Just What Is It About Today’s Planning System that Makes Appealing So … Appealing?

On 22 September 2025 the Secretary of State allowed two recovered appeals, granting planning permission for proposals which local authority members had refused against their professional officers’ opinions. In one of those cases, a full award of costs was ordered against the authority which I guess will amount to several hundred thousands of pounds. Development was unnecessarily held up in both cases for what turned out to be no good reason, in one case the decision to refuse having been in March 2024 following submission of the application in September 2022 and the other in May 2024 following submission of the application in November 2021. Both decisions were made in accordance with the relevant inspector’s recommendation.

I’m thinking back yet again to the Lichfields May 2025 research paper for the LPDF and Richborough Estates, How Long Is A Piece Of String? which found not only that applications for major development are taking twice as long to determine as 10 years ago but that it is now on average quicker to achieve permission via appeal than via the local planning authority.

I’m also thinking of the latest 50 Shades of Planning podcast episode Who’s In Control? (27 September 2025) where a number of us discuss, amongst other things, the ethical position of officers whose advice is overturned by councillors.

And I’m thinking that neither the proposed move to an increased number of applications being determined by way of delegated powers, and increased training for members, would have been likely to change the position with these two appeals. Do awards of costs influence behaviour? I would welcome your views. From the outside I’m not sure they really register either with councillors or, perhaps most importantly , with voters.

The two decisions were as follows:

Brighton Gasworks

Planning application submitted to Brighton and Hove Council in November 2021 by St William for a scheme that, following amendments,  included 495 residential units and 2,791 square metres of commercial space. It was recommended for approval in May 2024 but in the face of significant local opposition was resolved to be refused. The reasons for refusal (1) alleged the development would represent overdevelopment of the appeal site by virtue of excessive massing, density and height thereby harming the townscape of the area including its heritage assets; (2) related to the proposed housing mix (subsequently withdrawn) and (3) concerned the effect of the appeal scheme on the living conditions of future residents with particular regard to amenity and light.

St William appealed. The appeal was recovered by the Secretary of State. The inquiry sat for six days in March 2025. The Secretary of State’s decision letter accepted the inspector’s recommendations and allowed the appeal. The Secretary of State’s conclusions are worthy of note on issues such as character and appearance, density and height (paragraph 14),; the current negative effect of the “underused and despoiled” site on the “varied and robust urban townscape of east Brighton” (paragraph 15); daylight and sunlight and living conditions more generally (paragraphs24 to 28); and acceptance of the agreed position between the appellant and the council that the development would not be able to provide affordable housing given the high cost of remediating the site (paragraph 30).

In his accompanying costs decision letter, again accepting his inspector’s recommendation, he orders a full award of costs in favour of St William, on the basis that:

* the Council prevented or delayed development which should clearly be permitted, having regard to its accordance with the development plan, national policy and all other material considerations (CR48);

* the Council failed to produce evidence to substantiate each reason for refusal on appeal, made vague, generalised or inaccurate assertions about a proposal’s impact and failed to determine similar cases in a consistent manner (CR49); and

* there were substantial procedural failings on the Council’s part including an obstructive and untimely approach to the Statement of Common Ground, the submission of a Statement of Case which was bereft of meaningful detail and a failure to review.

When it comes to any councillor training programme I hope this appeal decision will be part of the study materials, including, verbatim, these conclusions from the inspector’s costs report:

Had the Council had proper regard to its own Development Plan, the NPPF, other material considerations and carried out a proper balancing exercise, the application would most likely have been approved notwithstanding the concerns raised by Members. The Council therefore prevented or delayed development which should clearly be permitted, having regard to its accordance with the development plan, national policy and all other material considerations.

The Council’s objections did not stand up to scrutiny and therefore I find that the Council failed to produce evidence to substantiate each reason for refusal on appeal, made vague, generalised or inaccurate assertions about a proposal’s impact and failed to determine similar cases in a consistent manner. It goes without saying that a decision to refuse planning permission on an allocated site against the professional advice of officers requires very careful consideration and highly robust reasoning.

There were also substantial procedural failings on the Council’s part including an obstructive and untimely approach to the SoCG, the submission of a Statement of Case which was bereft of meaningful detail and a failure to review its case promptly following a material change in national policy.

The above unreasonable behaviour resulted in unnecessary or wasted expense, as described in the PPG. I therefore conclude that a full award of costs is justified.

While I understand that the above will come as a bitter blow to the Council, it is right that I acknowledge the important work of officers during what was a long preapplication and determination period. That work culminated in the production of a Committee Report which was of the very highest order. Officers were also beyond reproach for the way they assisted the inquiry.”

Sky Studios Elstree expansion proposal

Planning application submitted in September 2022 for a film and television production studio (use Class E(g)(ii)) with ancillary floorspace, backlot, new access arrangements, car parking, landscaping, infrastructure and associated works in the green belt north of the existing Sky Studios Elstree complex. Hertsmere Borough Council members had resolved to refuse the application in March 2024 against officers’ recommendations, concluding that the “very special circumstances” test had not been made out for inappropriate development in the green belt.

Sky Studios appealed in October 2024 and the appeal was recovered by the Secretary of State. The inquiry sat for four days in March and April 2025. The Secretary of State’s decision letter accepted the inspector’s recommendations and allowed the appeal. Following the introduction of the grey belt policy designation into the NPPF in December 2024, the Secretary of State found that the site was indeed grey belt. The only real issue was whether there was unmet need for the development, on which issue his findings were as follows:

For the reasons given at IR14.20-IR14.23 and IR14.43, the Secretary of State agrees with the Inspector that Sky Studios Limited has identified a need to enlarge its current operation at SSE, that there is a reasonable and probable outcome that if the appeal is allowed, the type of development that would take place would be for an extension of the existing studio site at SSE, and that there is an unmet need for studio space related directly to the expansion of SSE (IR14.23).

In reaching this conclusion, the Secretary of State has taken into account that the description of development does not specify that the development would be used as an extension to the existing SSE site, and no condition requiring the development to be an extension has been put forward either (IR14.17). He acknowledges that it is conceivable that the proposed development could be operated as a standalone studio business separate to SSE without any restrictions imposed by the description and any planning conditions (IR14.19). However, taking into account the matters set out at IR14.20-14.23, the Secretary of State considers that the proposal is highly likely to be brought forward as an extension and that it is appropriate to proceed on this basis. He considers on that basis that unmet need has been demonstrated and carries substantial weight in favour of the proposal, and that the requirement in NPPF155(b) is met.

The Secretary of State has also considered what the need position would be on the basis of a standalone studio. He has noted the position set out at IR14.24-14.25, but like the Inspector considers that national and local economic policy seeking to grow the sector, and an increased spend in productions, do not in themselves equate to unmet need.”

“…if considered as a standalone studio, the Secretary of State considers that unmet need has not been demonstrated. On that basis, the requirement in NPPF155(b) would not be met, the proposal would therefore be inappropriate development in the Green Belt and very special circumstances would need to be demonstrated. As set out at paragraph 21 above, in that scenario the Secretary of State considers that the harm to the Green Belt in terms of inappropriateness, harm to openness and harm to purposes would have carried substantial weight. Although he has not proceeded on that basis, for the avoidance of doubt, he considers that the harm to the Green Belt and any other harm would be clearly outweighed by the benefits of the scheme such that very special circumstances would exist and development in the Green Belt would be justified.”

A textbook application of green belt principles. (Incidentally, in the unlikely event that you need a primer on grey belt I think you can still access a webinar I gave this week on that subject via Inside Housing – see here for more details).

Perhaps the outcome of the Sky Studios appeal only became obvious once we had the December 2024 NPPF but perhaps the big question for MHCLG should be, rather than further tweaks to law or policy, how to make sure that many more appeals like these two are not needed before the message gets through as to how the current legislation and policy framework is to be applied? Otherwise, whether through members’ overturns, or through non-determination appeals, schemes will be continuing to come before the Planning Inspectorate, with all the delay, expense and unnecessary risk thereby arising, that really should be determined appropriately at a local level. It’s reassuring that the appeal route is available but the relative attractiveness of that route versus waiting for a local outcome is not good in public policy terms – as I said at a breakfast discussion that we held at Town Legal this week alongside Shared Voice and Rupert Warren KC and attended by the interim chief planning inspector Rebecca Phillips (for which thanks for her participation), it’s the equivalent of people being unhappy with the service at their local GP and instead going straight to A&E…

Simon Ricketts, 27 September 2025

Personal views, et cetera

Just what is it that makes today’s homes so different, so appealing? 1956 collage by Richard Hamilton

Village Legal

What is a village? As a result of the government’s latest green belt planning practice guidance (see my 2 March 2025 blog post Colouring In The Grey Belt: The PPG) the answer to that question has practical policy consequences. When judging whether land is grey belt:

  • in assessing the extent to which the site strongly contributes to green belt purpose (a), to check the unrestricted sprawl of large built up areas, the guidance states categorically: “Villages should not be considered large built up areas”.
  • in assessing the extent to which the site strongly contributes to green belt purpose (b), to prevent neighbouring towns merging into one another, the guidance states categorically: “This purpose relates to the merging of towns, not villages.”

So if you have land on the edge of a village, the role that the land plays in separating that village from another village, or from a town, or in preventing the settlements from merging with one another, is irrelevant for the purposes of determining whether it is grey belt. Of course any potential development would have to meet other criteria, such as whether the location is “in a location that is or can be made sustainable”, but the distinction between town and village is now profound, for the purposes of applying green belt policy, both at local plan making stage and in determining planning applications and appeals.

Guess what, there is no definition of “village” in the glossary to the NPPF or indeed in national planning practice guidance. The issue is not entirely new given that one of the exceptions to development in the green belt being inappropriate has for many years been “limited infilling in villages” (now NPPF paragraph 154 (e)) but that was a relatively narrow point.

Because I live an interesting life, I participated this week in some lively WhatsApp debate on the issue (yes I’m looking at you, you and you others at this point). Someone pointed to the House of Commons Library’s research briefing City & Town Classification of Constituencies & Local Authorities (21 June 2018). Whilst interesting, this just deepened the mystery. It explains that according to an adjusted version of a taxonomy developed by the Centre for Towns, its classification (which is for wider public policy statistical purposes) was as follows:

12 Core Cities: twelve major population and economic centres (e.g. London, Glasgow, Sheffield)

24 Other Cities: other settlements with a population of more than 175,000 (e.g. Leicester, Portsmouth, Aberdeen)

119 Large Towns: settlements with a population between 60,000 and 174,999 (e.g. Warrington, Hemel Hempstead, Farnborough)

270 Medium Towns: settlements with a population between 25,000 and 59,999 (e.g. Gravesend, Jarrow, Exmouth)

674 Small Towns: settlements with a population between 7,500 and 24,999 (e.g. Falmouth, New Romney, Holbeach)

6,116 Villages and small communities: settlements with a population of less than 7,500 (e.g. Chapel-en-le-Frith, Cottenham, Menai Bridge)

But then the paper goes on to explain:

This classification isn’t intended to resolve long-standing disputes about which settlements deserve to be called ‘cities’, ‘towns’, or ‘villages’. In fact, it takes no account of the ceremonial definition of ‘city’, using the term only as a way to identify larger settlements. For instance, St Albans is identified as a ‘large town’ here because its population is 86,000 – even though it has city status. Luton, on the other hand, doesn’t have city status, but is classified here as an ‘Other City’ because its population is 225,000.

The precise division between ‘large’, ‘medium’ and ‘small’ towns is, to a large extent, subjective.”

Hmm. So that doesn’t help. By coincidence I then saw a blog post on Bluesky posted by the Urban History Group, What is a town? It starts: “What exactly is a town? The answer to this question has been debated for many decades by medieval historians.” Oh no, many decades is no good. The short piece refers to the definitional uncertainty as between small towns and large villages – resonating with the equivalent uncertainty that there is in our modern planning world. Most local plans will have a table settling out the area’s settlement hierarchy, eg

Tier 1 – city/large town

Tier 2 – town

Tier 3 – small town

Tier 4 – large village

Tier 5 – medium sized village

Tier 6 – green belt village

Tier 7 – green belt hamlet

The distinction between ”small town” and “large village” is going to come under additional scrutiny, but without any government guidance, that I am aware of, as to the criteria to be applied in drawing that distinction.

I did have a brief, far from comprehensive, look at planning appeal decisions. There was one dating from 2019 for instance (APP/B3438/W/18/3211000) which revolved around whether the proposal was “limited infilling in a village” or in fact just a hamlet. The inspector resorted to a dictionary:

The main parties dispute whether Ridgeway is a village or a hamlet.  This has consequences in terms of whether the scheme accords with Framework paragraph 145 e).  The Oxford Dictionary defines a village as a group of houses and associated buildings, larger than a hamlet and smaller than a town, situated in a rural area.  It defines a hamlet as a small settlement, generally one smaller than a village, and strictly (in Britain) one without a Church.  While a church may have once existed in Ridgeway, there is no church there now as it has been replaced by a dwelling known as Chapel House.  There are also no other associated buildings in Ridgeway that would, in my judgement, mean that Ridgeway is anything more than a hamlet.  The proposal does not accord with the exception in Framework paragraph [(now) paragraph 154(e)].

I think we are going to need some more specific guidance than dictionaries can provide. One WhatsApp response proposes an “if it has a Greggs it isn’t a village” test. I suppose that is a start but I am sure you can do better?

Whilst I’m being an annoying pedant, I would also like separately to draw attention to an inaccuracy in the NPPF glossary’s definition of “major development”:

The definition of “major development” in Article 2 of the Town and Country Planning (Development Management Procedure) (England) Order 2015 is as follows:

“major development” means development which involves one or more of the following—

(a) the winning and working of minerals or the use of land for mineral-working deposits;

(b) waste development;

(c) the provision of dwellinghouses where—

(i) the number of dwellinghouses to be provided is 10 or more; or

(ii) the development is to be carried out on a site having an area of 0.5 hectares or more and it is not known whether the development falls within sub-paragraph (c)(i);

(d) the provision of a building or buildings where the floor space to be created by the development is 1,000 square metres or more; or

(e) development carried out on a site having an area of 1 hectare or more;

The definition of “major development” in the NPPF glossary is:

For housing, development where 10 or more homes will be provided, or the site has an area of 0.5 hectares or more. For non-residential development it means additional floorspace of 1,000m2 or more, or a site of 1 hectare or more, or as otherwise provided in the Town and Country Planning (Development Management Procedure) (England) Order 2015.”

The green belt “golden rules” only apply to “major development”. What if you have a scheme of say nine units on a site of between 0.5 and 1 hectares? Under the Development Management Procedure Order that is not major development. But under the glossary, because it has imprecisely summarised the definition in the Order, it would seem to be. Error?

What a time to be a planning lawyer.

NB Back on the main theme of this blog post: shortly after we announced we were setting up our new law firm eight or so years ago, Peter Village KC called me to say that Village Legal would have been such a better name. Maybe so.

Simon Ricketts, 23 March 2025

Personal views, et cetera

Colouring In The Grey Belt: The PPG

Now that the Government’s Planning Practice Guidance has been confirmed by the Court of Appeal as having the same policy making status as the National Planning Policy Framework (see Mead Realisations Limited v Secretary of State (Court of Appeal, 30 January 2025), changes to the PPG might be seen as the MHCLG policy making equivalent of US Presidential executive orders in terms of immediacy. Last week’s PPG advice on grey belt might not have renamed the Gulf of Mexico but it does set some new firm boundary lines, effective from 27 February 2025.

In my 8 February 2025 blog post It Was The “Rushed And Incoherent” Jibe That Got Me I referred to the impact which the December 2024 NPPF has made by way of the introduction of the “grey belt” test, particularly in relation to decision making on planning applications and appeals. The flow of appeal decisions has continued and I refer to a couple of them later in this post, but since all of this (and indeed those decisions) we now have the government’s promised amendments to the PPG advice on the role of green belt in the planning system (27 February 2025) which will in my view serve to increase the number of proposals coming forward (given that its overall effect is to set the definitional boundary lines more clearly, largely to the benefit of promoters) whilst (to the extent that the advice is now more specific as to the way in which the grey belt tests should be applied) hopefully reducing the number of proposals that do actually have to go to appeal.

You will already have read Zack Simons’ 27 February 2025 blog post The “Grey Belt” has arrived but here is my brief take on some of the main points to note from the new guidance:

  • The Government expects all local planning authorities reviewing green belt boundaries to identify where land is grey belt, dividing their green belt into separate assessment areas for the purpose of identifying grey belt. The same will apply in due course for strategic authorities carrying out spatial development strategies. To state the obvious, these assessments are going to be hugely important to landowners.
  • Given that the core principle in relation to identifying green belt land as grey belt is an assessment as to the extent to which the land strongly contributes to green belt purposes (a), (b) and (d), there is helpful guidance as to the considerations to be applied in considering each of those judgements, setting out illustrative features in each case which might point to the contribution being strong, moderate or weak.“
  • In relation to Purpose A – to check the unrestricted sprawl of large built up areas – ignore villages, which are not to be considered to be “large built up areas”. An example of a strong contribution would be where, if developed, it would “result in an incongruous pattern of development (such as an extended “finger” of development into the Green Belt)”.
  • In relation to Purpose B – to prevent neighbouring towns merging into one another – a moderate (not strong) contribution would be “being able to be developed without the loss of visual separation between towns. This could be (but is not limited to) due to the presence or the close proximity of structures, natural landscape elements or topography that preserve visual separation”. A weak contribution: areas that “form part of a gap between towns, but only a very small part of this gap, without making a contribution to visual separation.”
  • In relation to Purpose D – to preserve the setting and special character of historic towns – this relates to historic towns, not historic villages. Only moderate contribution if the areas “form part of the setting and/or contribute to the special character of a historic town but include one or more features that weaken their contribution to this purpose, such as (but not limited to):
    • being separated to some extent from historic aspects of the town by existing development or topography
    • containing existing development
    • not having an important visual, physical, or experiential relationship to historic aspects of the town
  • Even if the area makes no strong contribution to purposes (a), (b) and (d), it needs to be shown that the application of the policies relating to the areas or assets in footnote 7 to the NPPF (other than green belt) would not provide a strong reason for refusing or restricting development. The PPG makes it clear that it may still be possible for authorities to provisionally identify land as grey belt in advance of more detailed specific proposals.
  • Even if the area makes no strong contribution to purposes (a), (b) and (d) and even if footnote 7 is not a bar, its release or development must not “fundamentally undermine the purposes (taken together) of the remaining Green Belt across the plan area as whole.” This apparently means that “authorities should consider whether, or the extent to which, the release or development of Green Belt Land would affect the ability of all the remaining Green Belt across the area of the plan from serving all five of the Green Belt purposes in a meaningful way.”
  • The final steps of determining whether the development would not be inappropriate development, even if it meets the above criteria, are considering:
    • whether a development is sustainably located
    • whether it would meet the ‘Golden Rules’ contributions (where applicable), and
    • whether there is a demonstrable unmet need for the type of development proposed

For the purposes of the inter-relationship between the affordable housing provision “golden rule” and the application of viability testing, we of course still await the updated viability PPG.

I’m running out of time this morning, but briefly now to turn to the decision letters I mentioned.

First of all, the Carrington decision letter dated 17 February 2025 . This followed a written representations appeal against Trafford Council’s refusal of planning permission for a 35MW battery storage facility at Wild Fowl Farm, Carrington. The inspector works through the grey belt tests methodically and concisely and finds that they are all passed.

Secondly, the Beaconsfield decision letter dated 24 February 2025 mentioned in Zack’s blog post. This followed an inquiry in relation to Buckinghamshire Council’s refusal of planning permission for up to 120 dwellings at Broad Lane, Holtspur, Beaconsfield. Again, the inspector works through the various tests, but here finds in his planning judgment that the appeal site strongly contributes to purposes (a) and (b). Accordingly this was inappropriate development so the “very special circumstances test” was to be applied and despite a housing land supply position that was agreed to be “dismal”, the appeal was dismissed (the grounds including findings as to substantial harm to the character and appearance of the area as well as substantial harm to biodiversity).

I agree with Zack that the inspector’s conclusions in relation to purposes (a) and (b) in the Beaconsfield appeal decision are potentially inconsistent with the new advice in the PPG. The PPG is definitely going to move the dial further in favour of release of sites and approval of development proposals.

Let’s take a step back. None of this is theoretical. The whole point of this “grey belt” branding is to secure more development in the green belt, sooner rather than later, on those sites which are least sensitive from the perspective of the traditional purposes for designation of green belt in the first place. I don’t find the tests, particularly in the light of the PPG, particularly challenging to navigate (although, as with so much in relation to planning, ultimately decisions will depend upon the application of human judgement, albeit within the tramlines of the policy guidelines). That is not to say that I don’t have any sympathy for opposite views: for instance this cri de coeur from my Strategic Planning Group compatriot (NB report from our group anticipated this Spring, watch this space) Andrew Wood in his 27 February 2025 blog post Grey Belt: Anti-strategic and wildly over-complicated. But, mindful of that need for development on appropriate sites, sooner rather than later, I don’t agree, and in my experience decision-making in relation to release and development of green belt sites was more of a “black box” process before the introduction of the grey belt.

Simon Ricketts, 2 March 2025

Personal views, et cetera

It Was The “Rushed And Incoherent” Jibe That Got Me

The House of Lords Built Environment Committee published its conclusions from its inquiry on grey belt on 5 February 2025, by way of a letter from Lord Moylan (its chair until 30 January 2025 since when he has been succeeded by Lord Gascoigne).

The stated purpose of the inquiry, which was commenced in September 2024, was to “to gain a better understanding of what Grey Belt land is, how it can contribute to housing targets and what sustainable Grey Belt development looks like.”

Obviously, this was in the context of the 30 July 2024 draft revised NPPF which introduced the “grey belt” concept, the idea having been specifically part of the Labour Party’s June 2024 manifesto:

Labour is committed to preserving the green belt which has served England’s towns and cities well over many decades. Under the Conservatives, greenbelt land is regularly released for development but haphazardly and often for speculative housebuilding. Without changing its purpose or general extent, Labour will take a more strategic approach to greenbelt land designation and release to build more homes in the right places. The release of lower quality ‘grey belt’ land will be prioritised and we will introduce ‘golden rules’ to ensure development benefits communities and nature.”

The party had of course been floating the proposal well before that (eg my 20 April 2024 blog post Labour’s Green Belt Grey Areas/Sadiq Khan’s London Manifesto).

The proposals in the draft July NPPF have since been refined but I had summarised them in my 2 August 2024 blog post 50 Shades of Grey Belt. The final version of the NPPF was of course published on 12 December 2024.  Links to the various relevant documents are set out in my 14 December 2024 blog post I Love It When A National Planning Policy Framework Comes Together and Zack Simons posted a brilliantly readable blog post if you don’t simply want to read section 13 of the NPPF and the definition of “grey belt” contained in its glossary.

We still await updated planning practice guidance green belt and on the identification of grey belt (expected this month) and on viability assessment (relevant to the application of the so-called green belt golden rules).

The Built Environment Committee inquiry was an important opportunity to review the “grey belt” refinement to existing green belt policy, in the context of government’s objective: (quoting from that manifesto) to “get Britain building again, creating jobs across England, with 1.5 million new homes over the … parliament” whilst not changing the “purpose or general extent” of green belt. This was a chance to recommend some improvements to its formulation and operation.

In my view that opportunity was missed, in favour of some political point scoring (Labour peers being in a minority on the Committee). Here are the Committee’s main conclusions:

The fact that the NPPF has been finalised at the same time as so many other complementary and interconnected policies are being developed raises significant concerns about the extent to which we can be confident that any of the individual policies contained within the NPPF will be successful. This is particularly the case for grey belt land, the benefits of which we now believe will be marginal, at best. Moreover, in the absence of any clear understanding of how the success of the policy will be measured or monitored, we cannot see how the policy can be implemented or developed in a robust and coherent way.

Ultimately, our assessment is that the grey belt policy has been implemented in a somewhat rushed and incoherent manner, and we do not believe that it is likely to have any significant or lasting impact on planning decision-making or on achieving your target of 1.5 million new homes by the end of this Parliament.”

Surely any proper examination of the issues should have started with a reflection on the operation of green belt policy itself prior to the introduction of the grey belt concept; its ad hoc, unplanned, growth both in extent and purposes and its incoherence in terms of the public’s conception of it as serving more than as a means of containing urban growth but as an indicator of environmental or landscape quality. That examination could have considered the subjective and politised nature of the existing tests in policy – the requirement for “exceptional circumstances” to justify release by way of local plans and “very special circumstances” to justify planning permission for so called inappropriate development.

Against that background and the Government’s various commitments flowing from that manifesto (including the reintroduction of strategic planning) it is a bit rich for the Committee to be complaining at the pace and extent of policy change! Whether you support individual policies or not, many will regard the business-like and speedy delivery by MHCLG, largely without surprises or u-turns, of what was promised as a breath of fresh air after previous regimes (remembering the instant dismantling by Eric Pickles in 2010 of regional planning with nothing in its place) or the constant yo-yoing of recent years: The 2020 Planning White Paper left to wither on the vine, followed by the Gove-led, changed priorities, December 2022 draft NPPF, only finalised a full twelve months later (despite Spring 2023 having been the promised publication date). And were any of the policy changes “robust and coherent”? Hmm.

Yes we still do not have a fully coherent system for determining what land should be released from the green belt, but I would argue that we now have more coherence than simply relying on those “exceptional circumstances” and “very special circumstances” tests. We’re also dealing with revisions to a policy which itself is incoherent, within a planning system which is incoherent. Against a pressing national need for homes and economic development, I suppose the choice is between “rushed and incoherent” or “delayed and incoherent”; you takes your choice.

It seems that part of the Committee’s thinking as to why the concept of “grey belt” is “largely redundant” (to use its own words) is that “more significant changes to other aspects of the NPPF…will be likely to result in Green Belt land being released through existing channels instead”, by way of green belt reviews via local plans and in due course spatial development strategies. If that turns out to be the case in the longer term, that is surely a good outcome. But the harder edged function of the concept in the meantime is to enable a consenting outlet that is not dependent on the much more uncertain “very special circumstances” test, where there is need that is not being accommodated in accordance with up to date plans and where delivery is falling short.

One only has to see (James Maurici KC’s LinkedIn posts are my usual source but you will no doubt have your own) the stream of appeal decision letters emanating from the Planning Inspectorate to have a sense of how often schemes are being promoted at present on the basis that they fall within the definition of “grey belt”, with “very special circumstances” as the fall-back, with many of those appeals being allowed. Surely, this has been exactly the sort of policy intervention that has been needed, albeit of course no overall panacea.

I have one final point to make in what has turned out to be a mini-rant, for which apologies (and of course I look forward to the happy sound of my phone buzzing as your rebuttal comments come in). I corrected Lord Moylan when I gave evidence to the Committee on 29 October 2024 and to my surprise at the time he appeared to be under the assumption that grey belt policy is only relevant to residential development. This was the exchange:

“The Chair:  Take an old abandoned industrial site inside the green belt. There could be strong arguments that a proper and effective use would be as a new industrial site. This policy is focused entirely on housing. Are you saying that you could still apply for that to be a new industrial site, but you would have to use the very special circumstances route to do so; grey belt simply would not apply to that?

Simon Ricketts: No. In fact, grey belt applies to commercial development as well as to residential development. It is a great problem with discussion about the planning system at the moment that everything is about housing. Allowing for logistics, industrial, life sciences and other development is just as important. The draft policy says that “housing, commercial and other development in the Green Belt should not be regarded as inappropriate where … “, and then sets out the criteria for grey belt that I have previously indicated.

There is a problem in that, if you are bringing forward housing development, it is easy to see whether there is an unmet housing need, because you apply the methodology that is in the public domain. However, in relation to commercial development, you have to show that “there is a demonstrable need for land to be released for development of local, regional or national importance”. There is no real guidance as to what the methodology would be for demonstrating that.

The Chair: That is under the very special circumstances test, or under the grey-belt test.

Simon Ricketts: Under the grey-belt test, if you consider that there is an unmet need for logistics development in your area and there is a piece of green belt that you consider to be grey belt because it makes a limited contribution to the purposes of the green belt, you can apply for planning permission if you can show that there is a demonstrable need for that land to be released for that form of development. That is inevitably more complicated than when you are dealing with housing development, because you will need to arrive at the right methodology.

The Chair: But it would be doable.

Simon Ricketts: Yes, absolutely.

The Chair: So it is perfectly possible that the grey-belt route could be used for non-housing development.

Simon Ricketts: Yes.”

Notwithstanding this exchange, is there anything in his letter to the Secretary of State which makes any reference whatsoever about anything other than housing? Nope.

 Simon Ricketts, 8 February 2025

Personal views, et cetera

I realised I’m currently wearing just the right t-shirt this morning.

I Just Called You In To Say I Love You

NB The title to this post is just for the benefit of those who say to me that the titles are the best bit. (I agree).

Following on from my 9 November 2024 blog post Intervention, there were two decisions issued yesterday (22 November 2024) resulting from call-ins of applications by the previous Government, one in relation to Berkeley’s Cranbrook scheme (initially refused by the previously Secretary of State, which decision was then quashed by consent, and now finally approved), the other in relation to a large logistics scheme in the Warrington green belt (initially resolved to be approved by Warrington Council, but now refused by the Secretary of State).

 The Secretary of State’s power in section 77 of the Town and Country Planning Act 1990 to call-in applications for planning permission which raise planning issues of more than local importance is sparingly used. Usually, the power is used after the local planning authority has resolved to approve an application for planning permission for development. The Secretary of State’s policy remains that examples of where “planning issues of more than local importance” include those which in her opinion:

  • may conflict with national policies on important matters;
  • may have significant long-term impact on economic growth and meeting housing needs across a wider area than a single local authority;
  • could have significant effects beyond their immediate locality;
  • give rise to substantial cross-boundary or national controversy;
  • raise significant architectural and urban design issues; or
  • may involve the interests of national security or of foreign Governments.
  • However, each case will continue to be considered on its individual merits.”

The Quinn Estates/Sittingbourne situation I mentioned in my Intervention blog post is unusual, in that the decision to call-in was taken just before a meeting of the local planning authority’s planning committee where the applications in question were recommended for refusal.

The case remains that call-in by the Secretary of State (under section 77) is of little advantage to an applicant as opposed to appeal (under section 78) against the refusal or non-determination of the relevant application. The procedures are equivalent. The position is very much in contrast to the position in London where the Mayor can become the relevant planning authority for applications which meet specified criteria and then determine them rapidly via a representations hearing – a useful process in unlocking situations as with, recently, the proposed redevelopment of Springfield Hospital in Wandsworth and the proposed expansion of the All England Lawn Tennis Club in Wimbledon.

Turning to yesterday’s decisions (neither of which incidentally draw at all on the contents of the draft revised NPPF – we should hold our excitement as to the relevance of that document until the final version emerges before the end of the next month – these Christmas NPPF drops are now an annual staple of our festive plans):

Cranbook

I reported on the previous Secretary of State’s initial decision to refuse the application in my 22 April 2023 blog post, Mind Blowing Decisions. As it turned out, the decision was so mind blowing that the Secretary of State ended up consenting to judgment in October 2023 when the decision was challenged in the High Court by Berkeley.

The new Secretary of State has considered further representations from the parties and has now approved the scheme.

You may recall the previous Secretary of State’s criticisms of the scheme as not “sensitively designed” and being “of a generic suburban nature”. Those concerns haven’t entirely gone away but their relevance is now downplayed:

Whilst the Secretary of State has concerns about the layout and design of the proposal, particularly the sensitivity and appropriateness of the design in the context of its setting, she has taken into account that only 20% of the site would be built on (IR730) and the proposed development would deliver landscape enhancements (IR826). Overall, she considers that the design of the scheme is a neutral factor in this case.”

The Secretary of State also notes the now enhanced protection for AONBs (now national landscapes) via section 245 of the Levelling-up and Regeneration Act 2023 and that the local planning authority can now demonstrate a five-year housing land supply but again these factors do not lead to refusal of the application. She “considers that the delivery of 165 homes (40% affordable housing) carries significant weight.”

Her overall conclusions:

58. For the reasons given above, the Secretary of State considers that the application is not in accordance with Policies LBD1 of the Local Plan, Core Policies 1 and 14 of the Core

Strategy, and Policy AL/STR 1 of the Site Allocations LP, and is not fully in accordance with Policy EN21, EN22, EN25 of the Local Plan or Core Policy 12. She considers that the application is not in accordance with the development plan overall. She has gone on to consider whether there are material considerations which indicate that the proposal should be determined other than in accordance with the development plan.

59. Weighing in favour of the development are the need for and delivery of housing, the BNG, enhanced recreation opportunities, improvements in highway safety, heritage benefits to the historic landscape and landscape benefits by way of woodland planting and management, which collectively carry substantial weight.

60. Weighing against the proposal is the harm to the landscape and the scenic beauty of the HWAONB which attracts great weight, harm arising from development outside the limits of built development which carries moderate weight, harm to air quality which carries very limited weight and the effect on the plan-making process of the eLP which carries very limited weight.

61. The Secretary of State has concluded for the reasons given above that exceptional circumstances exist to justify the proposed development in the HWAONB and that the

development would be in the public interest.  The AONB test at paragraph 183 (formerly 177) of the Framework is therefore favourable to the proposal.

62. Overall, the Secretary of State’s conclusion on section 38(6) of the Planning and Compulsory Purchase Act 2004 is that despite the conflict with the development plan, the material considerations in this case indicate that permission should be granted.

63. The Secretary of State therefore concludes that planning permission should be granted.”

Warrington

This was an application for planning permission for around 3 million square feet of B8 development at Bradley Hall Farm, Grappenhall Lane, Warrington. The application was originally made in April 2019. Warrington Council had resolved to approve the application in March 2022 before it was called in in November 2022. The site had been proposed to be allocated in the emerging local plan before then being removed in the plan that was adopted in December 2023, the local plan inspector having concluded that there was no strategic need for the allocation.

In her decision letter yesterday, the Secretary of State reaches this conclusion on employment land supply and demand, and the need for employment land:

For the reasons given at IR340-349 the Secretary of State recognises that there is a strong demand for logistics facilities and that the supply of the largest sites is limited within the region (IR347). However, overall she agrees with the Inspector at IR350 that the case for logistics supply and demand is overstated and largely based on subjective opinion rather than robust quantitative data.”

The Secretary of State agrees at IR353 that it was not for the Inspector to revisit the underlaying basis of the very recently adopted Local Plan and determine the objectively assessed need for employment land in Warrington.

For the reasons given at IR351-359 and IR384, the Secretary of State, like the Inspector, accepts that a need for large scale units across the region is present (IR358).  Like the Inspector, she is not persuaded that there is a lack of alternatives across the region, but agrees that provision is limited and not ideal. She further agrees therefore that a genuine need for the site within a regional context has not been wholly proven (IR359). The Secretary of State agrees with the Inspector at IR384 that the need for employment land carries limited weight.”

Overall, she found that the necessary “very special circumstances” case had not been made out.

Simon Ricketts, 23 November 2024

Personal views, et cetera

Photo courtesy of Jon Tyson via Unsplash

Money’s Too Tight: The One About Viability

The Valentine Brothers original version obviously, rather than Simply Red.

In fact, pardon me if this post feels a little like the extended 12” remix, but I wanted to work out for myself some of the long-running arguments that are out there as to the role of financial viability testing in planning.

The subject has been made topical by the “viability in relation to green belt release” annex to the consultation draft revised National Planning Policy Framework, as well as Labour’s proposals in relation to “no hope value” CPOs (mentioned in my 21 July 2024 blog post Hope/No Hope). But the discussion is vital anyway in present circumstances where, in order to deliver and/or fund necessary housing development (and indeed many other forms of development), the state largely relies on the private sector, which is inevitably motivated by profit.

It’s difficult to have a sensible discussion without trying to establish some basic principles. So here goes…

We want an acceptable environment around us: sufficient social housing for those who need it, health and education facilities, biodiversity and open space, good public transport, footpaths and cycleways.

We no longer seem prepared to pay for this fully through direct taxation or indeed charitable benevolence.

Instead, over the last 25 years or so of my career, Government policy has increasingly supported the indirect taxation of development activity (primarily by way of section 106 agreement planning obligations and the community infrastructure levy) to help pay for all these good things, even where it is not the development itself that is leading to the need for the particular infrastructure or facilities (and before you raise it, regulation 122 of the Community Infrastructure Levy Regulations only provides cover against the most egregious of LPA “asks”).

Affordable housing is the classic example of what I mean by indirect taxation. As I set out in my 28 May 2017 blog post Affordable Housing Tax:

In requiring the developers of private housing schemes to contribute to the provision of affordable housing, the planning system has become a tax collection system, and an inefficient, opaque one at that.

[…]

“The provision of market housing does not in any way increase the need for affordable housing, indeed over time by increasing supply if anything it should decrease it. It may be said that mixed use communities can only be achieved by requiring the inclusion of affordable housing within market residential schemes, but that in itself does not justify the state putting the cost of the affordable housing at the door of the developer.”

[Think how odd it would be for car makers to be required to sell a large proportion of their product at below market rate, in fact at a loss – or indeed for supermarket chains to be so required – nice as that thought might be. Why is housing so different?]

Add to this the much-reduced availability of grant funding.

You see the same indirect taxation in the case, for instance, of schools: whether or not a particular housing scheme is built, children need schooling somewhere in the country. And yet the cost of delivery of new schools is regularly met in large part by way of contributions and obligations extracted via the planning system.

Most recently, the 10% biodiversity net gain requirement. Laudable – but another indirect tax on development via the planning system.

All of this appears to be implicitly accepted as in the public interest, presumably on the basis that:

  • It’s a victimless crime – assumed to be paid for out of (a) the receipts the land-owner receives for sale of the land, as long as the requirements are flagged sufficiently far in advance that they can be built into the contractual arrangements between the land owner and developer and can generally manage the land-owner’s expectations; and/or (2) the developer’s profit (for whom the return needs to outweigh the risk).
  • It sugars the pill for local communities, which is important given the general antipathy towards development (or maybe that’s just my village’s Facebook group….).
  • It would be politically impractical to meet these costs via the national public purse.

This is all fine if the numbers work out – if the contributions required by policy can be paid for, whilst leaving enough money in the project to ensure that it will still proceed i.e. that between them:

  • The land-owner receives enough money to persuade them to sell the land, rather than hold onto it or sell it for other purposes
  • The developer concludes that there is a sufficient slice of profit left to make it worthwhile as a business proposition to proceed to carry out the development, having regard to the availability, and likely cost over time, of development finance and/or of funding partners, and the range of development risks such as the costs of construction, other regulatory costs and uncertainties over time, unforeseen problems along the way and as to the financial return likely to be achieved at the end of it all
  • The purchaser or renter of the home is protected by operation of market forces against the cost simply being passed onto them.

What happens when the contributions requested in return for planning permission don’t work out? That is where the viability appraisal process comes in.

The Planning Practice Guidance https://www.gov.uk/guidance/viability advises that local plans “should set out the contributions expected from development. This should include setting out the levels and types of affordable housing provision required, along with other infrastructure (such as that needed for education, health, transport, flood and water management, green and digital infrastructure).

These policy requirements should be informed by evidence of infrastructure and affordable housing need, and a proportionate assessment of viability that takes into account all relevant policies, and local and national standards, including the cost implications of the Community Infrastructure Levy (CIL) and section 106. Policy requirements should be clear so that they can be accurately accounted for in the price paid for land.”

Obviously, it is sensible for local plans to give as much certainty as possible as to what contributions will be sought from developers and thereby to serve to dampen the expectations of land-owners. But the reality is that viability assessments at the local plan making stage are inevitably broad-brush, often based on typical development typologies. They become out of date. There is often insufficient push-back from developers – either because they do not yet have a relevant project in mind at the time the plan is being consulted upon and examined, or because they are nervous about losing the potential allocation of their site for development. And so policy aspirations are set high.

When an application for planning permission comes forward for development which is in accordance with the local plan or otherwise in the public interest, save that the full range of policy requirements cannot be met without rendering the project unachievable, what happens then?

To quote paragraph 58 of the current NPPF (which paragraph is not proposed to be amended in the consultation draft):

Where up-to-date policies have set out the contributions expected from development, planning applications that comply with them should be assumed to be viable. It is up to the applicant to demonstrate whether particular circumstances justify the need for a viability assessment at the application stage. The weight to be given to a viability assessment is a matter for the decision maker, having regard to all the circumstances in the case, including whether the plan and the viability evidence underpinning it is up to date, and any change in site circumstances since the plan was brought into force. All viability assessments, including any undertaken at the plan-making stage, should reflect the recommended approach in national planning guidance, including standardised inputs, and should be made publicly available.”

A decision-maker can decide to grant planning permission without commitments on the part of the developer to all of the contributions normally required by policy, if the developer has justified that the development would otherwise be unviable  demonstrating that by way of a viability assessment carried out in accordance with the methodology set out in the Government’s Planning Practice Guidance.

The guidance these days is tighter than it was, although there is still much room for debate and disagreement as between the developer’s surveyor and the surveyor engaged by the local planning authority (invariably at the developer’s cost). There is much public discussion about “benchmark land value” in this exercise, i.e. in estimating the costs of carrying out the development, what cost should be assumed for the land itself? But that is by no means the only factor when it comes to viability. In many situations, development may be unviable even assuming little or no land value, simply because of, for instance, the large infrastructure costs which would need to be met by the developer, financing costs and/or low value of the completed development – and this is all made more complicated in relation to longer-term projects, where an internal rate of return model may be more appropriate. But for I’m going to focus here on the land value issue.

It’s been clear for many years that the benchmark land value to be plugged into the viability appraisal is not the price that the developer has actually paid for the land – see for example Parkhurst Road Limited v Secretary of State (Holgate J, 27 April 2018). Instead, the usual approach, according to the Planning Practice Guidance, should be EUV+, i.e. to take the existing use value (ignoring, for example, any development potential) and then to apply a premium. Oh dear, one of the big questions is how big should that premium be? The guidance says this:

The premium should provide a reasonable incentive for a land owner to bring forward land for development while allowing a sufficient contribution to fully comply with policy requirements.

Plan makers should establish a reasonable premium to the landowner for the purpose of assessing the viability of their plan. This will be an iterative process informed by professional judgement and must be based upon the best available evidence informed by cross sector collaboration. Market evidence can include benchmark land values from other viability assessments. Land transactions can be used but only as a cross check to the other evidence. Any data used should reasonably identify any adjustments necessary to reflect the cost of policy compliance (including for affordable housing), or differences in the quality of land, site scale, market performance of different building use types and reasonable expectations of local landowners. Policy compliance means that the development complies fully with up to date plan policies including any policy requirements for contributions towards affordable housing requirements at the relevant levels set out in the plan. A decision maker can give appropriate weight to emerging policies. Local authorities can request data on the price paid for land (or the price expected to be paid through an option or promotion agreement).”

There are some examples of where a premium of many times the EUV has been found to be appropriate. For example:

  • Long Marston, Pebworth (APP/H1840/S/16/3158916, 16 May 2017): In the particular circumstances there, the inspector found that a premium of around 15 times the EUV was appropriate. (The appeal pre-dated the PPG but turned on a similar earlier concept of EUV+).
  • Parkhurst Road, Islington (APP/V5570/W/16/3151698, 19 June 2017): The appeal site was a former Territorial Army barracks in north London. The inspector found that the EUV was £2.4m but EUV+ was £6.75m (still less than the developer had paid for the site) . In the subsequent High Court challenge I refer to above, Holgate J the judge said this about EUV+: “Some adherents appear to be promoting a formulaic application of ‘EUV plus.’ But as the RICS advised its members in its 2012 Guidance Note, an uplift of between 10 and 40% on existing use value is an arbitrary number and the method does not reflect the workings of the market…”.
  • Old Oak and Park Royal local plan examination in public, Inspector’s Interim Finding on Viability (10 September 2019) : In relation to the Car Giant site forming most of the plan area, a very large brownfield site in north London, the inspector found the EUV to be £5.3m. The Old Oak and Park Royal Development Corporation’s surveyors suggested a premium of 20% would be appropriate. The inspector found that the characteristics of the site, including in particular Car Giant’s significant relocation costs, would justify a far larger premium, concluding that EUV+ was “clearly in excess of £240m”.

On the one hand, this sort of exercise may be seen as sensible in that it is seeking to get to the number that can be taken to be the tipping point at which a land-owner might rationally choose to sell rather than stay put. But of course, on the other, the potential range is so wide that the outcome of the process can be very unpredictable and result in high numbers – true but what is the alternative that enables or persuades land-owners (who are often in fact reluctant to sell in any event – their heads only turned by a financial offer they can’t refuse) actually to make their land available, unless there is a market intervention such as compulsory purchase (but (1) that obviously needs careful justification and (2) a careful look is needed at how the compulsory purchase compensation principles work), some targeted form of tax credits or in fact (never thought I’d say this and I still only think this works in theory rather than reality) community land auctions?

I’ll throw in another complication here: the figures in a viability appraisal are in part theoretical. We know that the actual price paid for the land isn’t plugged into the equation. The actual price may have been far higher, meaning that the developer is always going to be struggling to get the project off the ground. It may have been lower – the land may have been held for generations, with a very low current book value, or be held by a body that is prepared to make the land available at an under-value. Similarly as to the efficiencies in construction or financing that a particular developer may be able to bring to the process (versus the greater challenges in this respect an SME may have than a national housebuilder), or preparedness to take a reduced profit, or even a loss with this development, given wider objectives. If we want an objective scrutiny of the financial position, not tied to a particular developer who may of course in any event sell on, this is probably right. But it does mean that there may be two processes underway: (1) what is the objective agreed assessment as to the viability of the project and (2) is this developer for some reason prepared to offer more than what is objectively viable on the basis of that agreed assessment?

Can we at least agree that this subject is not easy, either in macro policy terms or in its detailed application? And that whilst it may be tempting for some to say “get rid of viability testing, development must simply meet all policy requirements”, can we agree that this is unrealistic without (1) up to date realistic local plan policies (unlikely) or (2) an acknowledgement that effect would less development coming forward, particularly in the areas where it is most needed?

At which point I turn to the Government’s proposals.

A new annex is included in its draft revised NPPF, headed “viability in relation to green belt release”, but one of the only two new elements of the proposed approach set out in that annex is what I have put in bold in the following paragraph:

“To determine land value for a viability assessment, a benchmark land value should be established on the basis of the existing use value (EUV) of the land, plus a reasonable and proportionate premium for the landowner. For the purposes of plan-making and decision- taking, it is considered that a benchmark land value of [xxxx] allows an appropriate premium for landowners. Local planning authorities should set benchmark land values informed by this, and by local material considerations.

These are the key associated paragraphs in the consultation document which explain the “[xxxx]“:

29. Approaches that government could take to ensure the appropriate use of viability include the following options.

a. Government sets benchmark land values to be used in viability assessments. When assessing whether a scheme is viable, it is necessary to make an allowance for the amount of money to be paid to the landowner. This should currently be set by the local planning authority. Government could set indicative benchmark land values for land released from the Green Belt through national policy, to inform the policies developed on benchmark land value by local planning authorities. These should be set at a fair level, allowing for a premium above the existing use, but reflecting the need for policy delivery against the golden rules. Different approaches to benchmark land value are likely to be appropriate for agricultural land, and for previously developed land.

b. Government sets policy parameters so that where land transacts at a price above benchmark land value, policy requirements should be assumed to be viable. As part of this approach, Government sets out that if land has been sold (or optioned) at a price which exceeds the nationally set benchmark land value, viability negotiation should not be undertaken. Under this approach, the planning authority should not be seeking higher contributions (e.g. 60 per cent affordable housing), but equally the developer should not be seeking lower contributions (e.g. 40 per cent affordable housing), as this would represent a transfer of value from the public to private landholders. Therefore, planning permissions would not generally be granted for proposed developments where land transacts above benchmark land value, and cannot comply with policy.

c. Government sets out that where development proposals comply with benchmark land value requirements, and a viability negotiation to reduce policy delivery occurs, a late-stage review should be undertaken. This would build on the approach to be taken by the Greater London Authority, and tests actual costs and revenues against the assumptions made in the initial viability assessment. If, for example, the development is more viable than initially assumed, due to a rise in house prices, then additional contributions can be secured, to bring the development closer to or up to policy compliance.

30. Benchmark land values are generally set as a multiple of agricultural use values, which are typically in the region of £20,000 – £25,000 per hectare, and as a percentage uplift on non-agricultural brownfield use values. We also note that views of appropriate premia above existing use values vary: for agricultural land, a recent academic paper[footnote 6 ] suggested BLVs of three times existing use value; the Letwin Review of Build Out [footnote 7] suggested ten times existing use value; Lichfields found that local planning authorities set BLVs of between 10- and 40-times existing use value [footnote 8 ]. These BLVs do not necessarily relate to Green Belt land, which is subject to severe restrictions on development, and Government is particularly interested in the impact of setting BLV at the lower end of this spectrum.

31. The Government considers that limited Green Belt release, prioritising grey belt, will provide an excellent opportunity for landowners to sell their land at a fair price, while supporting the development of affordable housing, infrastructure and access to nature. Where such land is not brought forward for development on a voluntary basis, the Government is considering how bodies such as local planning authorities, combined authorities, and Homes England could take a proactive role in the assembly of the land to help bring forward policy compliant schemes, supported where necessary by compulsory purchase powers, with compensation being assessed under the statutory no-scheme principle rules set out in Part 2 of the Land Compensation Act 1961.

32. In such cases, these rules would operate to exclude any increases or decreases in value of land caused by the compulsory purchase scheme, or by the prospect of it, and valuation of the prospect of planning permission (‘hope value’) for alternative development would reflect the golden rules outlined in the NPPF. Use of compulsory purchase powers may also include use of directions to secure ‘no hope value’ compensation where appropriate and justified in the public interest. A comprehensive justification for a no hope value direction (e.g., which includes a high proportion of vital affordable housing being delivered) will strengthen the argument that a direction is in the public interest. This would align with the Government’s aspiration for high levels of affordable housing to be delivered on these sites.”

That emboldening is in the document itself. So, we are looking at a potential approach where, for the purposes of viability appraisals on green belt sites (where there will be the policy requirement of “at least 50% affordable housing, with an appropriate proportion being Social Rent”) the Government caps the potential premium on existing use value more towards 3x than between 10 and 40x. That would provide some clarity, and would in the long term (beyond the gestation of current promotion agreements, option agreements and the like which will have baked in potentially higher figures) dampen land-owner expectations. However, the outcome may be that some potential sites are not released by land-owners because the resultant return is simply not worth it for them – they would prefer to hold the land for its current purposes, or make it available for non-residential development which may result in a higher premium, or wait for a more liberal policy climate to open up in future decades – and in the meantime battle against any threat of compulsory purchase. This is particularly the case at the moment where, as another risk to factor in, there is a dearth of registered providers even willing to build-out or take on the affordable housing element in some areas. The impacts of the approach will also particularly be felt in areas with weaker housing markets, where 50% affordable housing (including, importantly, an as yet unknown proportion of socially rented housing) will be a big drag on viability – and those areas are often the same areas where housing targets will be going up most steeply under the proposed revised standard method.

This proposal to set a blanket cap on existing use values really does need to be stress-tested during the current consultation period. I would particularly urge those with market knowledge to review those papers referred to in paragraph 30 quoted above – I have included the links. For instance, I couldn’t immediately see the workings for 3x EUV in that first paper.

The other change which that annex proposes is in its last line:

Where a viability negotiation to reduce policy delivery has been undertaken, a late-stage review should be conducted to assess whether further contributions are required.”

Remember, this annex only relates to development in the green belt, but its effect is to advise that where policy compliant development (eg 50% affordable housing), cannot be delivered due to lack of viability, a provision should be included in the section 106 agreement, providing for a review at a later stage, or at later stages, of the development to see whether that is still the position or whether the project is now able to afford to meet those policy commitments, in full or at least in part. Obviously, in London, this has been relatively standard for some time (see eg the Mayor’s May 2023 draft development viability London Plan Guidance), and is often used in negotiations across the country. But the negotiation is never straight-forward, even in London where the provisions are so standardised. What should be the triggers; what is opened up on the review (and is it just a review of what has been developed so far or is it also an updated estimate of what has not yet been built); what proportion of the surplus should be retained by the developer so as to provide any incentive; what should be the cap on what can be secured on review (vital, as all of this is very sensitive to funders and lenders); what should any surplus be applied towards and what say does the developer has in this?

The threat of compulsory purchase in the case of recalcitrant landowners? That takes us back to the issues I covered in that Hope/No Hope blog post. In some cases, perhaps so, but of course as I have mentioned above, even acquisition of land at existing use value (which obviously would lead to protracted wrangling in many cases) does not always guarantee project viability.

Apologies for all that. Something got me started.

Simon Ricketts, 18 August 2024

Personal views, et cetera

50 Shades Of Grey Belt

Q: How do you eat an elephant?

A: One bite at a time.

So as well with the Government’s proposed reforms to the planning system, announced on 30 and 31 July 2024.

I reckon the whole elephant looks like this:

Gulp.

Maybe even this will be more than you or I can chew but for this blog post I am only going to focus on the proposed changes to green belt policy. Much of the text which follows is by my Town Legal colleagues Susannah Herbert and Aline Hyde to whom much thanks…

Green Belt – Plan Making

Local planning authorities will be required “to undertake a review where an authority cannot meet its identified housing, commercial or other need without altering Green Belt boundaries.” (This is in addition to removing the December 2023 additions which set out the circumstances in which local planning authorities would not be required to undertake a Green Belt review).  The amendment defines “exceptional circumstances” to “include instances where an authority cannot meet its identified need for housing, commercial or other development through other means”.

A sequential test is proposed, to guide changes to Green Belt boundaries through local plans – “This will ask authorities to give first consideration to PDL [previously developed land] within the Green Belt, before moving on to other grey belt sites, and finally to higher performing Green Belt sites where these can be made sustainable. …, land that is safeguarded by existing environmental designations, for example National Parks, National Landscapes and Sites of Special Scientific Interest, will maintain its protections.

18. The aim of this approach is to ensure that low quality Green Belt is identified first, while not restricting development of specific opportunities which could be made more sustainable (for example, on land around train stations). This is in recognition that not all PDL or ‘Grey Belt’ will be in the most suitable or sustainable location for development. As such, it is right that local planning authorities are empowered to make decisions that best support the development needs and sustainability objectives of their area through the plan-making process. There is clear expectation that local planning authorities should seek to meet their development needs in full. However, we remain clear that the release of land should not be supported where doing so would fundamentally undermine the function of the Green Belt across the area of the plan as a whole. We propose changes to paragraph 147 of the NPPF to achieve this approach.”

The proposed wording is as follows:

142 (previously 144) (comparison to Sept 2023) Once established, Green Belt boundaries should only be altered where exceptional circumstances are fully evidenced and justified, through the preparation or updating of plans. Exceptional circumstances include, but are not limited to, instances where an authority cannot meet its identified need for housing, commercial or other development through other means. In these circumstances authorities should review Green Belt boundaries and propose alterations to meet these needs in full, unless the review provides clear evidence that such alterations would fundamentally undermine the function of the Green Belt across the area of the plan as a whole. Strategic policies should establish the need for any changes to Green Belt boundaries, having regard to their intended permanence in the long term, so they can endure beyond the plan period. Where a need for changes to Green Belt boundaries has been established through strategic policies, detailed amendments to those boundaries may be made through non- strategic policies, including neighbourhood plans.

144.(previously 146)  When drawing up or reviewing Green Belt boundaries, the need to promote sustainable patterns of development should be taken into account. Strategic policy- making authorities should consider the consequences for sustainable development of channelling development towards urban areas inside the Green Belt boundary, towards towns and villages inset within the Green Belt or towards locations beyond the outer Green Belt boundary. Where it has been concluded that it is necessary to release Green Belt land for development, plans should give first consideration to previously-developed land in sustainable locations, then consider grey belt land in sustainable locations which is not already previously-developed, and only then consider other sustainable Green Belt locations. They should also set out ways in which the impact of removing land from the Green Belt can be offset through compensatory improvements to the environmental quality and accessibility of remaining Green Belt land.

Grey belt

Grey belt will be defined (in the glossary at Annex 2 to the NPPF) as follows:

“Grey belt: For the purposes of Plan-making and decision-making, grey belt is defined as land in the Green Belt comprising Previously Developed Land and any other parcels and/or areas of Green Belt land that make a limited contribution to the five Green Belt purposes (as defined in para 140 of this Framework) but excluding those areas or assets of particular importance listed in footnote 7 of this Framework (other than land designated as Green Belt).”

The Government is  “interested in whether further support is needed to assist authorities in judging whether land makes a limited contribution to the Green Belt purposes. They propose incorporating the following into the glossary appended to the NPPF:

 Land which makes a limited contribution to the Green Belt purposes will:

  • Not strongly perform against any Green Belt purpose; and
  • Have at least one of the following features:
    i. Land containing substantial built development or which is fully enclosed by built form
    ii. Land which makes no or very little contribution to preventing neighbouring towns from merging into one another
    iii. Land which is dominated by urban land uses, including physical developments
    iv. Land which contributes little to preserving the setting and special character of historic towns

Many local planning authorities will have evidence base documents which assess the effectiveness of parcels of land against the purposes of designating land as Green Belt but these documents do not necessarily observe this draft methodology. The extent to which they will be useful in guiding decision-making, at least in the short term until they can be revisited, is then unclear.

[Comment from me – “limited contribution”: huge room for debate!]

Green Belt Decision Making

The definition of “inappropriate development” is to be significantly restricted. At present in order for development on previously developed land not to be “inappropriate development” (and therefore be subject to the “very special circumstances” test) then (unless it would contribute to meeting an identified affordable housing need) it “must not have a greater impact on the openness of the Green Belt than the existing development”. Draft revised paragraph 151 waters down this test to “would not cause substantial harm to the openness of the Green Belt”.

[Another comment from me – “substantial harm”: huge room for debate, as it is already in the case of proposed development that would contribute to meeting an identified affordable housing need.]

In terms of the Grey Belt concept, the Government proposes to insert a new paragraph in the NPPF which will make clear that, “in instances where a local planning authority cannot demonstrate a 5-year housing land supply or is delivering less than 75% against the Housing Delivery Test, or where there is unmet commercial or other need, development on the Green Belt will not be considered inappropriate when it is on sustainable ‘grey belt’ land, where golden rules for major development are satisfied, and where development would not fundamentally undermine the function of the Green Belt across the area of the plan as a whole.” 

{Comment from me: “unmet commercial or other need“, “fundamentally undermine” – yes you’re there before me.]

This is set out in the new paragraph 152:

“152. In addition to the above, housing, commercial and other development in the Green Belt should not be regarded as inappropriate where:

a. The development would utilise grey belt land in sustainable locations, the contributions set out in paragraph 155 below are provided, and the development would not fundamentally undermine the function of the Green Belt across the area of the plan as a whole; and

b. The local planning authority cannot demonstrate a five year supply of deliverable housing sites (with a buffer, if applicable, as set out in paragraph 76) or where the Housing Delivery Test indicates that the delivery of housing was below 75% of the housing requirement over the previous three years; or there is a demonstrable need for land to be released for development of local, regional or national importance.

c. Development is able to meet the planning policy requirements set out in paragraph 155.”

In terms of development on non-Grey-Belt-Green-Belt, the Government states “Our proposal limits release via this route to grey belt, including PDL — reaffirming our commitment to a plan-led system by maintaining restrictions on the release of wider Green Belt land. It would, as now, be possible for other Green Belt land to be released outside the plan-making process where ‘very special circumstances’ exist, but such cases would remain exceptional.” 

Therefore, in theory, the test of “very special circumstances” for Green Belt development remains unchanged but the existence of Grey Belt and the priority given in policy may make it harder to make the case for development on non-Grey-Belt-Green-Belt (although the emphasis on sustainable locations in the sequential test may also benefit some non-Grey-Belt-Green-Belt locations).

Golden Rules and Viability for Green Belt development

The proposed “Golden Rules” for Green Belt development are set out in a new paragraph 155:

“a. In the case of schemes involving the provision of housing, at least 50% affordable housing [with an appropriate proportion being Social Rent], subject to

viability;

b. Necessary improvements to local or national infrastructure; and

c. The provision of new, or improvements to existing, green spaces that are accessible to the public. Where residential development is involved, the objective should be for new residents to be able to access good quality green spaces within a short walk of their home, whether through onsite provision or through access to offsite spaces.

156. Regarding the provision of green space, development proposals should meet local standards where these exist in local plans, for example local planning policies on access to green space and / or urban greening factors. Where no locally specific  standards exist, development proposals should meet national standards relevant to the development. These include Natural England standards on accessible green space and urban greening factor and Green Flag criteria.”

According to paragraph 155, these will apply “Where major development takes place on land which has been released from the Green Belt through plan preparation or review, or on sites in the Green Belt permitted through development management”.  This refers to major development.  However, paragraph 152 in respect of Grey Belt appears to refer to all potential development on Grey Belt needing to meet these Golden Rules.

The Government considers that “Green Belt land can deliver more affordable housing, infrastructure and environmental contributions, as the value of the land in its existing use is generally low and the Green Belt designation reduces the hope value associated with the prospect of securing planning permission.”  However, it does acknowledge that contributions that can be secured will vary because of varied house prices, abnormal costs, CIL rates or higher existing use values and therefore, they believe that “it is necessary to allow the limited use of viability assessments, where negotiation is genuinely needed for development to come forward, particularly in relation to affordable housing requirements. However, this cannot be an excuse to inflate landowner or developer profits at the expense of the public good”.

Additional guidance on viability considerations for development in the Green Belt is provided in Annex 4.  This is headed “Viability in Relation to Green Belt release”.  It proposes to set a specific benchmark land value.

It also provides that:

“- if land released from Green Belt is transacted above the benchmark land value and cannot deliver policy-compliant development, then planning permission should not be granted, subject to other material considerations;

–  if policy compliant development can be delivered, viability assessment should not be undertaken, irrespective of the price at which land is transacted, and higher levels of affordable housing should not be sought on the grounds of viability;

-Where land is transacted below the benchmark land value but still cannot deliver policy- compliant development, it is up to the applicant to demonstrate whether particular circumstances justify the need for a viability assessment at the application stage. The weight to be given to a viability assessment is a matter for the decision maker, having regard to all the circumstances in the case, including whether the plan and the viability evidence underpinning it is up to date, and any change in site circumstances since the plan was brought into force. Where a viability negotiation to reduce policy delivery has been undertaken, a late-stage review should be conducted to assess whether further contributions are required.”

The consultation notes that there is a spectrum of views of appropriate premia above existing use value ranging between 3 times EUV to 10-40 times EUV.  The Government is “particularly interested in the impact of setting BLV at the lower end of this spectrum.”  

The consultation then immediately goes on to mention the potential for the use of compulsory purchase powers where such land is not brought forward on a voluntary basis.  In this case compensation would be assessed under the statutory no-scheme principle rules set out in Part 2 of the Land Compensation Act 1961 so that any increases or decreases in the value of land caused by the proposed scheme would be ruled out.  The “hope value” for alternative development would reflect the “Golden Rules” set out above.  However, the consultation also states that “Use of compulsory purchase powers may also include use of directions to secure ‘no hope value’ compensation where appropriate and justified in the public interest. A comprehensive justification for a no hope value direction (e.g., which includes a high proportion of vital affordable housing being delivered) will strengthen the argument that a direction is in the public interest. This would align with the Government’s aspiration for high levels of affordable housing to be delivered on these sites.”  

Question 43 asks “Do you have a view on whether the golden rules should apply only to ‘new’ Green Belt release, which occurs following these changes to the NPPF? Are there other transitional arrangements we should consider, including, for example, draft plans at the regulation 19 stage?”.  As drafted, it is not clear when the Golden Rules, or the provisions of Annex 4 will apply.  At present, when land is released from the Green Belt through the plan making system, Green Belt policies no longer apply.  However, the proposed provisions are drafted to apply to “land released from Green Belt” so it will be important to have clear transitional provisions.

The Government’s clear intention expressed through the consultation is that development on Green Belt land is to be held to a higher standard and cannot be permitted without delivering a public benefit in the form of affordable housing, mitigating its own infrastructure impacts, and not undermining the overall strategic function of the designation.

More anon.

Simon Ricketts, 2 August 2024

Personal views, et cetera

Courtesy Vincent van Zalinge via Unsplash

What To Look Out For With This Week’s Promised Draft Revised NPPF

As Zack Simons noted in his LinkedIn post this morning (27 July 2024), there was a detailed story in today’s Times as to what will be in the consultation draft revised NPPF. As Zack summarises:

“-  Tuesday’s the day. 

–   8 week consultation, new NPPF adopted late September. 

–   “Mandatory housing targets” going up by 50%. 

–   That’s a circa 100,000 home national increase to what we now call “local housing need”. Changes include: (i) “toughened” affordability ratios “to take account of how many people might move into an area if housing was cheaper”, and (ii) no use of “previous oversupply of housing to reduce future targets”

  Councils “must review protections for the green belt if they cannot meet their housing need on brownfield land”.”

It’s such a detailed story that depressingly the new Government is obviously continuing the previous Government’s routine practice of trailing imminent significant announcements in the weekend newspapers as unattributed news stories rather than first announcing them in Parliament. Easy spin, easy journalism.

However, the story is totally and deliberately useless as anything that can yet be relied upon.

Here are some of the things I’ll be looking to understand on Tuesday (no surprise it’s Tuesday: that’s when the House of Commons rises for the summer):

  • I assume that the consultation document will be accompanied by a ministerial statement setting out the Government’s policy objectives underlying the document. This is important because, subject to anything specified to the contrary, then the statement and at least the direction of travel demonstrated by the draft is capable of being a material consideration in the determination of planning applications and appeals, with the weight to be given to it a matter for the decision maker. Depending on its potential relevance to current applications and appeals, the decision maker may choose to invite representations as to the implications for the particular application or appeal of what has been published, and, indeed, in some circumstances decisions may be susceptible to legal challenge if such an announcement is “obviously material” and not taken into account. So as much as its content, what will be important will be the tone of the consultation (is the consultation just about detailed wording or is it more open-minded, testing alternative potential approaches?) and of the accompanying statement or statements (particularly, what is said about its immediate intended effect). (And incidentally what we don’t want is for decision-makers to conclude that they need to wait for the final version!)
  • What transitional arrangements, if any, are proposed in relation to emerging and adopted local plans before their policies are to be treated as out of date by virtue of the new policies and targets? After all, we still have a plan-led system.
  • To what extent will the requirement that councils “must review protections for the green belt if they cannot meet their housing need on brownfield land” simply be a peeling back of the December 2023 revision to the NPPF?
  • If local housing targets are going to be increased, does this mean that the consultation process will include (long awaited) proposed revisions to the standard method? If so, how extensive will the changes be? For instance will the 35% uplift remain for England’s 20 largest towns and cities?
  • Is this going to be a “big bang” set of NPPF changes delivering on all that has been previously trailed by Labour, for instance giving some reality to the “grey belt” notion, or (possibly more pragmatically) are we to expect a further set of revisions before long, possibly alongside a proposed initial set of national development management policies and/or alongside guidance to reflect the amended local plans system enabled by the Levelling-up and Regeneration Act?
  • What about anything other than housing?
  • When really will we see the final version? Eight weeks’ consultation takes us to the end of September. To avoid an obvious legal challenge, the Government will need to consider properly the representations received (and there will be many). My bet is that the final version will be October at the earliest (12 October is the 100th day after the election and they will be going very fast to publish by then…). 

Anyone else remember the annual Beaujolais Nouveau races? That used to be how the industry routinely did business development, for better or worse, before we all became amateur journalists. These days its more sober and less fun replacement is the “who can get their NPPF text mark-up up first on LinkedIn” game. But that’s a young person’s sport. I’ll be truffle-hunting instead for the answers to those seven questions. 

Simon Ricketts, 27 July 2024

Personal views, et cetera

Photo by Maja Petric courtesy Unsplash

Labour’s Green Belt Grey Areas/Sadiq Khan’s London Manifesto

For those of us living or working in London, I reckon that Sadiq Khan’s manifesto for his next term as Mayor, published on 19 April 2024, is an important read. But yesterday it was rather drowned out by the media coverage that day of Labour’s press statement on green belt policy reform.

I’ll deal first with Labour’s green belt announcement.

As a country we certainly need to resolve the negative effects of this misunderstood policy concept (Sam Stafford’s updated blog post, The Green Belt. What it is; what it isn’t; and what it should be contains all (more than?) anyone could ever want to know about the subject). And for a sense of the sheer extent of green belt and its obvious consequent throttling effect on the areas it encircles, see for example Town Legal’s planning appeals map – green belt areas marked in … green).

It is surely positive in the context of a continuing, indeed worsening, housing crisis and the lack of other options which are likely to be sufficient and deliverable, that there is talk from Labour of using some green belt land to deliver more new homes. After all, even “going there” is politically brave. But fine words butter no parsnips. And I wonder whether the proposals in some ways just add to the confusion.

These are the core proposals from the press release :

A Labour government would take a brownfield first approach to development across England, prioritising building on previously developed land in all circumstances and taking steps to improve upon the government’s lacklustre record of brownfield build out rates. Areas with enough brownfield land should not release greenbelt.

A Labour government will implement five ‘golden rules’ for Grey Belt development:

1.⁠  ⁠Brownfield first – Within the green belt, any brownfield land must be prioritised for development. 

2.  Grey Belt second – poor-quality and ugly areas of the Green Belt should be clearly prioritised over nature-rich, environmentally valuable land in the green belt. At present, beyond the existing brownfield category the system doesn’t differentiate between them. This category will be distinct to brownfield with a wider definition.

3.⁠ Affordable homes – plans must target at least 50% affordable housing delivery when land is released.

4.⁠ Boost public services and infrastructure – plans must boost public services and local infrastructure, like more school and nursery places, new health centres and GP appointments.

5.⁠ Improve genuine green spaces – Labour rules out building on genuine nature spots and requires plans to include improvements to existing green spaces, making them accessible to the public, with new woodland, parks and playing fields. Plans should meet high environmental standards.”

What can we take from this as to what Labour would actually do, if elected?

This press statement is of course not intended to be picked over by people like me or you. Its purpose is to influence potential voters and to give us all a flavour of we would be likely to see, whilst giving plenty of wriggle-room when it comes to the actual implementation. So I’m not going to carp too much, but…

  • Are these tests for plan-makers or for decision-makers? If the former (likely), will there be a transition period before the new policy kicks in for decision-makers, if there is an otherwise up to date local plan?
  • So a basic hierarchy of brownfield; non-green belt greenfield; brownfield green belt; grey belt green belt; green belt green belt? It strikes me that this gives too much emphasis on the physical characteristics of the site itself rather than its sustainability and appropriateness in spatial terms? And how is this sequential testing to be carried out? The old questions as per the retail and flood risk sequential tests: to what extent can proposals be disaggregated; what is the area of search; deliverable over what period and what about where (as is often the case) there is not really a choice between site A and site B because the level of unmet need is such that A and B are both needed, and more besides?
  • How do references to “poor-quality and ugly” and “nature-rich, environmentally valuable” match up at all to the five traditional purposes for which green belt is designated – (a) to check the unrestricted sprawl of large built-up areas; (b) to prevent neighbouring towns merging into one another; (c) to assist in safeguarding the countryside from encroachment; (d) to preserve the setting and special character of historic towns; and (e) to assist in urban regeneration, by encouraging the recycling of derelict and other urban land. Is that what “poor-quality” means perhaps – not fulfilling those purposes?
  • If “brownfield” equates to what is currently defined as previously developed land, and treated less restrictively in green belt policy, give me an example of this untapped resource of non brownfield “grey belt”? And we’ve all gone on endlessly about the subjectivity of the concept of “beautiful” only now to be faced with a policy concept of “ugly“!
  • 50% is an eye-catching number for some areas but as a target what will actually change in practice? And define “affordable”. Will the opportunity be to introduce these requirements via national development management policies? That would be some exciting and early mission creep!
  • 4 and 5 are nothing new.
  • It’s not all about housing folks! What about logistics and other developments which need to be located in the green belt?

Now to Sadiq Khan’s manifesto, “A Fairer, Safer, Greener London” published ahead of the 2 May 2024 election. I’ll just draw out some quotes:

From his ten pledges:

3  Build 40,000 new council homes by the end of the decade

8  More support for renters – delivering new affordable ‘rent control homes’ and empowering Londoners to take on landlords through a New Deal for Renters

9  Continue world-leading action to tackle air pollution and the climate crisis – from making all buses zero-emission to providing air pollution filters to primary schools

10 Deliver a new London Growth Plan, with a target of creating more than 150,000 good jobs by 2028 and increasing living standards for Londoners

Under the heading “Tackling the housing crisis”:

To unblock more new homes, I will take decisive action where needed to create new Land Assembly Zones and set up more Mayoral Development Corporations to boost overall housing supply and drive regeneration. These will deliver new sustainable communities with homes for first-time buyers as well as homes for social rent. I’ll work with a Labour government to strengthen planning so that the London Plan can go even further in supporting the delivery of the affordable housing our city needs, while unlocking economic growth and being the greenest ever plan for our city.”

Under the heading “Cleaning up London’s air”:

making London the world’s first electric-vehicle ready global city by working with partners to double the amount of electric vehicle charging points installed since 2016 to more than 40,000 by 2030

continuing to oppose any expansion of airports in London

Under the heading “Growing our economy”:

I will build on our city’s economic recovery and set out an exciting new London Growth Plan, developed in close collaboration with councils, businesses and trade unions.

This new growth plan will set out how we can boost jobs and growth in the well-established sectors of our economy, including finance and business services; retail, hospitality, leisure and tourism; manufacturing; logistics; built environment and construction. I will also focus on and champion some of the fastest growing sectors, such as health and life sciences; digital including fintech, retail tech, cyber and AI; creative industries including film, fashion, TV, music and games; climate tech and the energy sector.”

To help boost economic growth across our city, I will support individual boroughs to build on their strengths – from the new global culture and education powerhouse that is East Bank in Stratford, to the world-leading TV and film production cluster in West London, and the internationally influential cutting edge cancer research centre in Sutton. This also means working with councils and businesses to deliver a new vision and plan for the centre of London, ensuring that we can continue to compete with the central activity zones of other global cities like Paris and New York. London has roared back as a tourist destination since the pandemic and I’ll continue to work with partners to improve our tourism offer.”

London is home to more than 600 high streets. We learned during the pandemic how intimately connected we are to local high streets, and their importance to our communities. That’s why I want to do more to protect, restore and improve them. If I’m re-elected, I will launch a support fund and set out a new vision for the future of London’s high streets, building on the work we have already done. I’ll also explore planning changes that can help breathe new life into our high streets, helping to ensure they remain a central feature of our economic and civic life.”

Not a word about green belt, you might note…

Simon Ricketts, 20 April 2024

Personal views, et cetera

GB News, Hertfordshire Edition

Some of the planning bar was all-caps aplenty on LinkedIn this week in relation to a couple of Hertfordshire green belt appeal decisions by the Secretary of State:

Before I discuss these (together with in fact a third one – take a bow David Hardy and team), I thought I would share with you some statistics. I have been looking at DLUHC’s list of called in planning application decisions and recovered appeal decisions to get a feel for the recent pass/fail rate and the extent to which the Secretary of State is departing from inspectors’ recommendations (a feature of two out of three of the recent decisions).

In relation to call in decisions over the last year, the Secretary of State has approved 5 out of 8. In 4 of them (half!) he has reached a different decision to that which the inspector recommended – two approvals against recommendation, two refusals against recommendation (although one of the latter – M&S Oxford Street – is of course back for redetermination).

In relation to recovered appeals, there have been 17 decisions – 10 allowed and 7 dismissed. In 5 of them he has reached a different conclusion to that which the inspector recommended – two allowed against recommendation, three dismissed against recommendation.

I’m not sure what you take from this back of the envelope calculation other than how unpredictable the process is. I feel I need to point again to my 9 February 2024 blog post, The Weighting Game .

Turning to these Hertfordshire green belt decisions…

Tring

This was an appeal against Dacorum Borough Council’s refusal of an application for planning permission for up to 1,400 dwellings (including up to 140 falling within use class C2), a new local centre, sports/community hub, primary school, secondary school and public open space on land bound by Bulbourne Road and Station Road, bisected by Marshcroft Lane, Tring, Hertfordshire. The site is in the green belt and surrounded on three sides by the Chiltern area of outstanding natural beauty. By his decision letter dated 15 March 2024 he disagreed with his inspector’s recommendations and refused planning permission.

The Secretary of State found that Dacorum has a significant housing land supply deficit – its supply stands at just 2.06 years. The inspector gave moderate weight to the provision of recreational and sporting facilities, whereas the Secretary of State gave this limited weight but, other than that, his findings did not materially depart from those of the inspector. However, it all came down to that tricky issue of weight:

In line with paragraph 148 (now 153) of the Framework, the Secretary of State has considered whether the harm to the Green Belt by reason of inappropriateness, and any other harms resulting from the development is clearly outweighed by other considerations. Overall, he considers that the other considerations in this case do not clearly outweigh the harm to the Green Belt and the other identified harms relating to impact on character and appearance, setting of the AONB, harm to designated and non- designated heritage assets and loss of agricultural land. He therefore considers that [very special circumstances] do not exist to justify this development in the Green Belt.”

Chris’ LinkedIn post on the decision is here .

Chiswell Green Lane, St Albans

This was the Secretary of State’s decision letter dated 22 March 2024 in relation to two appeals against refusal by St Albans City and District Council of applications for up to 391 new dwellings, the provision of land for a new school and associated development on land south of Chiswell Green Lane and  for up to 330 discounted affordable homes for key workers, including military personnel, the creation of open space and associated development on land north of Chiswell Green Lane, St. Albans

St Albans’ housing land supply stands at only 1.7 years and its housing delivery test figure stands at 55% (both figures worse at the time of the decision than at the inquiry). Although St Albans’ emerging local plan is still only at regulation 18 stage, the Secretary of State agreed with the inspector that “the Green Belt Review is a material consideration relevant in considering Green Belt matters in the district, and that the relative suitability of strategic sub-area S8 (which both appeal sites fall within), as defined by the Green Belt Review, is an important consideration.” and that the land to be secured for a new school via appeal A should attract significant weight.

In terms of housing:

“The Secretary of State agrees with the Inspector that there is a very substantial need for housing in the district which is persistently going unmet, that the Local Plan housing requirement is hopelessly out of date, and that, using the standard method, the Council can demonstrate just a two-year housing land supply at best. He also notes that the latest HDT has been failed by some margin.  Therefore, the presumption in favour of sustainable development is triggered, in accordance with footnote 8 to paragraph 11(d) of the Framework.

For the reasons given in IR586-591, the Secretary of State agrees with the Inspector that in the context of such a great housing need, very substantial weight should be attached to the proposed housing.”

Compare and contrast with that Tring decision – Dacorum 2.06 years versus St Albans 1.7 years – hmmm, not much in it is there?

“The Secretary of State has considered whether the harm to the Green Belt by reason of inappropriateness, and the other harms he has identified, are clearly outweighed by other considerations. He considers that they are, and therefore very special circumstances exist to justify permitting the development. As such, the proposed development accords with Policy S1 of the St Stephen Parish Neighbourhood Plan 2019-2036 and Policy 1 of the St Albans District Local Plan Review 1994, and national planning policy on Green Belt.”

Charlie’s LinkedIn post is here .

Great Wymondley

This was a decision dated 11 March 2024 taken on behalf of the Secretary of State in relation to an application, which he had called in, for a proposed solar array with associated battery storage containers and ancillary development including means of access and grid connection cable on land at Graveley Lane and to the east of Great Wymondley, Hertfordshire. The inspector recommended that the application be refused but the Secretary of State disagreed and granted planning permission.

The Secretary of State placed significant weight on the contribution that the scheme would have to renewable energy targets, including “the generation of sufficient electricity to meet the requirements of about 31% of the homes in” North Hertfordshire. He disagreed with the inspector’s conclusion that the development would cause serious harm to the setting of the grade 1 listed Wymondley Priory and a nearby grade II* listed nearby tithe barn and with the inspector’s concerns as to the inadequacies of the site selection process carried out.

In summary (although as always do read the full letter):

Weighing against the proposal is harm to the Green Belt which carries substantial weight, harm to heritage which carries great weight and uncertainty about mitigation for displaced Skylarks which carries moderate weight. Further to this, harm is found to the impact on views from Graveley Lane and the Hertfordshire Way which carries considerable weight, to the landscape of the site and its immediate surroundings which carries significant weight and to the effect on landscape character area which carries moderate weight.

The Secretary of State has considered paragraph 208 (formerly paragraph 202) of the Framework. He considers that the public benefits of the proposal do outweigh the less than substantial harm to the designated heritage assets and therefore, in his judgement, the Framework’s heritage balance is favourable to the proposal.

The Secretary of State has considered paragraph 153 (formerly paragraph 148) of the Framework. He considers that the potential harm to the Green Belt by reason of inappropriateness, and any other harm resulting from the proposal, is clearly outweighed by other considerations, and therefore considers that VSCs exist.”

It is so hard to predict outcomes or to establish reliable patterns: three decisions – one allowed in accordance with the inspector’s recommendations, one refused against the inspector’s recommendations and one allowed against the inspector’s recommendations. Rather dispiriting for any inspector, one imagines.

In return for reading this free blog post….

Chris Young is doing a seriously great thing again this year, running the London marathon dressed as a house, for Shelter. Sponsor this qood cause here .

Town Legal partners, staff and their pressganged families are all running, walking, roller-skating etc at least 5km this weekend in aid of XLP, a charity which does life-changing work for disadvantaged young people. I’m checking internally as to whether tapping out 5k words counts but if not I may go walking tomorrow, either in the direction of the Tring appeal site or in the direction of the St Albans one. Or maybe I’ll just head in the direction of my favourite hefty Belties on Blackbird’s Moor. Please help XLP and give me a bit of impetus to keep typing away by sponsoring this good cause here .

Simon Ricketts, 23 March 2024

Personal views et cetera

The Belted Galloways on Boxmoor, Hertfordshire, pic courtesy of the Boxmoor Trust