacy of the accommodation to be created not being one of the matters in relation to which prior approval is required under the Order. Either this needs to be a matter for which prior approval is required or it needs to be addressed by way of separate regulation.

Other minimum standards in relation to permitted development rights schemes

There is still so much misunderstanding as to the operation of permitted development rights. General horror has been expressed as to the permitted development appeal in Watford for the proposed conversion of a light industrial unit to apparently windowless bed-sit/studio accommodation, allowed by an inspector in his decision letter dated 5 July 2019:

Overall, I recognise that the proposed units are small and that, for example, living without a window would not be a positive living environment. However, the provisions of the GPDO 2015 require the decision makers to solely assess the impact of the proposed development in relation to the conditions given in paragraph PA.2. The appellant has also made clear that they are not proposing any external works at this stage.”

Photo: Watford Observer

The absence of any control over size of the proposed dwellings is indeed appalling, see my point above. But I am prepared to bet that the developer, now that he has prior approval to the use of the building as dwellings, will come back with an application for planning permission for the installation of windows and for the general recladding of the building. If it had all been applied for as one planning application, the authority would no doubt have objected to the principle of the change of use – just look at the sequencing of applications with most PD schemes and there is surely nothing wrong in that – the permitted development right just relates to use – and of course does not override other regulatory requirements.

Part B of the Building Regulations requires that every habitable room up to 4.5m from ground level either (1) has an openable window with dimensions of at least 45cm by 45cm, no more than 110cm above the floor or (2) (on the ground floor) opens directly onto a hall leading directly to an exit or (above the ground floor) with direct access to a protected stairway. Adequate ventilation is also required.

Since 20 March 2019 the Homes (Fitness for Human Habitation) Act 2018 also imposes specific requirements on landlords letting residential property for a period of less than seven years. In determining whether a dwelling is unfit for human habitation regard will be had to, amongst a range of matters, natural lighting and ventilation. MHCLG has published specific guidance for landlords as to the operation of the Act.

In considering whether further legislation or guidance is needed, ministers will need to consider carefully the extent to which the planning system should duplicate systems of protection provided in other legislation and where genuinely there are gaps that would allow unacceptable outcomes.

The Future Homes Standard

What of James Brokenshire’s reference in March of consultation on a proposed Future Homes Standard this year, with a view to introducing the standard by 2025? This was a reference to the commitment in the then Chancellor’s Spring budget to:

A Future Homes Standard, to be introduced by 2025, future-proofing new build homes with low carbon heating and world-leading levels of energy efficiency. The new standard will build on the Prime Minister’s Industrial Strategy Grand Challenge mission to at least halve the energy use of new buildings by 2030“.

There has not yet been any consultation. The House of Commons Business, Energy and Industrial Strategy Committee, in its 9 July 2019 report, Energy efficiency: building towards net zero, urged a greater sense of urgency:

We welcome the announcement of a Future Homes Standard. Any attempts by housebuilders to water down the standard should be blocked by the Government. The only barrier precluding housebuilders developing to higher standards before 2025 is a preoccupation with profit margins and shareholder returns. Despite receiving billions in taxpayer funds, most housebuilders will only raise the energy standards of their stock if forced to do so. Progressive housebuilders who want to go further are being held back by the laggards who actively lobby the Government to boost their profits, rather than help meet carbon reduction obligations.

We recommend that the Government legislates for the Future Homes Standard as soon as practically possible—and by 2022 at the very latest—to guarantee that no more homes by 2025 are built that need to be retrofitted. We recommend that the Government considers policy drivers at its disposal to drive early uptake. At a minimum, the Government should put in place a compulsory ‘learning period’ from 2022 in a subset of properties in preparation for the full-scale deployment. The Government should oblige bigger housebuilders to undertake regional demonstration projects to show how they will achieve the standard.”

Communities framework

MHCLG published a “communities framework” on 20 July 2019, entitled By deeds and their results:

How we will strengthen our communities and nation , expressed to be the “next step in refreshing the government’s aspirations for stronger, more confident communities. It provides a framework to build on a range of government activity that is contributing to stronger communities in different ways – from the implementation of the Civil Society Strategy and Integrated Communities Action Plan, to our efforts to boost productivity and inclusive growth through the Industrial Strategy and by supporting local industrial strategies across the country.

It promised that the Government will:

• Hold a national conversation with communities across England about their view of who we are as a nation, their vision for the future of their community and our country, and what local and national government can and should be doing to support their community to thrive.

• Establish a series of Civic Deal pilots to test how the Ministry for Housing, Communities and Local Government and the Department for Digital, Culture, Media and Sport put into practice the principles set out in this document in partnership with local areas.

• Publish a Communities White Paper to renew government’s focus on building stronger communities across England. The scope of the White Paper will be developed in partnership with communities and informed by the national conversation and Civic Deal pilots.”

Poor Doors

I referred in my 23 March 2019 blog post to widespread concerns over development projects where affordable housing tenants are prevented from using facilities provided for private market housing residents, for example children’s play areas and entrance/lift lobbies.

The basis for such arrangements may well be economically rational to the developer (preventing service charge leakage and/or preserving a sales premium in relation to the market units), to the registered provider (which would not be in a position to impose service charges high enough to cover the cost of the facilities provided for the market housing) and to the local planning authority (usually keen to protect the profitability of the development so as to secure the maximum amount of affordable housing that can be viably be delivered). But of course there can be wider, more damaging, implications.

On the same day as the communities framework was published, an MHCLG press statement Brokenshire unveils new measures to stamp out ‘poor doors’ announced there would be “measures to tackle stigma and help end the segregation of social housing residents in mixed-tenure developments…planning guidance will be toughened up and a new Design Manual will promote best practice in inclusive design.”

Meanwhile, as to we wait to see what the new ministerial team at MHCLG delivers, the Mayor of London’s new London Plan edges forward. We await the inspectors’ conclusions following their examination sessions but in the meantime the Mayor has published a Consolidated suggested changes version of the plan July 2019.

A specific policy has now been included to require that proposals likely to be used by children and young people should include good quality, accessible play provision that “is not segregated by tenure” (policy S4 B (f)).

Conclusion

With due deference to the list of banned words circulated by Mr Rees-Mogg:

Due to the ongoing change in ministers, with the old lot out, apparently unacceptable and no longer fit for purpose, I can only speculate as to the future of these initiatives. Hopefully I will ascertain more very soon.

I understand your concerns.

Simon Ricketts, Esq. 27 July 2019

Personal views, et cetera

Photo: Go UNESCO

Secretary Of State Throws Another Curve Ball

My 15 June 2019 blog post National Lottery: 2 Problematic Recovered Appeal Decisions focused on two appeals dismissed by the Secretary of State against inspectors’ recommendations.

Well, here is another one, in relation to the Chiswick Curve scheme on the Great West Road within the London Borough of Hounslow, the 19 July 2019 decision letter out just before Parliament rises on 25 July (by which date we will have a new prime minister). Another long inquiry (15 days), long delays (the initial application was made over three and a half years ago, the inquiry was a year ago), detailed analysis from an experienced inspector who had heard the evidence and seen the site first hand, ultimately counting for nothing.

The Secretary of State’s decision followed an inquiry held by inspector Paul Griffiths BSc(Hons) BArch IHBC, into appeals by Starbones Limited against the decisions of the London Borough of Hounslow to (i) refuse planning permission for a mixed use building of one part 32 storey and one part 25 storeys comprising up to 327 residential units, office and retail/restaurant uses, basement car and bicycle parking, residential amenities, hard and soft landscaping and advertising consent with all necessary ancillary and enabling works and (ii) refuse to grant advertising consent for 3x digital billboards. The applications were dated 11 December 2015 and amended in October 2016.

The differences of judgment as between the inspector and Secretary of State appeared to boil down to the following:

⁃ The Inspector considered “that the proposal would bring a massive uplift to the area around it” and would be in accordance with various local plan policies. “While the Secretary of State recognises that public realm improvements and the publicly accessible elements of the scheme…do offer some improvement to current conditions, in terms of accessibility and movement, he does not agree that this constitutes the massive uplift as described by the Inspector.

⁃ Both agreed that the harm to designated heritage assets (the Strand on the Green Conservation Area plus its listed buildings; Kew Green Conservation Area plus its listed buildings; Gunnersbury Park Conservation area plus its listed buildings and Registered Park and Garden, and the Royal Botanic Gardens Kew World Heritage Site plus its listed buildings) would be less than substantial but the Secretary of State disagreed with the inspector’s finding that the public benefits of the proposals would be sufficient to outweigh the harm.

⁃ The Secretary of State disagreed with the Inspector that there would be no conflict with a local plan policy concerning the impact of tall buildings proposed in sensitive locations such as conservation areas, listed buildings and their settings, and World Heritage Sites.

⁃ Accordingly the Secretary of State disagreed with the Inspector and found that the proposals did not comply with the development plan when read as a whole.

⁃ The Secretary of State “considers that the site has a strategic location, and he recognises the constraints and challenges associated with it. While he agrees with the Inspector […] that the proposed design seeks to respond to those challenges in a positive way, he does not find the proposal to be of such high quality as to be a brilliant response to its immediate context. He finds the scale and massing of the proposal to be such that the proposal does not relate to its immediate surrounding. While he recognises that attempts to minimise this impact have been taken with regard to glazing and fins, the building would still dominate the surrounding area. He considers the design to be a thoughtful attempt to respond to the challenges and opportunities of the site, but due to its scale, he disagrees with the Inspector […] that it is a significant benefit of the scheme.”

⁃ The Secretary of State considered that the proposals “would not provide the levels of private and communal amenity space that [the relevant local plan policy] requires. While he has found this to be a limited departure from this policy, the Secretary of State also recognises that the on-site provision, supplemented by the relative proximity of Gunnersbury Park does reduce the weight to be attached to this conflict.”

⁃ Given his finding that the proposals would not be in accordance with the development plan he went on to consider whether whether there were any material considerations to indicate that the proposals should be determined other than in accordance with the development plan. After a detailed analysis in paragraphs 34 to 38 of the decision letter, he concludes:

Overall, the Secretary of State disagrees with the Inspector […], and finds that the moderate weight to be attached to the benefits of the appeal scheme in terms of housing provision, workspace provision and economic benefits, are not collectively sufficient to outweigh the great weight attached to the identified ‘less than substantial’ harm to the significance of the above heritage assets. He considers that the balancing exercise under paragraph 196 of the Framework is therefore not favourable to the proposal.

Local MPs Ruth Cadbury (Labour) and Zac Goldsmith (Conservative) were recorded as having objected to the proposal. The objectors appearing at the inquiry included Historic England, the Royal Botanic Gardens Kew and the Kew Society (the first two instructing Richard Harwood QC and James Maurici QC respectively). Russell Harris QC and Richard Ground QC appeared for the appellant and for the London Borough of Hounslow respectively.

I note that on 19 July 2019, the Secretary of State also refused, against his inspector’s recommendation, Veolia’s called in application for planning permission for an energy recovery facility in Ratty’s Lane, Hoddesdon, Hertfordshire.

The Secretary of State accepted that there is an “urgent and pressing need” for the facility, that there is “no obvious alternative site”. “Given the urgent and pressing need, the Secretary of State considers that the provision of an ERF with sufficient capacity to accommodate the waste demands of the county carries substantial weight in favour of the proposal, and the climate change benefits of the proposal also carry substantial weight”. However, he considered that in view of the fact that the proposal was contrary to the development plan and there were unresolved concerns over highways matters, together with “significant adverse landscape and visual impacts”, the application should be refused. I thought that “need” means “need” but there we go.

Not much getting past this Secretary of State is there? An inference of his recent letter to the Planning Inspectorate (see my 13 July 2019 blog post Less Than Best Laid Plans: Political Pragmatism) might be that he considers that inspectors may on occasion be too robust in their examination of local plans and yet an inference of his approach on recovered appeals and call-ins might be that he considers that on occasion inspectors are not robust enough in assessing development proposals that are before them at inquiry. For my part, neither inference would be justified.

Simon Ricketts, 20 July 2019

Personal views, et cetera

Less Than Best Laid Plans: Political Pragmatism

The Secretary of State sent a curious letter to the Planning Inspectorate on 18 June 2019, which was only placed on the Government’s website on 28 June 2019. (The delay may have been to allow PINS to update its procedure guide for local plan examinations).

It is in two parts:

Sharing information with MHCLG

The Secretary of State reminds inspectors and local authorities that Parliament has given him “a number of powers that, where justified, allow [him] to become involved in plan making. This includes powers to notify or direct the Inspectorate to take certain steps in relation to the examination of the plan or to intervene to direct modification of the plan or that it is submitted to [him] for approval”. He states that he is “frequently asked by those affected by the plan making process to consider use of these powers and must look at each of these requests on a case by case basis. This includes requests from Members of Parliament, who have a legitimate interest in the progress of local plans in their areas and are accountable to their electorates. I am pleased that the Planning Inspectorate’s published Procedural Practice encourages MPs to participate in the examination hearing sessions even if they did not make a representation and I would encourage their involvement in this way”.

He considers that more can be done by way of sharing of factual information so that his officials can advise him as to whether use of his powers would be appropriate.

He sets out two changes to the arrangements for sharing of information between MHCLG and PINS with immediate effect:

1. On a quarterly basis the Planning Inspectorate will publish a report that sets out the plans that are expected to be submitted for examination in the following 6-month period. I ask that this report be published on the Planning Inspectorate website. Clearly this can only be as good as the information received from local authorities, and I am arranging for this to be drawn to the attention of local authorities to remind them of the importance of giving clear timetables;

2. The Planning Inspectorate will share all post-hearing advice letters, letters containing interim findings, and any other letters which raise soundness or significant legal compliance issues, as well as fact check reports, with my department on a for information basis, at least 48 hours in advance of them being sent to the Local Planning Authority

In relation to the second change, can I ask that we have on one website each of these documents as soon as they can be made public. There is a fundamental lack of transparency in the ad hoc way that this information is currently made available only on the relevant examination page of the particular local authority’s website, meaning that ensuring consistencies of approach, reviewing trends and learning from similar circumstances is currently very difficult indeed.

And what local plans have escaped to adoption before the relevant MP could ask the Secretary of State to apply the knife? Local Plan Intervention: a question of MP influence published by the House of Commons Library in July 2017 summarises the four times since the 2012 NPPF (to July 2017) when the Secretary of State had used his powers of intervention: Bradford, Birmingham, Maldon and North Somerset. In all but Maldon the intervention was at the request of an MP. I note that the MPs’ interventions only achieved delay to eventual adoption of the plan, whereas the call in of the Maldon plan was in circumstances where an inspector had found that the whole plan was unsound, due to its policies on traveller provision, the council’s chief executive successfully sought call in of the plan and the plan was eventually adopted.

Aside from the Secretary of State’s sabre rattling in relation to authorities that have not made sufficient progress with their plans, which I will come to in a moment, what interventions have there been since July 2017? Do we discern a continuing trend? Wouldn’t it be nice to have the information in one place so that potentially straight-forward questions such as that could be resolved. Is MPs’ interest more often in the “progress of local plans in their areas” or is it in being seen to be pressing in relation to those issues of most concern to their electorate eg retention of green belt and/or opposition to housing?

In fact, as I was typing this, in pinged a Planning magazine online update High Court allows legal challenge to Guildford local plan to proceed to full hearing (12 July 2019, behind paywall):

In May, Sir Paul Beresford, the Conservative MP for Mole Valley, wrote to several Guildford councillors expressing outrage at the “astonishing way” the plan had been adopted in the purdah period before local elections.”

Another Conservative MP on the “anti-housing in the Green Belt” campaign trail. Was this local plan perhaps “the one that got away” as far as MHCLG is concerned?

So how has the more general sabre rattling, in relation to delays in plan preparation, been going? My 18 November 2017 blog post Local Plan Interventions referred to the 31 January 2018 deadline given to 15 local authorities to set out any exceptional circumstances as to why they had failed to produce a local plan, to justify the Secretary of State not intervening in their local plan processes.

On 23 March 2018 the Secretary of State made a statement to the House of Commons, indicating that his attention had narrowed to three authorities: Castle Point, Thanet and Wirral:

In three areas, Castle Point, Thanet and Wirral, I am now particularly concerned at the consistent failure and lack of progress to get a plan in place and have not been persuaded by the exceptional circumstances set out by the council or the proposals they have put forward to get a plan in place. We will therefore step up the intervention process in these three areas. I will be sending a team of planning experts, led by the Government’s Chief Planner, into these three areas to advise me on the next steps in my intervention.

I have a number of intervention options available to me which I will now actively examine. As it may prove necessary to take over plan production, subject to decisions taken after the expert advice I have commissioned, my Department has started the procurement process to secure planning consultants and specialists to undertake that work so it can commence as quickly as possible. My Department will also be speaking to the county councils and combined authority with a view to inviting those bodies to prepare the local plan in these three areas as well as exploring the possibility with neighbouring authorities of directing the preparation of joint plans

Tough talk but it then took another ten months before intervention letters were finally sent to Wirral and Thanet on 28 January 2019.

The position in Castle Point is a mystery to me. Councillors voted down a proposed draft of the plan in December 2018. The council’s website simply says this:

A Special Council Meeting was held in November 2018, whereby the Council resolved to not proceed with the Pre-Publication Local Plan. As a result of this meeting the Council are in discussions with the Minstry of Housing, Communities and Local Government in regards to the next steps. “

But no intervention letter yet.

Sadly, if I worked for an authority I would presently be more concerned about the risk of the Secretary of State intervening in relation to a plan that has passed its examination and is about to be adopted than the risk of his intervening due to the lack of a plan in the first place or due to the authority’s withdrawal of a draft plan. We are seeing various authorities taking decisions to withdraw their submitted plans (for example East Cambridgeshire and Amber Valley) because they find the inspector’s findings, usually seeking further development allocations or additional housing numbers, unpalatable and there is still such slow progress on the part of many authorities. Surely this is the scourge – not plans which are within a process that has been refined by independent examination, the outcome of which happens to contradict the views of an MP, now encouraged to participate in hearing sessions “even if they did not make a representation”? In any world other than one in which backbench MPs have to be pacified, isn’t this madness?

The importance of being pragmatic

On the subject of pragmatism…

The second part of the Secretary of State’s 18 July letter comprises this final paragraph which I have already seen trotted out at an examination by one authority seeking to paper over the cracks:

Finally, on the substance of plan examinations, I wanted to stress to inspectors – who are doing a challenging job – the importance of being pragmatic in getting plans in place that, in line with paragraph 35 of the NPPF, represent a sound plan for the authority and consistent in how they deal with different authorities. We support and expect Inspectors to work with LPAs to achieve a sound plan, including by recommending constructive main modifications in line with national policy. In this regard, I would reiterate the views set out by the Rt Hon Greg Clark MP in his 2015 letter which I attach, on the need to work pragmatically with councils towards achieving a sound plan.”

I have since been trying to find an example of a local plan inspector in the last few years who has not been pragmatic in seeking to rescue a plan by way of main modifications rather than recommending withdrawal – and indeed the 2013/2014 spate of plans that failed examination were down to hard-edged legal failings in relation to the duty to cooperate.

Inspectors routinely allow pretty significant changes by way of main modifications, and general evidential backfilling, rather than recommend withdrawal. They routinely accept unenforceable assurances from the authority that the authority will carry out an early review – but at best “early” never means early and, at worst, as last week with the Reigate and Banstead plan, the authority’s (judge in its own cause) “review” determines that changes to the plan are not after all necessary!

So what is this paragraph getting at? If the Secretary of State were to be saying that inspectors should not be checking that legal requirements (eg the duty to cooperate and the need for adequate sustainability and habitats appraisals) have been met or that the plan meets the soundness test in NPPF, that would surely be wholly inappropriate. And shouldn’t we be protecting the independence of the Planning Inspectorate? Formal guidance is one thing, but “go easy” warning letters such as this surely just make an inspector’s task even more challenging.

Imagine equivalent guidance being given to appeal inspectors! Oh yes, bend over backwards to give the appellant time to amend elements of his scheme, overlook policy inconsistencies, fudge the approach to later phases of the development because the appellant has agreed, outside any enforceable timescale, to carry out an “early review” of those aspects. Doesn’t ring true, does it?

Simon Ricketts, 13 July 2019

Personal views, et cetera

What Really Is The Meaning Of Lambeth?

We held a dinner party for clients this week and after a certain amount of wine and gossip the conversation turned to a deeper question.

What really is the meaning of Lambeth?

The Supreme Court judgment’s judgment in London Borough of Lambeth v Secretary of State (Supreme Court, 3 July 2019) had been handed down that day.

Who hasn’t felt the same helplessness? You’re faced with a planning permission which does not say what the local planning authority plainly meant it to say. Do you go by what the document says? Or is its literal meaning changed by reference to what the authority intended?

Spoiler alert: Lambeth doesn’t provide the answer. It is specific to its facts. However it does provide another pointer as to the courts’ likely reaction to these sorts of issus. Following the approach of the Supreme Court in Trump International Golf Club Limited v Scottish Ministers (Supreme Court, 16 December 2015), Lord Carnwath indicates:

In summary, whatever the legal character of the document in question, the starting-point – and usually the end-point – is to find “the natural and ordinary meaning” of the words there used, viewed in their particular context (statutory or otherwise) and in the light of common sense.”

The facts of Lambeth are well set out in the Supreme Court’s press summary. A section 73 permission was issued which recited in the description of development the precise change that was authorised to be made to a condition on a previous 2010 permission restricting the types of goods that could be sold from a Homebase store but the local planning authority, whilst reimposing some conditions that were on the 2010 (including a condition imposing a three years’ implementation deadline) neglected to reimpose the condition restricting what types of goods could be sold and neglected to reimpose to other conditions (in relation to refuse and recycling and in relation to management of deliveries and servicing).

I summarised Lang J’s first instance ruling in my 14 October 2017 blog post Flawed Drafting: Interpreting Planning Permissions. She restricted herself to a formalistic interpretation of the permission. There was no condition restricting the types of goods to be sold. The description of development on the permission does not operate as a condition. There was therefore no operative restriction – there was nothing to prevent the shop being turned into, for instance, a food superstore. Some mistake on the part of the authority. Some windfall for the owner of the store, Aberdeen Asset Management. I speculated that the ruling might be overturned by the Court of Appeal but in fact they took the same line, in a judgment by Lewison LJ (Court of Appeal, 20 April 2018).

However, the Supreme Court has allowed the authority’s appeal. It found that the very nature of a section 73 permission is that it grants permission subject to a condition as varied. The document was “clear and unambiguous”, with the description of development setting out the “original wording” of the condition to be varied and the “proposed wording”. ““Proposed wording” in this context must be read as a description of the form of condition proposed in the application and “hereby” approved. In other words, the obvious, and indeed to my mind the only natural, interpretation of those parts of the document is that the Council was approving what was applied for: that is, the variation of one condition from the original wording to the proposed wording, in effect substituting one for the other. There is certainly nothing to indicate an intention to discharge the condition altogether, or in particular to remove the restriction on sale of other than non-food goods.

This reasoning will apply to other situations where the nature of the amendment proposed to a condition is set out precisely in the description of development. Where there is not that precision, clearly there will still be room for argument.

What about the two conditions which were not reimposed? I find this part of the court’s reasoning difficult, or at least potentially opening up further areas of uncertainty:

It will always be a matter of construction whether a later permission on the same piece of land is compatible with the continued effect of the earlier permissions…In this case, following implementation of the 2010 permission, the conditions would in principle remain binding unless and until discharged by performance or further grant. Conditions 2 and 3 were expressed to remain operative during continuation of the use so permitted. The 2014 permission did not in terms authorise non-compliance with those conditions, nor, it seems, did it contain anything inconsistent with their continued operation. Accordingly, they would remain valid and binding – not because they were incorporated by implication in the new permission, but because there was nothing in the new permission to affect their continued operation.”

So a potentially difficult exercise is required on a site with successive permissions (including section 73 permissions) – of working out which conditions from previous permissions continue to apply, even though the planning permission itself may have been superseded.

Two last points:

⁃ What of the reimposed time limit condition? People sometimes get themselves in an intellectual knot in relation to section 73 permissions granted after the physical development authorised by the previous permission has been completed. Does the section 73 permission need to be implemented in some way? Can an authority in fact grant a section 73 permission in these circumstances. Thankfully, the Supreme Court didn’t have any concerns along these lines. It agreed with the Court of Appeal that the condition was invalid, in circumstances where the development had already been carried out.

⁃ another worry sometimes – was the purported permission such a nonsense that it was of no legal effect despite no-one having challenged its validity in the six weeks’ JR time limit? Again, the Supreme Court showed no worries on that score:

If section 73 gave no power to grant a permission in the form described, the logical consequence would be that there was no valid grant at all, not that there was a valid grant free from the proposed condition. The validity of the grant might perhaps have been subject to a timely challenge by an interested third party or even the Council itself. That not having been done, there is no issue now as to the validity of the grant as such. All parties are agreed that there was a valid permission for something. That being the common position before the court, the document must be taken as it is.”

On the facts I do support the outcome. The lower courts’ approach seemed to fly in the face of common sense – of the meaning that any reader of the document (other than a planning lawyer perhaps!) would have given to it. But I do recognise the difficulties that can arise, as identified in a post by Zack Simons.

The tension between literal versus “following the formalities regardless of the words” interpretation will always be there. We have all seen so many variants of permissions that do not quite say what they are meant to say, and who can blame planning officers for sometimes not getting it quite right.

For instance, despite the provision in section 73(5) of the 1990 Act, preventing section 73 permissions from varying the time limits that were imposed on the original permission for implementation or reserved matters submissions, the restriction is overlooked from time to time and fresh time limits are set. Once free from the risk of JR, can the new time limits be relied upon? On the approach in Lambeth, my provisional view is that I don’t see why not. The natural and ordinary meaning of the permission is clear and once free from legal challenge surely there is a valid permission. Even where a permission is issued in a flawed state without legal authority, as in the Thornton Hotel case (see my 18 May 2019 blog post Slow Claim Coming: Limiting JRs https://simonicity.com/2019/05/18/slow-claim-coming-limiting-jrs/ ), the courts will apply strict criteria before the validity of a permission to be challenged after the usual deadline.

Two more planning law cases are heading to the Supreme Court. Whilst permission to appeal was refused in the air quality case, Shirley, we can look forward to the Supreme Court justices applying their minds on 22 and 23 July to the vexed area of community benefits in Resilient Energy and, on a date to be fixed, to the question of what is a listed building in Dill.

Aren’t I the life and soul of the dinner party?

Simon Ricketts, 4 July 2019

Personal views, et cetera

It’s a sign.

Another Green World: The South Coast Nitrate Crisis

Local authorities in south Hampshire have been advised by a Government body not to grant permission for most forms of residential development until further notice. Perhaps absurdly, but in desperation, authorities have even been exploring amongst themselves whether they could at least grant planning permission subject to a condition restricting the homes from being occupied, or simply risk the consequences of ignoring the advice – the position is that bad.

I’m not sure that anyone can blame the EU, or lawyers, or local authorities, or developers, but no doubt they will. Rather, the problem arises from the apparent lack of adequate measures to ensure that, by virtue of its nitrate content, sewage generated as a result of new development does not harm the integrity of coastal waters protected as special areas of conservation and special protection areas under the Habitats and Birds Directives. Nitrate enrichment causes green algae, harmful to protected habitats and birds, through a process known as eutrophication. The chickens (not those in my 1 June 2019 blog post, although the same by product) are coming home to roost following a lack of priority for too long on the need by the Government and water companies to ensure that we have adequately funded and operated waste water treatment processes (see for instance the 25 June 2019 Guardian story Southern Water faces prosecution after record £126m penalty).

The issue was raised in a House of Commons debate on 17 June 2019 by Suella Braverman, Conservative MP for Fareham, but worryingly more from the perspective of seeking to suspend affected authorities’ housing targets rather than resolving the underlying issue:

“Planning applications that could deliver hundreds of new homes in Fareham are in limbo following advice from Natural England, which has instructed that planning permission should be refused unless developments are nitrate-neutral, after two rulings from the European Court of Justice. Will the Government work with me to look at suspending house building targets while affected councils work to find a solution to avoid being unfairly treated at potential appeals?

I’m not sure how reassured she we are by the response from the relevant Under-Secretary, Jake Berry: “We will happily work with my hon. Friend as she sets out. I believe that the housing Minister is already looking into this issue, and I am sure he will be in touch with her in due course.”

In south Hampshire the problem arises from a legal opinion obtained by Natural England and shared with relevant authorities on a confidential basis. If there is a copy in public circulation then do let me know and I will add it to this post. The opinion draws upon recent case law, particularly the ruling of Court of Justice of the European Union in Coöperatie Mobilisation for the Environment UA, Vereniging Leefmilieu V College van gedeputeerde staten van Limburg and Stichting Werkgroep Behoud de Peel v College van gedeputeerde staten van Noord-Brabant (CJEU, 7 November 2018).

Thankfully it’s known as the “nitrogen deposition” or the “Dutch” case. Whilst the case concerned nitrogen deposition effects arising from agricultural activities, there are two particular (unsurprising) parts of the ruling which are relevant for our purposes:

1. The Habitats Directive does not preclude “national programmatic legislation which allows the competent authorities to authorise projects on the basis of an ‘appropriate assessment’ within the meaning of that provision, carried out in advance and in which a specific overall amount of nitrogen deposition has been deemed compatible with that legislation’s objectives of protection. That is so, however, only in so far as a thorough and in-depth examination of the scientific soundness of that assessment makes it possible to ensure that there is no reasonable scientific doubt as to the absence of adverse effects of each plan or project on the integrity of the site concerned, which it is for the national court to ascertain.”

2. An appropriate assessment under the Habitats Directive “may not take into account the existence of ‘conservation measures’ within the meaning of paragraph 1 of that article, ‘preventive measures’ within the meaning of paragraph 2 of that article, measures specifically adopted for a programme such as that at issue in the main proceedings or ‘autonomous’ measures, in so far as those measures are not part of that programme, if the expected benefits of those measures are not certain at the time of that assessment.

The most detailed account that I could find of the legal advice and underlying issues is in Portsmouth City Council report to cabinet 11 June 2019. It explains that the Integrated Water Management Strategy published last year by the Partnership for Urban South Hampshire (PUSH) authorities, Natural England and the Environment Agency recognised that there were “significant uncertainties beyond the year 2020 relating to water quality, quantity, the capacity for accommodating future growth and the impacts on European nature conservation designations.

Following the CJEU ruling, Natural England (NE), the government’s adviser for the natural environment, advises that, under the requirements of the Habitat Regulations, the existing uncertainty about the deterioration of the water environment must be appropriately addressed in order for the assessment of a proposal to be legally compliant. They recommend that this is addressed by securing suitable mitigation measures to ensure that proposals achieve ‘nitrate neutrality’. It is recognised that it would be difficult for small developments or sites on brownfield land (which form the majority of applications in Portsmouth) to be nitrate neutral.

NE has therefore advised [Havant Borough Council that ‘planning permission[s] should not be granted at this stage’ whilst the uncertainty around this issue means that a comprehensive assessment of the impacts of a proposal cannot be satisfactorily carried out and while an interim strategic solution is being developed for the sub-region’. Natural England’s advice is that proposals for new employment or leisure uses which do not entail an overnight stay are generally not subject to these concerns.

Officers sought advice from Queen’s Counsel on the matter, which confirmed the validity of Natural England’s position (as of 05.05.19). As per the legal advice received, and in the absence of any pre-existing mitigation strategy, the City Council has temporarily ceased granting planning consent for additional dwellings (or an intensification of dwellings), tourism related development and development likely to generate an overnight stay at this time. Such applications can still be considered on an individual basis if they are able to demonstrate that the development would be ‘nitrate neutral’. It is understood that other Local Authorities within the Solent catchment have also temporarily stopped granting planning consent for development affected by this matter whilst mitigation strategies are being developed.”

In a subsequent specific agenda item on the issue in its report to planning committee on 19 June 2019 members were updated:

“3.11  Immediate actions being progressed are as follows:

a)  Portsmouth and the PUSH authorities to lobby central government on the approach to the matter. There appears to be disconnect between government agencies on their advice to Local Authorities, including a clear conflict between the approach to the water quality issue and the pressure to meet the government’s housing delivery targets. We will be urging Government to examine the sources of the nitrates problem, including its own environmental permitting regimes and insufficient wastewater treatment practices by statutory undertakers, rather than solely focusing on the planning system/ development industry to present solutions.

b)  PUSH authorities have agreed to explore a strategic solution to the nitrates problem that can be used as mitigation by all authorities.

c)  Officers are identifying and exploring with Natural England and other relevant parties short term measures which could enable planning consents to resume in the short term while a more comprehensive and strategic solution is determined.

d)  Officers are arranging to meet with Southern Water to explore any existing capacity for improvements in the operation of the existing waste water treatment infrastructure and the scope, timescales and mechanisms to improve the existing treatment”

The Partnership for Urban South Hampshire (“PUSH”) comprises Hampshire County Council, Portsmouth, Southampton, Eastleigh, East Hampshire, Fareham, Gosport, Havant, New Forest, Test Valley and Winchester.

PUSH held a joint committee meeting on 4 June 2019. The minutes make interesting reading. The meeting was joined by Graham Horton from Natural England and Philip James from Southern Water. Philip James made it clear that any solution arrived at by Southern Water would need to be acceptable to its regulator, the Environment Agency. I suspect this issue is not going to be resolved quickly…

As discussion continued, Members sought views from Graham Horton whether there is a short-term solution which might mitigate risk but allow housing to be built. Members were advised that an option could be that Natural England prepares a form of words which, whilst it would not remove the risk of challenge, may give reassurance to legal advisers to support Local Planning Authorities deliver housing.

The suggestion was put to the meeting that a possibility could include Local Planning Authorities granting permission with conditions of no occupation until this matter is resolved and Graham Horton was asked whether if this approach was taken whether Natural England would challenge LPAs.

The Committee was advised that if Natural England agree and sign up to this then there would not be a challenge, but they will reserve judgment at this time until a joint position is developed and agreed which allows the issue to be resolved. This will not eliminate the risk but should give Local Planning Authorities some comfort and allow them to determine their planning consents.

At the conclusion of the discussion on this item, the Chairman summarised that it was a matter for individual Local Authorities whether they started to issue planning consents, that the best approach was to collectively work on a form of wording and it was agreed this would form joint working and the that the PUSH Planning Officers’ Group would take the lead on the preparation of this Assessment as a matter of priority. ”

It was further resolved that the Chairman should write “on behalf of PUSH to the Ministry of Housing, Communities and Local Government and the Department for Environment, Food and Rural Affairs to outline how we balance the need for housing and the need to protect the environment and to request consideration of respite from the Housing Delivery Test until this is resolved.”

I can foresee a practical veto for some time to come in relation to housing proposals in the area, bar those which are big enough so as to be able to incorporate their own measures to ensure nitrogen neutrality.

But is anyone focusing on this huge issue, an issue not just for the environment but for the breakdown in practice of the normal planning system in a number of authorities? There has been one piece in the mainstream media, a 14 June 2019 BBC report, Hampshire housing developments on hold over nitrate as well as a more detailed subsequent 19 June 2019 article in Planning magazine (which provided my way into much of this post, thank you Mark Wilding).

It’s not as if Parliament is blind to the issue. After all the House of Commons Environmental Audit Committee published a detailed and pretty direct set of recommendations in its 6 November 2018 report UK Progress on Reducing Nitrate Pollution.

But what chance of any solutions to the immediate crisis on the south coast, please?

Simon Ricketts, 29 June 2019

Personal views, et cetera

No Time To Be 21: Where Are We With Aarhus Costs Protection?

As with blog posts, it is helpful for legislation to have a snappy title.

The United Nations Economic Commission for Europe’s Convention on Access to Information, Public Participation in Decision-making and Access to Justice in Environmental Matters is therefore better known as the Aarhus Convention, after the city in Denmark where it was signed on 25 June 1998.

It currently has 47 parties. The UK ratified it in February 2005, as did the EU.

The Convention has three pillars:

⁃ access to information

⁃ public participation in decision making

⁃ access to justice

You will know that the Aarhus Convention requires that access to justice in environmental matters should be “be fair, equitable, timely and not prohibitively expensive”, a challenging requirement in jurisdictions such as ours where access to justice in environmental matters frequently relies upon access to the High Court and appellate courts thereafter, and where processes are almost by definition prohibitively expensive – not just your own lawyers’ costs (cough) but, if the dice roll the wrong way, your liability for those of the defendant authority.

I last properly blogged on Parliament’s, and the English courts system’s, response to that challenge in my blog post dated 11 March 2017, Aarhus: Caps In The Air Again.

I agreed to speak on this subject at the Kingsland Conference event at King’s College London arranged for this Tuesday to mark the 21st anniversary of the signing of the Convention. If this post whets your appetite to hear that day from much more knowledgeable people than me on every aspect of the Convention’s three pillars, then do sign up.

In itself, the Convention has no direct effect in domestic law and its enforcement is indirect, at member state level via meetings of the parties to the Convention and non-binding communications by the Aarhus Convention Compliance Committee. I say “in itself” because it does have direct effect in domestic law via specific EU directives in relation to environmental protection, which was the basis for the European Court of Justice’s preliminary ruling in Edwards (CJEU, 11 April 2013).

At the time of my March 2017 blog post the Civil Procedure (Amendment) Rules 2017 had just come into force, which tightened up the regime in various ways.

The claimant’s default cap against exposure to the defendant’s legal costs in an Aarhus Convention claim) is still £5k where the claimant is an individual and otherwise £10k, with the default cap on how much the claimant can claim if successful still capped at £35k. The caps apply to each party where there are multiple claimants or multiple defendants.

An Aarhus Convention claim is basically defined as a claim brought by a member of the public, challenging the legality of a decision on grounds which concern environmental matters as defined in Articles 9 (1), (2) and (3) or the Convention, whether the claim is by judicial review, or under two specific forms of statutory review:

⁃ section 289 of the Town and Country Planning Act 1990 (challenges to decisions in relation to enforcement notice appeals)

⁃ section 65 of the Town and Country Planning (Listed Buildings and Conservation Areas) Act 1990 ((challenges to decisions in relation to listed building enforcement notice appeals)

The 2017 changes introduced the requirement that, where a claimant brings a claim and is seeking Aarhus costs protection it must say so on the claim form and must file a schedule of financial resources. The court may remove or vary the cap in these circumstances if satisfied that “to do so would not make the costs of the proceedings prohibitively expensive for the claimant“.

Proceedings are to be considered prohibitively expensive if their likely costs (including any court fees which are payable by the claimant) either—

(a) exceed the financial resources of the claimant, or

(b) are objectively unreasonable having regard to –

(i) the situation of the parties;

(ii) whether the claimant has a reasonable prospect of success;

(iii) the importance of what is at stake for the claimant;

(iv) the importance of what is at stake for the environment;

(v) the complexity of the relevant law and procedure; and

(vi) whether the claim is frivolous“.

Where the court considers the financial resources of the claimant, “it must have regard to any financial support which any person has provided or is likely to provide to the claimant”.

Three aspects of the 2017 rule amendments were challenged by the the RSPB, Friends of the Earth and ClientEarth in R (RSPB) v Secretary of State for Justice (Dove J, 15 September 2017):

1. The ability for the court to vary costs caps at any stage in the litigation would not meet the EU law requirement for “reasonable predictability

2. No express provision for hearings to be in private when a claimant or a third party supporter’s financial details may be discussed and examined.

3. Uncertainty as to whether the claimant’s own costs of bringing the litigation should be included in any assessment of their financial resources.

Dove J’s judgment is essential reading for an understanding of the background to costs capping in environmental matters, including the domestic and CJEU authorities.

He found against the claimants on the first ground but the issue was addressed in any event by Parliament in the Civil Procedure (Amendment) Rules 2018 which tightened up the procedural rules to make it clear that, save where there is a significant change in circumstances, variation of the caps can only be considered by the court if either the applicant had so requested in his claim form or if the defendant had so requested in his acknowledgement of service.

He found for the claimants on the second ground and the rules have again been changed to specify that hearings in relation to examination of claimants’ financial details must be heard in private.

He found that it was unnecessary to make a formal declaration to deal with the third ground but considered that it was clear that the court may indeed take account of a claimant’s reasonable costs in determining whether proceedings are “prohibitively expensive“.

The 2017 rule amendments defined “environmental matters” by reference to matters falling within the scope of Article 9 (1) to (3) of the Convention. I had wrongly assumed in my previous blog that the effect might be to limit the scope of the procedure but that has not been the case, following the broad meaning given by the Court of Appeal in Secretary of State v Venn (Court of Appeal, 27 November 2014).

I had also wondered whether the reference to “members of the public” in the amended rules might exclude parish councils from seeking Aarhus costs protection, but that assumption may also have been misplaced. At the permission stage of Crondall Parish Council v Secretary of State (Dove J, 14 May 2019), deputy judge John Howell QC accepted that the parish council was indeed a “member of the public”.

The 2017 rule amendments do not extend the automatic costs capping process to the Court of Appeal and beyond. It will be for the appellate court to consider whether the costs of the appeal proceedings will be prohibitively expensive for a party which was a claimant (with no guidance as to how the costs of previous stages in the litigation are to be taken into account).

The UK is still under some international pressure as to its approach to compliance. In its September 2017 decision VI/8k, the Economic Commission for Europe noted that “while the 2017 amendments to the cost protection system in England and Wales introduced some positive improvements, the 2017 amendments overall appear to have moved [the UK] further away from meeting the requirements of its 2014 decision V/9n, namely that the UK should:

“(a) Further review its system for allocating costs in all court procedures subject to article 9, and undertake practical and legislative measures to ensure that the allocation of costs in all such cases is fair and equitable and not prohibitively expensive;

(b) Further consider the establishment of appropriate assistance mechanisms to remove or reduce financial barriers to access to justice;

(d) Put in place the necessary legislative, regulatory and other measures to establish a clear, transparent and consistent framework to implement article 9, paragraph 4, of the Convention”.

Furthermore, “by failing to ensure that private nuisance proceedings within the scope of article 9, paragraph 3, of the Convention, and for which there is no fully adequate alternative procedure, are not prohibitively expensive, the Party concerned fails to comply with article 9, paragraph 4, of the Convention“.

There is also a complaint which is being investigated by the Aarhus Convention Compliance Committee. It is based on (1) the exclusion from current system of automatic costs capping for section 288 challenges of planning appeal decisions and (2) the risk of public disclosure of claimants’ financial means.

The complainant sets out the position as follows:

In 2008 a property developer sought to obtain planning permission to build an estate of 18 houses in open countryside outside of Ashover, Derbyshire. Permission to carry out this development was refused. The developer then reapplied for planning permission to develop 26 houses in 2014 and again in 2015. These applications were both refused. An appeal was made against the most recent decision and an Inspector was appointed by the Secretary of State for Communities and Local Government to hear the evidence and make a recommendation to the Secretary of State. After hearing all evidence over a four-day period and visiting the site the Inspector recommended that the appeal be dismissed and planning permission be refused. The Secretary of State disagreed with his Inspector’s recommendation, allowed the appeal, and granted planning permission.

Challenging the Decision

Objectors to the development sought a legal opinion on challenging the Secretary of State’s decision. It was the opinion of counsel that challenging the Secretary of State’s decision would be extremely costly and could fail. The costs protection regime for “Aarhus claims” would not be available for challenges to decisions of the Secretary of State even though the only difference rendering it inapplicable was the identity of the decision-maker. As a result of the uncertainty as to costs no member of the public had the appetite to challenge the decision.

We have been made aware that amendments were made to Part 45 Section VII of England and Wales’ Civil Procedure Rules (“CPR”) (“The 2017 Amendments”) on 28th February 2017. These mean that any claimant or a third party supporter of a claim now risks public disclosure of their financial means.”

DEFRA’s response dated 8 March 2019 is interesting:

1. Section 288 challenges will be brought within the scope of the rules later this year.

2. The new Civil Procedure (Amendment) Rules 2019 change the criteria as to when a hearing will be held in private but one of the criteria is whether “it involves confidential information (including information relating to personal financial matters) and publicity would damage that confidentiality“.

There do remain various open questions, for instance:

1. Post-Brexit, how will we see the Government flesh out the principle outlined in the draft Environment (Principles and Governance) Bill of “access to justice in relation to environmental matters“?

2. Does the current process give claimants “reasonable predictability“?

2. What are the practical risks for a defendant, in terms of potentially thereby elongating proceedings, in seeking to vary or remove a costs cap?

3. What effects are the changes having in practice on potential claimants as well as third party funders?

4. Where there is no Aarhus costs protection, are we going to see more applications for security for costs by defendants: the £250,000 required of Heathrow Hub Limited for example in the recent Heathrow proceedings (to be heard in the Court of Appeal in November) or the £60,000 required of the claimant in We Love Hackney v London Borough of Hackney (Farbey J, 17 April 2019).

Happy birthday, Aarhus Convention. Let them eat cake?

Simon Ricketts, 22 June 2019

Personal views, et cetera

National Lottery: 2 Problematic Recovered Appeal Decisions

The exercise of the Secretary of State’s power to call in applications and recover appeals for his own determination is inherently politically charged.

This blog post focuses on two recent recovered appeals. The other reverse lottery, of call in, is for another day.

The Secretary of State’s policy as to recovering appeals is handily summarised in section 6 of the House of Commons briefing paper Calling-in applications (England).

Wavendon, Woburn Sands

If anyone thinks that the Secretary of State’s intervention in this case did anything other than, at the request of a fellow MP, frustrate or delay the delivery of homes in accordance with national policy, and in so doing place unjustified financial pressure on an SME housebuilder, then do let me know.

This relates to a relatively small proposal for the development of 203 homes at Woburn Sands, Buckinghamshire. The application was made to Milton Keynes Council in July 2016 and refused in December 2016, against officers’ recommendations.

The developer, Storey Homes, appeals. An inquiry takes place over six days in July 2017, with an extremely experienced inspector, David Cullingford.

The proposal is locally controversial, with various objectors appearing at the inquiry, including three councillors. I can only assume that objectors are spooked by the way the inquiry goes because in August 2017 the councillors then ask the then planning minister to recover the appeal for the Secretary of State’s own determination. The request is refused. But they don’t stop there.

As reported at the time in MK Citizen (2 November 2017) local Conservative MP Iain Stewart then writes a billet doux to the then Secretary of State:

The letter […] starts with ‘Dear Sajid’, and thanks him for his “kind” email on Mr Stewart’s election to the government’s transport committee.

It states: “I implore you to intervene in any way you can to at least delay the announcement of the Inspector’s decision.”

It ends: “Yours ever, Iain

Anyway the charm works, and the appeal is recovered on 31 October 2017.

There is then an elongated period of post-inquiry correspondence. The most significant issue was whether Milton Keynes Council could show five years’ housing supply or whether the NPPF tilted balance applied. All the evidence points to the position being as shown by the appellant at the inquiry – less than five years’ supply.

It turns out that the objectors were right to be worried by the way the inquiry had gone. When the Secretary of State published his decision letter on 5 December 2018, they could see that the inspector in his 2 February 2018 report had indeed recommended that the appeal be allowed, finding that there was less than five years’ housing supply and that taking all considerations into account he considered “that the planning balance in this case is firmly in favour of the scheme. The benefits of this sustainable housing proposal would significantly and demonstrably outweigh the adverse impacts elicited.”

But hey never mind, babychams all round, Mr Stewart’s intervention had done the job for the objectors because the Secretary of State’s decision was to reject the inspector’s recommendation and dismiss the appeal. On the basis of some not fully explained calculations, the Secretary of State determined that there was indeed five years’ supply: “Taking all these factors into consideration, he considers that on the basis of the evidence put forward at this inquiry, estimated deliverable supply is roughly in the region of 10,000– 10,500. The Secretary of State therefore considers that the housing land supply is approximately 5.9–6.2 years. He notes that on this basis, even if the emerging plan figure of 1,766 were used (1,854 with a 5% buffer added), as the agent proposes, there would still be an estimated deliverable housing land supply of over 5 years.”

This conclusion of course meant that the tilted balance in what is now para 11(d) of the 2019 NPPF did not apply, “the policies which are most important” for determining the appeal were not automatically to be treated as out of date and he could therefore find that the proposal “conflicts with development plan policies relating to development outside settlement boundaries and density. He further considers that it is in conflict with the development plan as a whole.

The Secretary of State considers that the housing benefits of the scheme carry significant weight and the economic benefits carry moderate weight in favour of the proposal.

The Secretary of State considers that the low density of the appeal proposal carries significant weight against the proposal, while the location in unallocated open countryside outside the development boundary of Woburn Sands carries moderate weight, and the impact on the character of the area carries limited weight. He further considers that the minimal harm to the listed building carries little weight and that the public benefits of the scheme outbalance this ‘less than substantial’ harm. The heritage test under paragraph 196 of the Framework is therefore favourable to the proposal.

The Secretary of State considers that there are no material considerations which indicate the proposal should be determined other than in accordance with the development plan. He therefore concludes that the appeal should be dismissed, and planning permission should be refused.”

Many would have given up this apparent lottery at that point, but all credit to Storey and to their legal team, Peter Goatley and James Corbet Burcher (No 5 chambers) together with Stephen Webb (Clyde and Co). The decision was duly challenged in the High Court and has now been quashed by Dove J in Wavendon Properties Limited v Secretary of State (Dove J, 14 June 2019)

The judge found the Secretary of State’s reasoning to be inadequate in relation to the critical question as to whether there was five years’ supply of housing land:

“All of these factors lead me to the conclusion that the reasons provided by the First Defendant in relation to the figure were not adequate in the particular and perhaps unusual circumstances of this case. By simply asserting the figures as his conclusion, the First Defendant has failed to provide any explanation as to what he has done with the materials before him in order to arrive at that conclusion, bearing in mind that it would have been self-evident that it was a contentious conclusion. Simply asserting the figures does not enable any understanding of what the First Defendant made of the Inspector’s conclusions which he accepted in paragraph 17 of the decision letter, and how they were taken into account in arriving at the final figures in his range.

“I accept the Claimant’s submission that the need for the range to be in some way explained is not requiring reasons for reasons, it is simply requiring reasons for a conclusion which was pivotal in relation to the application of the tilted balance in this case, and which derived from figures which had not been canvassed as an answer to the question of what the Second Defendant’s housing land supply was anywhere in any of the material before the First Defendant prior to the decision letter.”

In passing, there are two other interesting aspects to the judgment:

1. An analysis of what is meant in paragraph 11(d) of the NPPF, when, separate from questions of five years’ supply, you are considering whether “the policies which are most important for determining the application are out-of-date“. Unsurprisingly, Dove J concluded that this is “neither a rule nor a tick box instruction. The language does not warrant the conclusion that it requires every one of the most important policies to be up-of-date before the tilted balance is not to be engaged. In my view the plain words of the policy clearly require that having established which are the policies most important for determining the application, and having examined each of them in relation to the question of whether or not they are out of date applying the current Framework and the approach set out in the Bloor case, an overall judgment must be formed as to whether or not taken as a whole these policies are to regarded as out-of-date for the purpose of the decision.

2. The judge’s agreement with the Secretary of State that a section 106 planning obligation by the housebuilder to use its reasonable endeavours to build out the development within five years of the council approving the last reserved matters application was not a material consideration to be taken into account. One to return to, once perhaps we see the Government’s promised green paper on measures to improve delivery and other matters.

Of course the housebuilder is not yet out of the woods. Back the appeal will go to the Secretary of State of the day for redetermination as against whatever the housing supply position, and national policy position, happens to be at that time, whenever it will be. The problem doesn’t just lie in the arbitrary nature of the recovery process (it is particularly wrong that appeals can be recovered even after the inquiry has concluded) but with the glacial pace of appeals (until the anticipated brave new world of Rosewell) which means that no-one ever knows what the policy or housing supply/delivery position is going to be when any decision is finally taken, let alone which minister will be sitting at the relevant desk.

I note that an application by the housebuilder for specific disclosure against the Secretary of State did not need to be determined by the judge in the light of his ruling. No doubt this was for civil servants’ internal recommendations to ministers before those decisions were taken in relation to the appeal, including potentially its recovery in the first place. Now wouldn’t that make interesting reading?

Sainsbury’s, Cambridge Heath Road

Last week we saw another decision by the Secretary of State to dismiss an appeal against the recommendations of his inspector. This was the decision letter dated 10 June 2019 in relation to an appeal by Sainsbury’s following the non-determination by the London Borough of Tower Hamlets of its application for planning permission for “a replacement Sainsbury’s store, an ‘explore learning’ facility, flexible retail/office/community floorspace, 471 residential units arranged in 8 blocks, an energy centre and plant at basement level, 240 ‘retail’ car parking spaces and 40 disabled car parking spaces for use by the proposed residential units, two additional disabled units proposed at Merceron Street, creation of an east-west public realm route from Cambridge Heath Road to Brady Street and public realm provision and enhancements, associated highway works to Brady Street, Merceron Street, Darling Row and Collingwood Street and Cambridge Heath Road“.

Again, an experienced inspector, David Nicholson, had recommended approval in a nuanced report, following a lengthy inquiry. There was one issue where clearly he was not convinced by the proposals, namely the location of the affordable housing within the scheme:

In describing the main entrance to the AH as poor doors, it drew attention not only to the simple design but also to the position of these at the north end of the scheme. Unlike the private units, this would put them at the greatest walking distances from public transport, shops and services. The podium barrier would not only divide the types of tenure, but also separate the amenity and play space areas as well as extend the walking distances (although access to these could be addressed through condition 43). Although more than one witness was questioned on this, no persuasive explanation was given as to why the units were separated in this way.”

The inspector pragmatically recommended that if the Secretary of State were to share these concerns “then he should seek an alternative arrangement through a further s106 Agreement“.

To a very small extent this concern was addressed by the revised s106 Agreement which would include a few shared ownership units on the other side of the proposed barrier. Nevertheless, the location of vast majority of the AH, including all the rented housing, would be both at the far end of the site and altogether rather than integrated, and this counts heavily against the benefits of the AH“.

The Secretary of State in his decision letter appears to agree with almost all of the inspector’s conclusions but the “poor doors” concern appears to be the tipping point:

The Secretary of State has further considered the fact that the social rented housing is positioned at the north end of the scheme, at the greatest walking distance from public transport, shops and services, and that the podium barrier would not only divide the types of tenure, but also separate the amenity and play space areas. He notes the Inspector’s comment that no persuasive explanation was given as to why the units were separated in this way (IR11.33). He agrees with the Inspector that to a very small extent this would be addressed by the inclusion of a few shared ownership units on the other side of the proposed barrier, and has taken into account that condition 43 requires the measures for providing access to be approved. Nonetheless the location of the vast majority of the affordable housing, including all the rented housing, would be both at the far end of the site, and all together rather than integrated (IR11.34).

In assessing the implications of this, the Secretary of State has taken into account that the Framework aims not just to deliver raw housing numbers, but to achieve healthy, inclusive and safe places (paragraph 91). He considers that the separation of the affordable housing, amenity and place space areas is not in keeping with the aims of paragraph 91(a) to achieve inclusive places that promote social interaction, including opportunities for meetings between people who would not otherwise come into contact with each other. The Secretary of State considers that this carries substantial weight against the proposal.

The Secretary of State has considered the Inspector’s comment at IR11.33 that if the Secretary of State shares his concerns, then he should seek an alternative arrangement through a further s.106 agreement. However, the Secretary of State notes that previous concerns about this matter which were addressed by a revised s.106 agreement only resulted in the inclusion of a few shared ownership units on the other side of the proposed barrier (IR11.34). He therefore considers that a seeking more fundamental changes via further revisions to the s.106 agreement is unlikely to be successful. He has also taken into account that other matters also weigh against a grant of permission. Overall he does not consider that a ‘minded to allow’ letter would be an appropriate approach in this case.”

He dismisses the appeal.

Whatever the rights and wrongs of the proposal itself, was it right not to give the appellant a short opportunity to complete a further section 106 agreement so as to address this concern? On the one hand it could have led to an appropriate form of development that would deliver much needed housing. Or it could all have proved too much for the appellant to swallow, or too complicated without scheme changes, in which case at least the opportunity would have been given.

Presumably the scheme will now be reworked, at significant expense and delaying any start on site.

I thought we were in a housing crisis – more, better, faster? And yes of course the developer could have got the scheme “better” to begin with but no doubt with a hit to viability and therefore potentially the amount of affordable housing to be provided – that’s the balance.

But is there really no room for procedural solutions such as this? Or, in the case, of Woburn Sands, de-recovery?

Simon Ricketts, 15 June 2019

Personal views, et cetera

The Bottom Line: Updates On CIL And Viability

“Out of the blue and into the black

You pay for this, but they give you that

And once you’re gone, you can’t come back

When you’re out of the blue and into the black.”

(Neil Young)

Two double act dates for the diary:

12 July (Bob Dylan and Neil Young, Hyde Park)

1 September (CIL amendment regulations due to come into force, RICS professional statement on financial viability in planning takes effect).

I was going to force myself to write a dull, worthy and academic blog post on one of these, but I know what you want so 1 September it is.

CIL

The Community Infrastructure Levy (Amendment) (England) (No. 2) Regulations 2019 were finally laid before Parliament on 4 June 2019. They will be debated in the House of Commons and, assuming they receive an affirmative resolution, will come into force on 1 September 2019.

There was an accompanying press release, Communities to benefit from new housing infrastructure rules, and, more informatively, a more detailed document, Government response to reforming developer contributions.

Further regulations will follow:

The Government intends to lay the secondary legislation which will enable the delivery of starter homes later this year. Therefore, the Government also intends to introduce the regulations for the exemption of starter homes from the Levy later in the year.”

There has been some attempt at consolidation (although a single set of consolidating regulations really is overdue for those, particularly non-lawyers, without access to expensive online legal information subscription services):

The Government recognises that unconsolidated regulations can be challenging to understand, and that this challenge can be particularly acute when calculating Levy liabilities. To increase usability the Government has consolidated all regulations relating to the calculation of Levy liabilities into a single schedule. The Government will consider fully consolidating the regulations when any further regulatory amendments are made.

There will be some simplification in terms of access to information on indexation:

The Regulations have instead been amended to improve the transparency around indexation, while retaining the existing approach by indexing the Levy to the Building Cost Information Service’s (BCIS) All-in Tender Prices Index. The Government has asked the Royal Institution of Chartered Surveyors to produce a bespoke index for the Levy, based on BCIS. This will be produced annually and be made publicly available. The index will not change through the year, as BCIS forecasts can at present. The Government will review guidance to improve clarity, including making clear that from 1 January each year, the latest index figure produced by the Institution should apply. The Government also proposes to retain the proposal for charging authorities to produce annual rate summaries, which will further improve transparency, in particular for smaller developers. The changes to regulations will address several issues raised during consultation regarding how the existing approach to indexation is implemented.”

There are also some other detailed fixes of previous glitches, but largely the Regulations are as foreshadowed in its Reforming developer contributions Technical consultation on draft regulations (December 2018) and before that in its document Government response to supporting housing delivery through developer contributions: A summary of consultation responses and the Government’s view on the way forward (October 2018) which was the subject of my 9 November 2018 blog post An Update On CIL: Reform Promised, Meanwhile Continuing & Increasingly Expensive Uncertainties.

It really is the Never Ending Tour.

Viability

The RICS published its professional statement on Financial viability in planning: conduct and reporting on 28 May 2019, which comprises fourteen mandatory requirements which chartered surveyors must observe when carrying out financial viability assessments in a planning context. It is all strong stuff, not just vague exhortations of good practice. Breaches will be a disciplinary matter for the RICS member and his or her firm: “Sections within professional statements that use the word ‘must’ set mandatory professional, behavioural, competence and/or technical requirements, from which members must not depart.

The RICS covering statement says this:

Dissatisfaction has been expressed among some stakeholders in the sector about the standards to which viability assessments are being produced. The concerns extend from public representatives, the development sector, community groups and decision makers all of whom rely on viability assessments in a key public interest area. Questions about objectivity, conflicts of interest, transparency and contingency fees among others have been raised about those working for both the private and public sectors. While not all viability assessments are undertaken by chartered surveyors, in response RICS has strengthened our advice on these areas, the professional conduct of chartered surveyors and regulated firms undertaking viability assessments and the essential information which should be reported so that informed decisions may be taken transparently.

We have also produced this professional statement in recognition of the Mr Justice Holgate’s comments in the Parkhurst Road case requesting professionals to contribute to a more efficient public administration of planning. His further comments on the technical aspects of viability will be addressed in the review of our guidance note which will go to consultation over summer 2019.”

I covered those comments from Holgate J in my 27 April 2018 blog post Pointers From Parkhurst.

These are the key requirements:

“The RICS member carrying out the FVA must be a suitably qualified practitioner.”

“The report must include a statement that, when carrying out FVAs and reviews, RICS members have acted:

• with objectivity

• impartially

• without interference and

• with reference to all appropriate available sources of information.
This applies both to those acting on behalf of applicants as well as those acting on behalf of the decision-makers.”

Terms of engagement must be set out clearly and should be included in all reports. The RICS professional statement Conflicts of interest (1st edition, 2017) applies, but with the additional requirement that RICS members acting on behalf of all those involved must confirm that no conflict or risk of conflict of interest exists (see Conflicts of interest paragraph 1.1). The professional statement allows ‘informed consent’ management, which, subject to the circumstances, can be both pragmatic and appropriate. This should take the form of a declaration statement.”

A statement must be provided confirming that, in preparing a report, no performance- related or contingent fees have been agreed.”

Transparency and fairness are key to the effective operation of the planning process. The PPG (paragraph 021, reference ID 10-021-20190509) states that:

‘Any viability assessment should be prepared on the basis that it will be made publicly available other than in exceptional circumstances.’

Although certain information may need to remain confidential, FVAs should in general be based around market- rather than client-specific information.

Where information may compromise delivery of the proposed application scheme
or infringe other statutory and regulatory requirements, these exceptions must be discussed and agreed with the LPA and documented early in the process. Commercially sensitive information can be presented in aggregate form following these discussions. Any sensitive personal information should not be made public.”

“Before accepting instructions, if RICS members are advising either the applicant or the LPA on a planning application and have previously provided advice, or where they are providing ongoing advice in area-wide FVAs to help formulate policy, this must be declared.”

“All inputs into an appraisal must be reasonably justified. Where a reviewer disagrees with a submitted report and/or with elements in it, differences must be clearly set out with supporting and reasonable justi cation. Where inputs are agreed, this must also be clearly stated. Where possible, practitioners should always try to resolve differences of opinion.”

“In the interest of transparency, when providing benchmark land value in accordance with the PPG for an FVA, RICS members must report the:

current use value – CUV, referred to as EUV or first component in the PPG (see paragraph 015 reference ID: 10-015-20190509). This equivalent use of terms – i.e. that CUV and EUV are often interchangeable – is dealt with in paragraph 150.1 of IVS 104 Bases of Value (2017)

premium – second component as set out in the PPG (see paragraph 016 reference ID: 10-016-20190509)

market evidence as adjusted in accordance with the PPG (see PPG paragraph 016 reference ID: 10-016-20190509)

all supporting considerations, assumptions and justi cations adopted including valuation reports, where available (see PPG paragraphs 014 reference ID: 10-014-20190509; 015 reference ID: 10-015-20190509; and 016 reference ID: 10- 016-20190509)

alternative use value as appropriate (market value on the special assumption of a specified alternative use; see PPG paragraph 017 reference ID: 10-017-20190509). It will not be appropriate to report an alternative use value where it does not exist.
A statement must be included in the FVA or review of the applicant’s FVA or area-wide FVA that explains how market evidence and other supporting information has been analysed and, as appropriate, adjusted to reflect existing or emerging planning policy and other relevant considerations.

“During the viability process there must be a clear distinction between preparing and reviewing a viability report and subsequent negotiations.”

“All FVAs and subsequent reviews must provide a sensitivity analysis of the results and an accompanying explanation and interpretation of respective calculations on viability, having regard to risks and an appropriate return(s).”

“At all stages of the viability process, RICS members must advocate reasonable, transparent and appropriate engagement between the parties, having regard to the circumstances of each case. This must be agreed and documented between the parties.”

“For applicants, subsequent reviews and plan-making, FVAs must be accompanied by non-technical summaries of the report so that non-specialists can better understand them. The summary must include key gures and issues that support the conclusions drawn from the assessment and also be consistent with the PPG”

“Reports on behalf of both applicants and the authority must be formally signed off and dated by the individuals who have carried out the exercises. Their respective qualifications should also be included.”

“All contributions to reports relating to assessments of viability, on behalf of both the applicants and authorities, must comply with these mandatory requirements. Determining the competency of subcontractors is the responsibility of the RICS member or RICS-regulated firm.”

“RICS members must ensure that they have allowed adequate time to produce (and review) FVAs proportionate to the scale of the project, area-wide assessment and specific instruction. They must set out clear timeframes for completing work. If the timeframes need to be extended, the reasons must be clearly stated, both at the time and in the subsequent report.”

Well done technical author, Gerald Eve’s Robert Fourt, and his working group:

Jeremy Edge FRICS (Edge Planning)

Nigel Jones FRICS (Chesters Commercial)

Jacob Kut MRICS (Avison Young)

Simon Radford FRICS, Chair (Lothbury Investment Management)

Charles Solomon MRICS (GLA)
Peter Wyatt MRICS (Reading University)

(Albeit a very male group).

It may be that the stable door has already bolted but I do hope that the professional red lines in the statement give some reassurance that viability figures are not cooked up behind closed doors without appropriate professional discipline being applied, and strengthen surveyors’ position in discussions with their clients, whether from the private or public sectors.

The professional statement is separate from RICS guidance as to how to carry out financial viability appraisals in accordance with government policy, which is now very out of date. The professional statement says this:

“Since the publication of the NPPF 2018 and PPG 2018 (as updated in 2019) RICS has also been reviewing its 2012 guidance note to align it with the changed emphasis in current government policy; a second edition is forthcoming.”

The Government’s PPG guidance on viability was tweaked again on 9 May 2019. Having been through it and flagged changes from the previous 24 July 2018 version, I can’t really improve upon this summary, from the day it was published, by Matthew Spilsbury (Turley).

Hey hey, my my.

Simon Ricketts, 8 June 2019

Personal views, et cetera

Chickens**t EIA

An interesting example last week of the legal pitfalls should planning permission be granted on the basis of inadequate environmental impact assessment.

Interesting partly because although the messages read straight across to all EIA development, including the glitziest of urban development projects, the specific question arose in a very different context:

Did a local planning authority, when granting planning permission for an intensive poultry-rearing facility, fail to consider the likely effects of odour and dust arising from the disposal of manure?

The basis for the error was a misplaced assumption that certain effects would be controlled by other regulatory processes. That is an issue which potentially arises in various development contexts.

The case is R (Squire) v Shropshire Council (Court of Appeal, 24 May 2019), with Lindblom LJ giving the lead judgment.

For a summary of the case, apologies but I will plug again Town’s “free to subscribe” weekly updating service that covers all Planning Court cases and appeals from the Planning Court. The case is summarised by my colleague Paul Arnett in the latest update.

There is much in the judgment about the proper interpretation of environmental permits under the IPPC regime and the extent to which a local planning authority should impose conditions to control matters which may in theory be controlled by other legislation where the regulator under that legislation (in this case the Environment Agency) has indicated that in practice it would not enforce, but what was particularly interesting to me was Lindblom LJ’s conclusion that at first instance Deputy Judge Rhodri Price Lewis QC “was wrong to conclude that the EIA undertaken for the proposed development – in particular the assessment of the likely effects of odour and dust arising from the storage and spreading of manure – was adequate and lawful.

The “project description” part of the environmental statement explained what was proposed:

In chapter 3, “Description of development”, in the “Project Description”, it explained that “[at] the end of each flock cycle, the buildings are cleaned out and the manure removed … and loaded directly in waiting vehicles, which are sheeted and the manure removed from the site for disposal as a sustainable fertiliser on agricultural land.”

The claimant, Ms Squire, was concerned that the 2,322 tonnes of manure to be produced annually would be disposed of by spreading it on farmland close to residential areas, including farmland not not owned by the prospective operator of the facility, Mr Bower. So how were the potential effects in terms of odour and dust, from these proposals, assessed in the environmental statement?

In its assessment of likely significant effects in the environment, the environmental statement relied significantly on an environmental permit that had been issued by the Environment Agency to Mr Bower to cover the activities proposed on his land.

In chapter 9, “Environmental Management”, under the heading “Assessment”, it acknowledged (in paragraph 9.2) the requirement for “an IPPC permit … administered by the Environment Agency”. It said that “[the] permit must take into account the whole environmental performance of the plant, covering e.g. emissions to air, water and land, generation of waste …”, and also this:

9.2 … As the proposed poultry unit will be controlled under the IPPC permitting regime, the likelihood of significant impact on the environment from the proposed development is negligible due to the strict regime of control.”

On “Odour Management”, it said that “[the] development [has] been assessed as part of the IPPC permit application and deemed acceptable subject to odour control conditions”, and that “[the] site is subject to the IPPC permit conditions which requires emissions from the activities shall be free from odour at levels likely to cause pollution outside the site” (paragraph 9.4). On “Dust”, it said that “[the] results of the DEFRA research project demonstrated that emissions from poultry units in terms of particulate matter reduced to background levels by 100m downwind of … even the highest emitting poultry houses” (paragraph 9.7). On “Manure Disposal”, it said (in paragraph 9.11):

“9.11 The proposed poultry units will operate on a floor litter basis and will generate poultry manure. The manure will be disposed of through use as a sustainable agricultural fertiliser. The [applicant’s] manure management plan is attached to this statement as Appendix 4.”

The “Summary” in paragraph 9.16 said this:

9.16 The operation of the site is subject to the rigorous controls of the Environment Agency’s IPPC permitting regime. The site is required to operate to Best Available Techniques and the conditions of the permit require the site to be free from pollution.”

However, the Environment Agency’s response to consultation had made it clear that “[f]or the avoidance of doubt we we would not control any issues arising from activities outside of the permit installation boundary“.

Lindblom LJ noted the following in relation to the environmental statement:

⁃ it did not identify the third party land on which manure was going to be spread.

⁃ there was no meaningful assessment of the effects of odour and dust from the spreading of manure, either on Mr Bower’s land or on any other farmer’s. “It did not seek to anticipate the content of any future manure management plan, including the fields to which it would relate, or the arrangements that would be undertaken for the storage and spreading of manure. It did not attempt to predict and assess the polluting effects of those activities either on land owned by Mr Bower, or on other land to which the manure management plan would not relate. The Manure Management Report did not venture to assess the effects of the arrangements to which it referred. In short, there was no relevant assessment.”

⁃ “it cannot simply be inferred from the relevant parts of the environmental statement that its authors had concluded that the proposed storage and spreading of manure on farmland was not a potential source of pollution, including odour and dust, with significant effects on the environment, which ought to be addressed in determining the application for planning permission. Those who prepared the environmental statement – and Cymru ADAS Wales, who prepared the Manure Management Report in Appendix 4 – were of course entitled to assume that the Environment Agency would perform its regulatory functions as it should, and as far as they went (see my judgment in Preston New Road Action Group v Secretary of State for Communities and Local Government [2018] Env. L.R. 18, at paragraphs 89 to 93; the judgment of Glidewell L.J. in Gateshead Metropolitan Borough Council v Secretary of State for the Environment [1995] Env. L.R. 37, at p.49; and the judgment of Gilbart J. in Frack Free Balcombe Residents’ Association v West Sussex County Council [2014] EWHC 4108 (Admin), at paragraph 100). The control that would be exerted by the Environment Agency through the environmental permit was clearly a factor they had in mind. However, they did not attempt to relate that control to the spreading of manure on land to which the permit and its conditions would not apply. Nor did they consider whether a gap would exist between the control under the permit and such control as could be exercised through restrictions and requirements imposed in the planning process. The Manure Management Report touched upon measures by which harmful effects on the environment might be reduced. But it did not consider what measures were likely to be applied on third party land, in what form such measures might be imposed as requirements attached to the planning permission – whether by conditions or by a planning obligation under section 106 of the Town and Country Planning Act 1990 – or how effective they were likely to be in reducing the effects of odour and dust.”

⁃ “the future manure management plan to which the planning officer referred in paragraph 6.7.5 of his report was not a substitute for the assessment lacking in the environmental statement. Not only was it yet to come into existence, but even when it did it was only going to relate to the storage and spreading of manure on Mr Bower’s own land, and not to the substantial quantities that were going to have to be disposed of elsewhere.”

The judge concluded:

In my view, therefore, the environmental statement was deficient in its lack of a proper assessment of the environmental impacts of the storage and spreading of manure as an indirect effect of the proposed development. In this respect it was not compliant with the requirements of the EIA Directive and the EIA regulations.”

The judge then considered whether any advice in the report to committee satisfactorily addressed the inadequacies in the environmental statement. There was not. Nothing “went beyond generalities“.

He therefore allowed the appeal – the planning permission had been issued unlawfully.

Before deciding to quash the permission, Lindblom LJ then considered whether under section 31 (2A) of the Senior Courts Act 1981, the permission should not be quashed on the basis that it was highly likely that the council’s decision would have been substantially different had the legal error not occurred. Mr Bower sought to argue that the position had changed because, after the proceedings had been issued, he had entered into a section 106 unilateral undertaking so as to control the effects arising by way of a manure management plan. The judge did not consider that the undertaking saved the permission from being quashed:

The planning obligation itself illustrates some of the uncertainties persisting at the time of the council’s decision. It does not, however, overcome the lack of a proper assessment of the environmental effects of odour and dust in the EIA. There is, in my view, no justification here for withholding an order to quash the planning permission, which will enable the council, when redetermining the application, to ensure that the requirements of the EIA Directive and the EIA regulations are properly complied with“.

The lesson is to make sure that any environmental statement properly assesses all direct and indirect environmental effects that are likely to arise from a development, without reaching unwarranted assumptions that effects will be limited, or that mitigation will be achieved, by way of separate regulatory processes. If the local planning authority considers that the assessment is inadequate it should require further environmental information to be provided (following the procedure set out in regulation 25 of the 2017 Environmental Impact Assessment Regulations). I am surprised that the court was even prepared to consider whether deficiencies were in practice remedied by any analysis in the committee report, and not surprised that the belated decision to enter into a section 106 unilateral undertaking did not save the day.

This is no Chicken Little message that the sky is falling, but Squire is certainly a reminder of the care that is needed, particularly in relation to environmental impact assessment, in order to avoid landing in the unpleasant stuff.

Simon Ricketts, 1 June 2019

Personal views, et cetera